49
Hamid Shoaee LCLS Facility Advisory Committee [email protected] October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS Controls Group Outline Goals & Commissioning Schedule Injector Control System Installation Responses to FAC Concerns Status update Summary

Hamid Shoaee LCLS Facility Advisory Committee [email protected] October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

  • View
    213

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 20061

Control System OverviewOctober 12, 2006

Hamid Shoaeefor the

LCLS Controls Group

OutlineGoals & Commissioning Schedule Injector Control System InstallationResponses to FAC ConcernsStatus updateSummary

Page 2: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 20062

The focus in the past six months has been timely installation of the injector Controls

Complete the design of critical systems and follow through with system productionAccelerate procurement activities to ensure availability for installationAlign cable plant design and procurement with the project-wide installation scheduleCollaborate with the physicists to ensure the availability of required software tools for machine commissioning

Page 3: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 20063

LCLS Electron Commissioning Schedule

July 24July 24 S20 ready for laser installationS20 ready for laser installationAug 29Aug 29 Laser installation completeLaser installation completeDec 18Dec 18 Virtual cathode fully characterized (ready to install gun)Virtual cathode fully characterized (ready to install gun)Dec 19Dec 19 RF gun installation starts (10 days) + pre-beam checkoutRF gun installation starts (10 days) + pre-beam checkoutDec 18-Jan 1Dec 18-Jan 1 HolidaysHolidaysJan 2Jan 2 VVS’s switched on (RF power available)VVS’s switched on (RF power available)Jan 12Jan 12 First laser UV-light on cathodeFirst laser UV-light on cathodeJan 12-Feb 4Jan 12-Feb 4 Electron commissioning in GTL and gun-spectrometer onlyElectron commissioning in GTL and gun-spectrometer onlyJan 12-Feb 4Jan 12-Feb 4 RF processing L0a, L0b, Tcav (and gun: already processed)RF processing L0a, L0b, Tcav (and gun: already processed)Feb 4Feb 4 Latest start for L1 and X-band processing (assumed 15 days)Latest start for L1 and X-band processing (assumed 15 days)Feb 5Feb 5 Beam into L0a, L0b and down to SAB – Beam into L0a, L0b and down to SAB – L0a,b proc. completeL0a,b proc. completeFeb 20Feb 20 Beam into L1 linac (to TD11 dump) - Beam into L1 linac (to TD11 dump) - L1, X-band proc. completeL1, X-band proc. complete~June~June Take beam down full linac (to BSY SL2 stopper)Take beam down full linac (to BSY SL2 stopper)

From P. Emma

Page 4: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 20064

LCLS Accelerator and Compressor Schematic

SLAC linac tunnelSLAC linac tunnel research yardresearch yard

Linac-0Linac-0L L =6 m=6 m

Linac-1Linac-1L L 9 m9 m

rf rf 25°25°

Linac-2Linac-2L L 330 m330 mrf rf 41°41°

Linac-3Linac-3L L 550 m550 mrf rf 0° 0°

BC1BC1L L 6 m6 m

RR5656 39 mm39 mm

BC2BC2L L 22 m22 m

RR5656 25 mm25 mm DL2 DL2 L L =275 m=275 mRR56 56 0 0

DL1DL1L L 12 m12 mRR56 56 0 0

undulatorundulatorL L =130 m=130 m

6 MeV6 MeVz z 0.83 mm 0.83 mm 0.05 %0.05 %

135 MeV135 MeVz z 0.83 mm 0.83 mm 0.10 %0.10 %

250 MeV250 MeVz z 0.19 mm 0.19 mm 1.6 %1.6 %

4.30 GeV4.30 GeVz z 0.022 mm 0.022 mm 0.71 %0.71 %

13.6 GeV13.6 GeVz z 0.022 mm 0.022 mm 0.01 %0.01 %

Linac-Linac-XXL L =0.6 m=0.6 mrfrf= =

21-1b,c,d

...existinglinac

L0-a,b

rfrfgungun

21-3b24-6dX

25-1a30-8c

Commission in Jan. 2007Commission in Jan. 2007 Commission in Jan. 2008Commission in Jan. 2008

From P. Emma

Page 5: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 20065

Pre-Beam Checkouts

Vault/Linac CheckoutsPower on access: Check polarity of magnets Read-backs , Motion controller: Exercise motion-control YAG/OTR camera images: Use Alignment laser to define screen center

Pre-Beam preparation Laser stabilization system Fiducializing of real cathode location w.r.t virtual cathode LLRF for Gun, L0a, L0b (Volt. feedback, Phase Lock) Start conditioning (Gun, L0a, L0b) if PPS ready

Dark current measurement if FC1 ready Vacuum pumps and gauges reading available

Feedback loops for gun temperature stabilization

Page 6: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 20066

Injector Control System Installation Plan

Controls installation has taken place in several stages including:

Design, procurement and installation of the cable plant including trays, long haul DC and I&C cables, terminations, etc.

