35
John N. Galayda LCLS Facility Advisory Committee [email protected] 27 October 2005 Linac Coherent Light Source Project Update •Recent progress •Enhancements of capability •Conventional facilities cost

John N. Galayda LCLS Facility Advisory Committee [email protected] 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

  • View
    214

  • Download
    1

Embed Size (px)

Citation preview

Page 1: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Linac Coherent Light Source Project Update

•Recent progress

•Enhancements of capability

•Conventional facilities cost

Page 2: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Linac Coherent Light Source

1.1 Management, Global Controls

1.2 Injector1.2 Injector1.3 Linac

1.3 e-BeamTransport

1.4 Undulator

Near Experiment Hall

FarExperimentHall (underground)

1.5 X-Ray Transport/Optics/Diagnostics1.6 Endstation Systems

1.9 Conventional Facilities

Page 3: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

1.1 Project Management 8,880 8,375 8,648 -505 -273 0.94 0.97 28,970 28,970 0

1.2 Injector 7,113 6,163 6,096 -951 67 0.87 1.01 19,297 19,297 0

1.3 Linac 3,122 3,049 2,520 -73 529 0.98 1.21 26,431 26,431 0

1.4 Undulator 8,912 6,244 6,206 -2,668 39 0.70 1.01 50,724 50,724 0

1.5 X-ray Transport 4,356 4,225 4,102 -131 123 0.97 1.03 27,127 27,127 0

1.6 X-ray Endstations 721 721 680 0 41 1.00 1.06 14,779 14,779 0

1.9 Conventional Facilities 4,813 4,828 5,394 15 -567 1.00 0.89 80,649 80,649 0

1 LCLS Total Base Cost 37,917 33,604 33,646 -4,313 -42 0.89 1.00 247,976 247,976 0

315,000 315,000

67,024 67,024

31.3% 31.3%

13.6% 13.6%

2.1 LCLS Project Mgmt, Planning & Admn (OPC) 4,437 4,538 4,345 101 193 1.02 1.04 33,021 33,021 0

2.2 Injector (OPC) 699 757 578 58 179 1.08 1.31 6,107 6,107 0

2.3 Linac (OPC) 1 1 1 0 0 1.05 1.00 2,545 2,545 0

2.4 Undulator (OPC) 742 689 776 -53 -86 0.93 0.89 5,873 5,873 0

2.5 X-ray Transport (OPC) 480 412 339 -68 73 0.86 1.22 4,015 4,015 0

2.6 X-ray Endstations (OPC) 165 137 98 -28 39 0.83 1.39 5,200 5,200 0

2.9 Conventional Facilities (OPC) 0 0 0 0 0 0 0 0

2 LCLS Total Other Project Cost 6,524 6,534 6,136 10 397 1.00 1.06 56,761 56,761 0

64,000 64,000

7,239 7,239

14.4% 14.4%

LCLS Total Obligations to Date 58,430 11.5% 11.5%

LCLS Total Project Cost 44,441 40,137 39,782 -4,303 355 0.90 1.01 379,000 379,000

13.2% 13.2%

LCLS Other Project Cost

LCLS Cost/Schedule Status Report - Work Breakdown Structure

WBS Variance

Schedule

Actual Cost Work

Performed

% Complete LCLS Base Cost

% Comp LCLS Other Project Cost

Avail. Management Reserve

% Contingency / Rem. Work

% Contingency / Rem. Work

31-Aug-05

SPI CPI

Performance Indices

Cumulative to Date ($K) At Completion ($K)

Budgeted

Avail. Contingency

Work Performed

VarianceLatest Revised

Estimate

Budgeted Cost

Work Scheduled

Cost

% Complete LCLS TPC

LCLS Total Estimated Cost

Page 4: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

10' ACCELERATOR

S2

OT

R3

LINAC HOUSING SIDEWALL

PEP-2 HE/LE BYPASS

LINAC COHERENT LIGHT SOURCE MODIFICATION TO LINAC 10' HIGH

BEAM

LE

LINAC HOUSING SIDEWALL

LINAC HOUSING SIDEWALL

YA

G 4

C

0 1

PEN. 20-17

BE

AM

ST

OP

PE

R

QE

-90

1

BPM

17 D

UM

P

9.4

LINAC HOUSING SIDEWALL

SECTION 21-1BSC

11

PEN. 20-16PEN. 20-15

2" TUBE

QU

AD

10' ACCELERATOR

SC

5

QU

AD B

01

SC

9

BP

M 1

3

BP

M 6

SC

3

LINAC HOUSING SIDEWALL

SECTION 20-8A SECTION 20-8B

A

10'

