Upload
jared-owen
View
215
Download
0
Embed Size (px)
Citation preview
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006
Report to the LCLS Facilities Advisory Committee
LCLS Project Management
M. Reichanadter / SLAC
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 2
Outline
Status of the LCLS
Progress in the past six months
Project Management
Cost and Schedule Performance
Contingency Allocation
Organization and Integration
Plans for the next six months
Risks/challenges ahead
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006
LCLS Status•Cost Status
–CF subcontracts substantially over LCLS estimates• Descope CLOC to stay within TPC
•Schedule Status–Technical systems maintaining reasonable schedule progress
• Milestone performance ~OK, but installation activities are behind.–Construction start delayed due to high subcontract bids
• Working new schedule & CP. New Co- and Beneficial milestones.• Construction packages of LCLS beampath now awarded and
construction is underway!• Recent shutdown of Turner activities. Frequent cable discoveries.
•Management Status–Procurements going reasonably well with the dedicated cell
• Consultants (Miller/Dee), expediter and BOA’s are on board–Integration management team in place
• Manage the technical / CF interfaces and facilitate installation
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 4
TEC Project Performance - July 2006
LCLS Project Performance (TEC = $315MAY))
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
AY
K$
BCWS (TEC)
BCWP (TEC)
ACWP (TEC)
BAC
BA
OBL-S (TEC)
EAC
• LCLS showing steady progress overall.
• 31% TEC comp • 28% TPC comp
• SPI = 0.93• CPI = 0.95
• $ burn rate ~$5-6M per/mo
• Labor burn rate ~$2.5M/mo
• At SLAC ~165 FTE’s ~350 heads on LCLS
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 5
LCLS Project Performance – July 2006
• Injector 95% complete in Jan07.
1.1 Project Management 16,428 65.8% 24,958
1.2 Injector 15,810 76.0% 20,795
1.3 Linac 7,912 32.1% 24,677
1.4 Undulator 16,719 40.7% 41,095
1.5 X-ray Transport 8,938 35.2% 25,367
1.6 X-ray Endstations 1,239 8.5% 14,555
1.9 Conventional Facilities 18,741 14.9% 125,793
1 LCLS Total Base Cost 85,786 30.9% 277,240
315,000
37,760
19.7%
2 LCLS Other Project Cost 8,992 15.7% 57,435
64,000
6,565
13.6%
LCLS Total Obligations = $106,483.6K
LCLS Total Project Cost (TPC) 94,778 28.3% 379,000
Total Budget at Completion
% CompleteWork
Accomplished
% Contingency on ETC
LCLS Total Other Project Costs (OPC)
Available Mgmt Reserve
% Mgmt Reserve on ETC
LCLS Cost/Schedule Performance - July 2006 (AYK$)
WBS
LCLS Total Estimated Cost (TEC)
Available Contingency
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 6
TEC Contingency Performance – July 2006
% Contingency AvaIlable (on remaining work)
0%
5%
10%
15%
20%
25%
30%
35%
40%
Oct-04
Dec-04
Feb-05
Apr-05
Jun-05
Aug-05
Oct-05
Dec-05
Feb-06
Apr-06
Jun-06
% CompleteBCWP/BACCont/(BAC-BCWP)
• ~$19M contingency allocated in July.
•~$18M, CF Gp #1•~$0.4M Linac ETC•~$1.2M, XTOD ETC•~$0.2M, XES ETC
• All ETC’s updated except CT & CF.
• Aug Pending BCR’s;•CF ETC•CT ETC•Bid Group #2
• CLOC to be descoped to maintain adequate contingency.
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 7
Major Schedule Variances
Linac System: SPI = 0.72, CPI = 1.09 Linac (and Injector) controls hardware current installation. Work behind schedule but recovering. Linac Controls work, RF waveguides and vacuum hardware for 2007 installation being deferred to support immediate needs.
Undulator System: SPI = 0.85, CPI = 0.92Single Undulator Test (SUT) system development at ANL developed into a larger test than anticipated. SUT is nearing completion. SLAC’s Magnetic Measurement Facility (MMF) is not yet prepared for undulator segment tuning. The Undulator alignment monitoring HLS behind on hardware procurements. Increased SLAC-LCLS oversight to recover schedule.
XES Controls System: SPI = 0.72, CPI = 1.07XES controls effort has been focused on preparations for Injector installation and commissioning period. Replan future XES controls work.
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 8
Schedule StatusOld Schedule – Critical Path (CP) - Und B.O. – install – FEL commission. Total float 213d to CD-4.