Phase 1 (Apr. ’06 thru Jun. ’06)Phase II (Aug. ’06 thru Dec. ’06)

Procurement, preparation and installation of the electronics racks.

Installation of electronics chassis, modules, and intra-rack wiring

Installation of the Controls software on the production servers

Page 7: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 20067

Phase I Cable including Laser Room & LIT-01 Rack

-Terminate Cables

Phase II Cable Plant

-Install Trays, Cable

-Terminate Cable

..to BC1 Area

Page 8: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 20068

Phase II Installation Scope - Gun to TD11

Page 9: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 20069

Linac/ BC1 Housing Area

Page 10: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200610

Phase I Cable/Tray was successfully completed

Page 11: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200611

Cable Plant Phase II, Racks, Crates, etc.

Phase II cable plant has been successfully designed and documented

Davis-Bacon contract has been awarded.

The procurement and installation is currently in progress

All electronics racks have been received and installed in the field

Page 12: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200612

PS Racks B024 Assembly Area

Page 13: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200613

Vacuum Controls Racks in Sector 20

Most equipment has been installed in racks in Sector 20

All long haul cables installed and most connectors installed

Remaining work: PLC programming and EPICS databases – in progress

Page 14: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200614

PPS/LSS Rack Field Installation

PPS/Laser Safety System (LSS) Field Installation (S20)

LSS active for Laser room.

PPS installation in process

CertificationDecember 18-24

Page 15: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200615

Installation details will be presented in the breakout session

With a few exceptions the procurement of control components has been completedWhile the majority of subsystems will be installed on time, a few will be just in time delivery, including BPMs and Toroids electronics.Systems are typically checked out on test stands, and field installation will be done by Davis-Bacon contractors.

Page 16: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200616

MCC, Networks, Servers, & Workstations

Production Systems DeliveredNetworks at S20 RF Hut & MCC: physical and wireless

LCLSDMZ, LCLS private, wirelessMCC infrastructure built: power & racksFirst group of LINUX RHEL4 Servers:

2 applications, 2 EPICS archiver

Control Room Linux Workstation – 4 (24-inch) monitor & 2 monitor configurations

Control Room StationsS20 Laser Room is actively in use to commission laserMain Control Center (MCC) Control Room space is allocated, installing 3 Workstations & laptop work areasMCC Foyer: space for SUNray & laptop work areas

Page 17: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS
Page 18: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200618

Control Room Infrastructure

Working on applications and migrating to production environments.Error LogsArtemis LCLS area existsOperations and Physics E-logs createdCyber Security Protection Program (CSPP) Update Completed – MCC enclave included LCLS accelerator controlsAIP network upgrade at MCC for gigabit traffic to support digital control room

Page 19: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200619

FAC Response 1 – MPS

The controls group made the wise decision to extend the 1553 MPS system for the injector turn-on and will later continue development of the newer MPS system (which is needed to respond in 1 pulse rather than the 3 pulse response time of the 1553 MPS system). An update on MPS progress should be presented at the next FAC meeting. In addition to implementing the 1553 system, further work should be done on the new system.

There will be a presentation on the MPS in the breakout session.

Work has been done on the design of the linac MPS and a design review will be held in November

Page 20: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200620

FAC Response 2 – BPM

They still have a tight schedule. There has been progress since the last review, but no decision has been taken on which digitizer to use yet. This decision should be taken very soon.

The schedule is still very tight. However we have selected a digitizer and the details will be presented at the breakout session

Page 21: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200621

FAC Response 3 – Cost, Schedule, cable plant concerns

Management has changed. [Hamid] has made some changes and does think they can support an on time injector commissioning with some temporary solutions. We agree with the latter statement and believe the schedule will be very tight. Particular attention is needed for the cables in the linac which must be installed in the coming shutdown. We support Hamid’s plan to rework the schedule and cost estimates.

Linac Cable plant installation is proceeding well and will be completed during the shutdown.

There has been a bottom up cost estimate of the control system

Page 22: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200622

FAC Response 4 – Use of commercial solutions

It seems like now there is less emphasis on using COTS solutions. Increase that emphasis please. For example the plan has been to use a commercial card for the timing system, but now they are thinking of getting rights to the design and modifying it to remove unused functionality and reduce cost. We highly doubt this would be worth the engineering effort.

All timing system electronics have been procured from the manufacturer. There are no plans to produce them locally.

With a few exceptions, most of the controls electronics consist of commercial boards: exceptions include BPM & Toroid AFE, LLRF.