WS

04

QU

AD

LINAC HOUSING SIDEWALL

HE

1 2 4

3SECTION 20-8C

B

OTR

4

BP

M 5YA

G 2

CM

3

ACCEL

SC

4

10' ACCEL

LINAC HOUSING SIDEWALL

B, ,

KEY: ... ETC. ARE SIX SOURCE AREAS ALONG THE DRIFT REGION2,1

... ETC. ARE POINT-SOURCE LOCATIONS ALONG THE HE BYPASS LINE02,0 1

ARE THE DETECTOR LOCATIONS INSIDE THE LCLS INJECTOR VAULTCA

ACCELERATOR

EO

2

RF

KIC

KER

OT

R6

BP

M 1

4

3" TUBE

10'

0 2 03 04

B0

2

5 6

PEN. 21-1

ACCEL

QU

AD

QU

AD

CONCRETE

10' HIGH

B0 QS01

DRIFT SECTION

PICPIC

BSOIC

VALVE

Fe 1 Fe 2 Fe 3

Pb 3

FC1,YAG

E01

BPM

3

RF G

UN

CAT

HO

DE

CM

1

MAGNETIC

SC1 X-Y,QUAD

VALVE 1

S1Spectro.

CM2

BPM

2

BPM 4

FC2,YAG

BPM

1

RFCav.

SC2X-Y

PORC

UPINE CATHO

DE

HOLDER

UHV ALL M

ETAL

GATE VALVES

SPOOLS FR

OM VALVE

SEAL

LONG

BELLOWS

ASSEMB

LY

TREATM

ENT CHAMB

ER

VACUUM

PUMPS

QUAD

UNDULATOR

RA

D S

TOP

PER

QU

AD

OT

R5

Pb 2

Pb 1

QS02 QS03

OTRFC 4

EO

3

CM

4

SC

7

BPM

9

BP

M 1

0 VA

LVE

2

BPM

11

VALV

E 3

SC

8

BP

M 1

2

SC

10

VA

LVE

4S

C12

SC

13

FC3,YAG

SC

6

YAG

1

YAG

3

BP

M 8

BP

M 7

BPM 20

BPM 19

BPM 18

QU

AD

QU

AD

QU

ADQU

AD

QUAD

QU

AD

BPM 15BPM 16

1/22/2004

OT

R 1

OT

R 2

1.2 InjectorRF Gun

Load Lock

Transverse RF Cavity

Laser Heater

DL1 Bend

Straight Ahead Spectrometer

L0-1 & L0-23-m SLAC Sections

Gun Diagnostics

10/2005 Shutdown-Laser transport tubes-RF waveguide to injectorGun fabrication in process

Page 5: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

LCLS RF Gun Fab. In SLAC Klystron Dept.

Courtesy L.Xiao

Dual FeedSuppresses the time dependent dipole kickMatching phase for 2 feeds by holding mechanical tolerances on both arms

Z-coupling (instead of -coupling)Pulsed heating reduced + easier machiningRacetrack shape compensates for stronger quadrupole mode

Overcoupling =215 MHz mode separation adoptedPush-Pull deformable tuners

Replace plungers

Shaping of RF pulse for reducing average power4kW -> 1.8 kW ; cooling channels designed for handling 4kWReduce reflected power from gun

Gun fabricated at SLACRF design completeMechanical model in progress120Hz heat calculations under way

LCLS-TN-05-3.pdf

L. Xiao, et al., “Dual feed RF gun for the LCLS”, SLAC-PUB-11213, May 2005, http://www.slac.stanford.edu/pubs/slacpubs/11000/slac-pub-11213.html ; to be published in the proceedings of the 2005 Particle Accelerator Conference, 16-20 May 2005, Knoxville, TN; also to be published at the Joint Accelerator Conference Website (

http://www.JACOW.org )

Page 6: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Injector Laser Chosen - Thales

Delivery expected in May

LLNL (Brent Stuart, et al.) Studying temporal pulse shaping

ANL ( Yuelin Lee) Studying transverse pulse shaping

Bill White, LCLS Laser Group

Leader

Group will support facility lasers

Page 7: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Architecture Thales Laser System

1.5mx3.75m footprint(~4.5’x11.5’)

Spectra Physics MILLENIA Vs

Femtolasers OscillatorFemtosource Scientific 20s

(chirped mirrors)

