Upload
frank-cameron
View
215
Download
2
Embed Size (px)
Citation preview
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 20081
LCLSLCLS Overview Overview
December 2, 2008December 2, 2008
Project Construction StatusProject Construction StatusLCLS Operations OrganizationLCLS Operations OrganizationCommissioning/Transit to Commissioning/Transit to operationsoperations
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 20082
Linac Coherent Light Source at Linac Coherent Light Source at SLACSLAC
Injector (35Injector (35ºº))at 2-km pointat 2-km point
Existing 1/3 Linac (1 km)Existing 1/3 Linac (1 km)(with modifications)(with modifications)
Far ExperimentFar ExperimentHall (underground)Hall (underground)
Near Experiment Hall Near Experiment Hall (underground)(underground)
New New ee Transfer Line (340 m) Transfer Line (340 m)
X-ray X-ray Transport Transport Line (200 m)Line (200 m)
Undulator (130 m)Undulator (130 m)
X-Ray Transport/Optics/Diagnostics
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 20083
Table 2; Linac Coherent Light Source Re-Baselined Funding Profile ($M)
FY02 FY03 FY04 FY051 FY06 FY072 FY08 FY09 FY10 Total TEC 0 5.93 7.46 49.67 84.69 101.16 51.35 36.50 15.24 352.00 OPC 1.50 0 2.00 4.00 3.50 13.00 15.50 17.00 11.50 68.00 TPC 1.50 5.93 9.46 53.67 88.19 114.16 66.85 53.50 26.74 420.00 1 FY2005 TEC funding includes $29,760,000 for long lead procurements. 2 FY07 TPC funding reflects the ~$8M reduction as a result of the FY2007 CR and directed change.
Construction(TEC)>87% complete
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 20084
LCLSLCLS Injector Injector
100% Complete100% Complete LCLSLCLS Linac Linac
>96% Complete>96% Complete
Commissioning Complete Commissioning Complete
3/20083/2008
Commissioning Complete 9/2007Commissioning Complete 9/2007
Undulator>97% complete
Beam to theDump by 12/19
ARRARR
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 20085
Linac-to-Undulator (227m)
X-rayTransport(200m)
UndulatorHall (175m)Beam Dump (40M)
Front End (29m)
NearExpt’l.Hall
Near Experimental Hall
1.9 Conventional Facilities >87% complete Turner Construction Co. >95% complete
FarExpt’l.
Hall
64.6 m
14 m
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 20086
Re-establishRe-establishee to SL2 to SL2
LTU/LTU/UndUnd
Comm. Comm.
Firs
t Li
ght
in
Firs
t Li
ght
in
FEE
FEE
Firs
t Li
ght
in F
EH
Firs
t Li
ght
in F
EH
NEH Ops & NEH Ops & CommissioningCommissioning
JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS OOOO NNNN DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJOONNAA
2008 2009 20102008 2009 2010 2008 2009 20102008 2009 2010DownDownPPS
PPS
Linac/BC2 Linac/BC2 CommissioninCommissionin
g g FEL/FEEFEL/FEECommissioniCommissioni
ng ng Nov. 3, 2008Nov. 3, 2008
Inst
all
Inst
all U
ndula
tors
Undula
tors
MMDD
LCLSLCLS Installation and Commissioning Time-Line Installation and Commissioning Time-Line
LTU
/Und
In
stall
LTU
/Und
In
stall
PEP-I
I ru
n
PEP-I
I ru
n
ends
ends
FEE/N
EH
In
stall
FEE/N
EH
In
stall
PPS C
ert
. LT
U/D
um
pPPS C
ert
. LT
U/D
um
p
CD-4
CD-4
(7
/31
/201
0)
(7/3
1/2
01
0)
X-R
ays
in N
EH
X-R
ays
in N
EH
no
wn
ow
DDDown?Down?
FEH
Hutc
h B
OFE
H H
utc
h B
O
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 20087
PROJECT SAFETY EXPERIENCEThrough October 2008
Total Project Hours2,045 M Hours worked
SubContractors579 K Hours workedDART Rate 3.1 (9 Incidents)
TRC Rate 4.1 (3 Incidents)
LCLS Collaboration 1,466 K Hours worked DART Rate 0.27 (2 Incidents)
3.23.1
0.31
0
0.5
1
1.5
2
2.5
3
3.5 ConstructionIndustry
LCLSContractors
LCLSCollaboration
Total Project
DART Rate
Injury rates based on 200 K hours (100 man years) of effort. DOE/SC Goal is a Reportable Case (TRC) rate of < 0.25 and a Days Away, Restricted, or Transferred (DART) rate < 0.65 per 100 FTEs.