Page 23: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200623

FAC Response 5 – Embedded IOC

Different groups may be using different embedded IOCs. See if they can be standardized. Don’t do this if it is so late in the development cycle that the change would be highly disruptive.

A single embedded IOC board is being used on a number of systems including BPM, Toroid, BLM, LLRF

Page 24: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200624

FAC Response 6 – Management

Controls would benefit from a full time deputy and designated technical leads for each technical area. The latter would be people who spend 25% of their time on management and do technical work the rest of the time.

The recently revised controls budget includes a deputy position which will be posted shortly.

Page 25: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200625

Update April 2006 – October 2006 (1)

Long Haul cable plant design is complete and reviewed. Installation is in progress.

Magnet Controls & PS HW & SW StatusFinal Design Review conducted successfully6 new racks Installed in Sector 20: Sep 24, 2006

EPICS Software Almost all functionality is implemented and tested

SLC-aware magnet control and monitor - done

provides interface between magnet devices and the legacy control system

System Integration on Nov 10, 2006

Page 26: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200626

Magnet Control Display

Page 27: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200627

Update April 2006 – October 2006Safety Systems

PPSLCLS Injector PPS Reviews are CompleteRSC ‘conditional approval’ obtainedHardware drawings, wiring diagrams are complete; installation in progress

BCSPrevents radiation from ‘escaping’ the shielding enclosureDirect measurements of radiation or beam lossProtection of safety-critical collimators and stoppers Hardware is nearing readiness for installationOriginal ‘Mode-switching’ BCS proposal has been sidelined for nowPropose an ‘Interim BCS’ where conservatively “All BCS faults shut-off all Guns.”

Page 28: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200628

Update April 2006 – October 2006Safety Systems

Interim MPS Using existing linac infrastructure (1553 MPS)Adding new signals and devicesInterim MPS will be used for gating beam

Single Shot ModeBurst Mode

MPS algorithm is responsible for both LCLS and CID beamPockels cell and MPS mechanical shutter limit laser rate on cathodeHardware procurement is almost complete and installation will be completed in early December

Page 29: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200629

The injector laser stabilization system includes two feedback loops

The first loop includes two mirrors, each with two actuators and one camera. It stabilizes laser traveling through a 10-meter tubeThe second loop includes one mirror with two actuators and adjusts the laser position on the cathode.

The IOC reads the image from camera, calculates the laser’s position error and applies a correction to the actuators.The loop operates @ 1 Hz, and the camera is synced to 120Hz.

The prototype of the first loop has been tested for several months and works well.

Injection Laser Control System

Page 30: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200630

The first loop

Actuator A1

Camera A

Laser

Actuator A2

Actuator B1

Actuator B2

Camera B

Spiricon

Page 31: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200631

Motion: Newport XPSC8 Motion Controller

Pentium 4 PC basedvxWorks poweredSupport up to eight motorsEthernet control interfaceDigital I/O and analog I/O built-in

Page 32: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200632

Image Acquisition

PULNiX TM-6710CL cameraCCD: 1/2”

Shutter: Full Frame

UV option: Yes

Resolution: 648x484

Progressive: Yes

External Trigger: Yes

Full scan: 120Hz

Analog Output: Yes

Cameralink: Yes

EDT PMC DV C-LinkCameralink compatible32bit/66MHz PCI

Page 33: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200633

Snapshot

EDM screen of two cameras

Page 34: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200634

OTR/YAG systemsWe have a total of 21 OTR/YAGs of which 14 are needed for commissioning

The equipment consists ofUniqVision UP900CL-12B camera

EDT PMC Cameralink® interface

EDT RCX Cameralink®/Fiber converter

Profile Monitor Controller is built in SLAC to handle pneumatic, filter, lens and bulbs

Acromag Digital I/O module IP445/440 are used in IOC to interface with Profile Monitor Controller.

Page 35: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200635

Toroid/Faraday Cup

We have a total 14 Toroids and 2 Faraday cups of which 6 Toroids and 2 Faraday cups are needed for commissioning

Beam Charge Monitor Chassis is built in SLAC to handle signal conditioning, integration and MPS interface.

Acromag IP330 ADC is used in IOC to interface with Beam Charge Monitor Chassis. Since the existing EPICS driver did not match our requirement, a brand new driver developed.

4-Channel fast ADC is built at SLAC to image dark current for FC01, FCG1 and IM01, IM02(optional).

Page 36: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200636

Bunch Length Monitor

There are 2 Bunch Length Monitors needed for commissioning

BL11, BL12

The amplifier is built in SLAC to handle signal conditioning.

4-Channel fast ADC is built in SLAC to read the signal.

A Solenoid Controller is built in SLAC to handle filters and pneumatic actuators.