JEDI #1100 mJ,120 Hz

JEDI #2100 mJ,120 Hz

Amplifier2-pass Bowtie

CompressorTHG

Pre-Amp4-pass Bowtie

RGARegen Amp

Stretcher DAZZLER

20 mJ, 120 Hz

80 mJ, 120 Hz

100 mJ, 120 Hz

119MHz400mW

5W, 119MHZ

150ps80mW119MHz

1mJ, 120Hz

>20mJ, 120Hz

>40mJ, 120Hz>25mJ, 120Hz>2.5mJ, 120Hz

To cathode

Amplifiers are not cryo-cooledIR stability <1%rms (short term)

Page 8: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

1.3 Linac

LCLS Klystron Injector Quad BC-1 DipolesFab Complete first article ordered measured

Page 9: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

1.4 Undulator Systems Progress, Changes

Magnet Blocks AwardedMagnet Poles AwardedStrongback AwardedAssembly, first articles AwardedUndulator Measurement Lab designedRFP issued for roomOn track for complete delivery of undulators by June 2007Design Changes

Electromagnet quadrupolesAluminum surface in undulator vacuum chamberFixed supports in ANL scopePlanning production prototype testsShim incorporated in undulator design – permits K reduction (significant shutdown required)

Page 10: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Page 11: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

1.4 Baby Pictures (cont’d)

Magnetized blocks Magnet Poles

Page 12: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

1.9 Conventional Facilities

Sector 20 Injector Magnet Meas.

2/28/06 Completion

Page 13: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

FFTB Shielding Sector 24 Stairs

Page 14: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Next Steps

Construction manager

Cost estimate

Construct road?

Construct tunneling portal?

Plan FFTB decommissioningDate will be between April and June

Page 15: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

~30m

GAS ATTENSOLID ATTENSTOP COLLIM

OffsetMirrors

STOP

1.5 New layout of FEEIncorporates Offset Mirrors

7 ft Fe 3 ft concrete 4 ft Fe

Page 16: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

1.6 XES instrumentation effort

Old Plan:XES to build a generic set of instrument components(infrastructure PPS, MPS, network)

New Plan: XES builds one instrument for soft x-ray Atomic Physics studies

Experiment infrastructure, laser, chambers, PPSPixel array detector spec’ed for cluster imaging

Page 17: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

1.6 - Since the Last Review

Scope modificationsSoft X-Ray Atomic Physics Experiment

Deletion of generic optics

Re-program to functional near hall station

Pixel Array Detector Specs address single molecule imaging

Page 18: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

20ft tunnel

30ft transition

46ft tunnel

212ft

28x33ft hutch 29x33ft

hutch36x33ft hutch

10ft

passage belowbeam pipe

Fire door

Fire door

10ft10ft

6ft

ToiletsFuture tunnel to other stations

Entrance 14ft tunnel

Sliding hutch door

15x25ft control cabin

1.9 New FEH design in baseline

Page 19: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Recent Events

SSRL User Meeting, 17 October 2005Pat Dehmer presentation, 2007 Budget

LCLS has high priority, high visibility, high likelihood of full funding

BES must get funding above its “line” to do LCLS without shutting down some facilities

BES is prepared to do this for LCLS IF we are ready

Page 20: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Wouldn’t Be a Project Without Some Challenges…

Conventional FacilitiesHigh bids

Sector 20, Magnet Measurement Facility, Construction Management

Jacobs Title-II (30%) estimate for future work is 50% above Title-IElectrical, Mechanical disciplines are 100% above Title-IJacobs expects increased escalation

Page 21: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

De-Scopes

Undulator Hall A/C redesign ~$3.5M savingsOther CF Economies - $ 7.5MStill looking for $5M

further CF reductions might yield $1M-$2M

Flipping Mirrors - $2MFlipping Mirrors - $2MMore to go, emphasis on:More to go, emphasis on:

ReversibleReversibleNo impact on commissioning and early No impact on commissioning and early operationoperation

Page 22: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

2nd Undulator Line

3rd Undulator Line NearExpt.Hall

XR tunnel shortenedfrom 250m to 230m

28x33ft hutch 1 29x33ft

hutch 2 36x33ft hutch 3

20ft tunnel212ft

46ft tunnel

15x25ft control cabin

Entrance 14ft tunnel

Page 23: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Central Lab Office Complex (CLOC)Capacity >26078,000 GSF Total150-Seat Conference Room

Leave 3rd floor unfinished

Delete 3rd floor?

Page 24: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Continuing Resolution

No slowdown unless CR extends past December

CF, undulator assembly must go forward to stay on schedule

Will ask for help.