Near CP – Undulator vacuum system, Undulator testing,
New Schedule – Updating project schedule and CP with Turner BO milestones.
Provides “Co-occupancy” Target dates allow installation prior to BO.Estimate ~60 days loss of float resulting from evaluation of bids, additional value engineering effort and possible options.
Near-term L3 milestone performance6/2/06 – 1st Article Undulator 1 Rcvd @ SLAC. Done – 6/12/067/10/06 – Award CF subcontracts
Done, Group #1 packages out, Group #2 ~ready, NTP to Turner on Aug 17/28/06 – MMF Qualified & Ready to Measure Prod Undulators
~Aug 28. Benches are installed and measuring the first magnets.8/21/06 – FY06 Shutdown: HW Reqd for Installation
Aug 16 Conducted Hardware Installation Readiness ReviewAug 30 Conducted Controls Installation Readiness Review
11/15/06 – Start Drive Laser Commissioning. On schedule
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 9
LCLS Organization Chart
• Strengthened Senior Mgmt
•APD-C•APD-E (TBD)•IMT
• Procurement•Miller•Dee
• Conv. Fac.•Turner•Jacobs T3
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 10
LCLS Integration - IMT addresses the “5I’s”
LCLS establishes IMTIMT under direction of RM BoyceDescribed under PMD 1.1-028
Integration management (gaps/conflicts)Review and ownership of Interfaces (ICD’s)CF-Tech leads identified for constructionInstallation readiness & planning
Aug06 shutdown underway
APD Engineer – To facilitate LCLS system engineering and inter-lab integration
Interview process completeLCLS Design Reviews - ~35-40 have been conducted across the project to mature the design, validate progress and identify integration issues early.
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 11
LCLS design continues to mature
LCLS Specs
• 77% PRD’s • 65% ESD’s • Most open
requirements are in photon area. Need to do better.
• 100% RDS’s• 92% ICD’s• IMT reviews ICD’s
Requirements Document
Total No.
Documents
Number
Approved
Number in Sign-Off
% Complete
Comments
Global Requirements Document (GRD)
1
1
0
100
Complete
Physics Requirements Documents (PRDs)
79
61
0
77
Engineering Specification Documents (ESDs) Management Physics Liaison Support Controls Injector Linac Undulator X-R Endstations Conventional Facilities XTOD
126
3 3
16 32 13 17 15 10 17
82
3 3
14 31 11 9 0
10 1
0
0 0 0 0 0 0 0 0 0
65
100 100 87 97 85 53 0
100 6
Room Data Sheets (RDSs)
51
51
0
100
Complete
Interface Control Documents (ICDs) Injector Linac Undulator X-R TOD XES
12
3 4 1 2 2
11
3 4 1 2 1
0
0 0 0 0 0
92
100 100 100 100 50
Total
269
206
0
~76
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 12
LCLS Risk Registry
Risk registry has been modified to provide a more tactical plan (FAC recommendation)
System Managers identify and ‘own’ riskImproves consistency on risk characterization
SM’s have authority and resources to prioritize risks.
Risks reviewed each month at senior mgmt meeting
Bulleted tasks identified to reduce riskStatus punch list each month
Avoid the broad, non-actionable risks
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 13
Near-Term Project ObjectivesProject Management
Hire APD-EngineeringEmphasize the IMT in resolving integration issues
Cost ManagementComplete ETC’s and ensure remaining scope fits LCLS TPC
Schedule ManagementComplete Injector / Linac shutdown effort safely
Injector (RF Gun – BC1)
Conduct Injector ARR and begin laser/injector commissioningDeliver 50% of undulators to MMF ~ Dec06
Monitor MMF measurement throughput
Perform on civil construction, safe operations are a must to stay to cost/schedule.
Mark Reichanadter
LCLS FAC Meeting [email protected]
October 12-13, 2006 14
Risks / Challenges AheadExecution Phase – Safety is primary concern
Fully staffed in ES&H, construction safety and oversight (UTR’s)Regular job site inspections, enforced proceduresAligned DOE, SLAC, Turner, Subcontractor team
Technical / Quality – Missing scope/gaps are a riskScrutinize ICD’s, LCLS / LUSI interface needs attentionImprove technical specs, continue emphasis on design reviewsEmphasize role and influence of IMT and APD-E
Schedule - Installation activities and coordination IMT to facilitate installation planningNeed to get APD-E on board
Cost - Site conditions, field orders and staying to scheduleCLOC descoped to maintain adequate contingencyRecent bottoms-up ETC for the projectStrong procurement and negotiating team in place