Acromag Digital I/O module IP445/440 are used in IOC to interface with Solenoid Controller.

Page 37: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200637

Wire Scanner Detector Locations

7 Wire Scanners for Injection CommissioningHardware Assembled, Tested (without beam), Calibrated, and currently being installedSoftware is 80% completeRequire further testing of PMTs and Ion Chambers for acquisition of Wire data

Page 38: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200638

Injection Wire Scanners after Assembly

Page 39: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200639

Wire Scanner Operator Displays

Scanner ControlOptions

Page 40: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200640

LLRF Distribution Schedule

Racks to be installed in RF Hut – next week

RF Cables (On-site) to be pulled – mid October

RF Chassis – 50% complete10 more chassis required for turn on, to be installed by December

Remainder by March 2007

Testing of RF distribution system - DecemberPhase measurements of cables / looped

Ready for turn-on – Mid December

Page 41: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200641

LLRF Distribution Scope of Work – Injector Turn-on

Sector 20 RF distribution systemPhase and Amplitude Controllers (PACs) – 5 unitsPhase and Amplitude Detectors (PAD) – 2 unitsPhased Locked Oscillator – Use SPPS unit for Turn OnLO Generator – Complete - 50% tested – looks good so farMultiplier – 476MHz to 2856MHz – Complete 75% Tested4 distribution chassis – Complete 102MHz, 2056MHz, 2830.5MHzLaser Phase Measurement – in Design, diagnostic, not required for turn on – Laser group wants it next week. Distribution Amplifiers – 10W, 2850MHz due Oct 25, 102MHz Amp being built

LLRF Control and Monitor System1 kW Solid State S-Band Amplifiers – 5 units – Design Complete, In FabPAD – 12 units – 6 required for turn on PAC – 6 unitsBunch Length Monitor Interface – awaiting Specs

Beam Phase CavityWill use single channel of PAD ChassisPill box cavity with 2 probes and 4 tuners – 2805MHz 3 units Complete

Page 42: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200642

High Level Applications

Through interactions with LCLS physicists we have tried to identify the required software for injector commissioning

Prio

rity

Injector Devices to be Scanned by

Correlation Plots

1 Magnet settings (BDES) XCOR, YCOR,

SOLN, QUAD, BEND, BTRM, LGPS

1 RF phase settings (PDES?) for gun, L0a,

L0b, L1, Lx, and TCAV0

1 RF amplitude settings (VDES?) for gun,

L0a, L0b, L1, Lx, and TCAV0

1 Drive-laser x, y pointing on cathode (or

feedback set-point)?

2 BC1 chicane-mover setting

2 BC1 collimator (CE11) jaw settings

Page 43: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200643

High Level Applications

Required high level applications softwareCorrelation PlotsBuffered AcquisitionOrbit Applications MultiknobImage ManagementEmittance, Slice Emittance, Beta MatchingEnergy Spread and Slice Energy SpreadBunch Length MeasurementOn-line model Configuration management

Page 44: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200644

Many application are available from the legacy control system

Page 45: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200645

Applications provided by the SCP

A large suite of applications are available from the SLC control program including correlations plot, orbit control, modeling, etc.

The SLC-aware IOC provides beam synchronous data to Buffered Acquisition and Correlation Plots from a number of sources including

BPM, BLEN, PMT, LLRF, Faraday Cups, Toroids, some Laser devices

Page 46: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Applications provided in MATLABImage ManagementBunch Length MeasurementEmittance and Energy Application

Page 47: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200647

Next Six MonthsLinac MPS designCable plantPS procurementLinac BPMXESLUSI

Page 48: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200648

Breakout Session 4 – CONTROLSLocation – Redwood C, Bldg 48

11:30am Controls Organization Overview H. Shoaee12:00pm Injector/Linac Controls Installation R. Fuller12:30 Lunch (FAC members only) 1:30pm High-Level Applications & Feedback D. Fairley 2:00pm Timing Systems Update P. Krejcik 2:30pm PLC-based PPS M. Saleski 3:00pm BPM Update S. Smith 3:30pm Break 4:00pm Machine Protection System S. Norum

Page 49: Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu October 2006 1 Control System Overview October 12, 2006 Hamid Shoaee for the LCLS

Hamid Shoaee

LCLS Facility Advisory Committee [email protected]

October 200649

ConclusionsGreat progress has been made in the past six months towards readiness for injector installationWhile the majority of Controls subsystems will be installed on time, a few will be just in time deliveryAn ETC exercise has identified and fixed a number shortcomings in the baseline budgetThe collaboration with other departments at SLAC has proven very productiveWhile commissioning the injector, we need to be aware of the installation schedule for the rest of the machine including the experimental areasThrough collaboration with the physics group are ensuring the availability of required applications software for injector commissioning.