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 20088
LCLS ConstructionProject Organization
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 20089
LCLS Project Now Incorporated in theLCLS Directorate Organization
LCLS Directorate
Define and deliver the transformational potential of Ultrafast photon science through efficient
and effective operation of the Linac Coherent Light Source as a BES User facility
Business Office
Deliver the enabling Infrastructure necessary for efficient operation
of LCLS
Accelerator Systems Division
Deliver the LCLS quality beam in a sustainable and efficient manner that meets the
needs of the user program
Engineering Physics Division
Deliver the approach, resources, and standards, to optimize the configuration of LCLS in a reliable,
available, and maintainable manner
Experimental Facilities Division
Deliver the instrument systems and user administration activities necessary for efficient
performance of a user based research program
Strategic Projects Division
Deliver the planning and implementation of next generation upgrades and major
modifications of LCLS
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 200810
Staff assigned on matrix basis from other organizational elements of LCLS and SLACLCLS Project Management Roles/Responsibilities continue through commissioning process
Strategic Lab Infrastruct. Project G. Herman/J. Albino
Future Projects
LCLS Strategic Projects Division J. Galayda
LCLS Project J. Galayda
LUSI Project Tom Fornek
PULSE Center Project
Dave Rich
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 200811
Organizational Responsibilities
Dave Schultz has taken on these Project Responsibilities for Electron Beam Systems
Fully integrated with existing SLAC accelerator operations/maintenance systems in design and handover
Safety Assessment Document
Now incorporated in SLAC SADs
Readiness Process
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 200812
Organizational Responsibilities
Accelerator Systems DivisionAccommodate/control the interaction between LCLS Project activities and accelerator operationsIncorporate new LCLS Systems into existing SLAC operations & work control
Area management responsibilities for newly constructed facilitiesConfiguration controlEnforce requirements for beam authorization
Support LCLS Commissioning Team activities
Limits on ASD authority to produce beam are specified in the Beam Authorization SheetKey upper limits on electron-beam power/energy operation are set by Radiation Safety Officer for each run
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 200813
Organizational Responsibilities
LCLS Project Commissioning TeamPaul Emma leading for Electron Beam Systems
Paul’s group now has Engineering/Physics Division (EPD) as its administrative/operations home
Plans technical/physics aspects of LCLS commissioningFulfill CD-4 performance requirementsAccountable to Project for achievement of commissioning goals
Post-commissioning, Paul’s group supports LCLS Directorate goals as part of EPD
Support LCLS Experiment Program, expand/improve performance of the FEL
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 200814
LCLS LTU/Undulator/FEL Commissioning Goals Sep. 29, 2008
The third phase of LCLS commissioning (LTU/Undulator/FEL) will begin in November 2008, from gun through the final electron dump after the FEL undulator. The goals of this Phase-III commissioning cycle are outlined in the points below:
1) Full linac operations (drive-laser, gun, injector, BC1, BC2, and main linac) will be re-established to the 52-SL2 stopper in the BSY during the first 1 month of Phase-III commissioning (see previous injector and BC2/Linac goals).
2) The electron bunch will be transported to the main electron beam dump, through the FEL undulator, at up to 13.6 GeV with at least 200 pC of charge and minimal beam loss at a repetition rate of at least 10 Hz.
3) All relevant new electron beamline components (magnets, BPMs, screens, toroids, wire-scanners, RF-structures, dumps) will be operationally verified (with beam) in terms of polarity, calibration, function, timing, reasonable alignment, and motion-control, where relevant. Basic control system functionality will be validated simultaneously and as a consequence of this verification process.
4) All relevant new FEE photon beamline components (mirrors, imagers, collimators, attenuators, gas-detectors, thermal sensor, etc) will be operationally verified (with x-rays) in terms of polarity, calibration, function, timing, reasonable alignment, and motion-control, where relevant. Basic control system functionality will be validated simultaneously and as a consequence of this verification process
5) All machine protection (MPS) and beam containment systems (BCS) will be operationally verified early in the commissioning cycle to ensure safe operation for both personnel and hardware. PPS checkout is not part of commissioning.
6) The electron bunch will be characterized, and tuning sensitivities demonstrated, with regard to energy, energy spread, trajectory, charge, emittance, beta function, bunch length, and centroid coordinate stability in all six dimensions.
7) The undulator beam-based alignment (BBA) procedure has been successfully performed with the undulator segments all rolled in and all rolled out.
8) The undulator x-ray radiation will also be characterized, and tuning sensitivities demonstrated, with regard to wavelength, bandwidth, pointing, x-ray power, transverse size, and centroid coordinate stability in five dimensions (x-ray timing diagnostics will not be available at this time).
9) An x-ray flux of at least 106 photons/mm2 per pulse in a 0.1% bandwidth at 8 keV will be measured in the FEE.
Technical goals for activities addressed by this Readiness Review
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 200815
SolidAttenuator
Gas Attenuator
Slit
Start of Experimental
Hutches
5 mm collimator
Muon Shield
Hard X-Ray Offset mirror
system
PulseEnergyThermal Detector
Gas Detector
Gas Detector
e-
Direct Imager
Hard x-ray Monochromator (K Spectrometer)
Soft X-Ray Offset mirror
system
LLNLLLNL
WBS 1.5 is >80% complete
Front end X-ray optics being assembled
All mirrors delivered; mirror figures meet spec
Most diagnostics under assembly at LLNL
X-Ray Transport/Optics/Diagnostics
First use~3/2009
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 200816
Near Experiment Hall Hutch 3
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 200817
Find out what will be
Schematic of AMO Instrument
•Build/buy and assemble – Jul-Dec 2008•Assembly & Testing – Feb-Jun 2009•Ready for first light – Jul 2009
July 2010
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 200818
Installing re-bar in the Far Experimental Hall
John N. Galayda
LCLS Accelerator Readiness Review [email protected]
December 2, 200820
Presentation MaterialsThanks to:SLAC ANL LLNLJess Albino Geoffrey Pile Richard BiontaJohn Arthur Bill Berg Donn McMahon Paul Emma Marion WhiteTom FornekDavid SaenzDavid Schultz
End ofPresentation