Page 25: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Response to Comments/RecommendationsMembers of the FAC had minor concerns about the organization chart as having a baroque appearance in that on the surface, lines of authority don’t appear to be that clear. However, throughout the course of the FAC meeting clear lines of responsibility and authority were in evidence and only a few issues on communication (notably between the physics requirements on the conventional facilities and the operations configurations and approaches) were apparent. Response: The LCLS organization chart has been revised to clarify roles and responsibilities.

Page 26: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

LCLSProjectOrganization(Sep05)

Page 27: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

The project should incorporate those risk or trade-off items identified in this and previous FAC meetings into the Project Risk Registry to ensure adequate tracking and resolution. The project may wish to also incorporate any such risk items cited in official DOE reviews as well.Response: The LCLS organization continues to use the Risk Registry on a monthly basis as a key management tool to proactively address its known risks. The undulator floor stability risk has now been retired as it has now been shown that expected stability issues can be addressed with the alignment systems and BBA at acceptable intervals.

https://www-lcls-internal.slac.stanford.edu/projectspace_L2/Project_Office/Risk_Registry_Documents/LCLS_risk_registry_September_05.pdf

Page 28: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

The project is entering into its boost phase where it is undergoing its maximum gradient: staffing, effort and procurement. During this phase, the timeliness of decisions often becomes critical and delays can quickly accumulate that can impact the overall progress of the project without specific attention. This is a concern to the FAC as the decision making process is not transparent and may need to accelerate to ensure avoiding unnecessary delays. Response: The decision making process has been made more transparent with the Change Control Board (CCB). With the CD-2b (Approve Performance Baseline), LCLS has enacted the CCB to deal with technical, cost and schedule issues on a timely basis. The CCB forum ensures that decisions are communicated uniformly across the project and formally documented in a manner consistent with good configuration control. Since CD-2b (April 2005), LCLS has approved 77 changes to the project and allocated ~$7M of contingency to the baseline cost of the LCLS.

Page 29: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

The critical path of the project, likewise, may be extremely fluid during this phase and near critical paths can quickly become critical paths, and so those efforts which at present are not on the critical path, must understand that they can quickly become the pacing activities.Response: The LCLS has significantly increased its staffing since April 2005 and with that some time for assimilation of new staff into the project is required. The LCLS is now nearly complete on its staffing plan so the inefficiencies due to assimilation can be expected to drop off. Critical path is monitored regularly and has not shown any appreciable degradation since established at 215 days.

Page 30: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

…However, an insightful planning exercise is to evaluate all activities for early starts up to the point where all of the budget authorization (BA) in each fiscal year would be used. In addition, exceeding this optimistic BA plan by 5 to 10% would also be helpful in evaluating potential resource demands. This planning assures that there are “swing items” identified in order to accomplish other work if planned activities are delayed. If the project doesn’t have swing items identified to work in the available time and with the available BA, the CD-4 milestone may be at greater risk than necessary.

“Swing procurements” are procurements that can be advanced should budget become available due to delays in other areas. This is of primary importance between FY06 and FY07. Since civil construction sets the critical path, LCLS will plan to use its budget flexibility in this area to best advantage, based on advice from the Construction Manager.

Page 31: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

A useful plot that can illustrate this phenomenon, and serve as both a leading and lagging indicator, is the contingency as a percent of the estimate to complete (ETC) budget as a function of the percent of the project complete. Generally, this should be roughly a horizontal line above 20%. Early in the project life it would likely start out at a higher number and depending upon the remaining risks within a project, the percentage can also be less than 20%.Response: Currently, the LCLS holds ~32% contingency on work remaining. This number may fall lower as the conventional facilities estimates become more mature and LCLS approaches the start of construction.

Page 32: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

There is a need for a central database containing and controlling the complete configuration of the LCLS project.

Work has begun on defining the detailed needs of the central database effort for the LCLS project. An IT Manager (Andrea Chan from the SLAC SCS group) has been hired into the LCLS Division and bringing significant experience in setting up databases in a project environment. At the same time Sergei Chevtsov in the LCLS Controls Group has been looking at the relational database needs for the control system, in particular the RDB requirements for online modeling for the accelerator.

Page 33: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

The LCLS Project should consider giving the FAC access to the LCLS internal website. This would allow the FAC to view other reviews and important work that can have an impact on the scope and details of FAC meetings. It will also allow the LCLS Project to exploit the full potential of the FAC.LCLS is in the process of exploring a different data management system, which would make access control but the system is not likely to become operational in this calendar year. At present, LCLS is working with Kem Robinson to do it the hard way now or wait until the simpler solution is in place.

Page 34: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

Charge to Committee

Consider responses to last review

Consider planned/proposed scope changes to accommodate conventional facilities costs

Page 35: John N. Galayda LCLS Facility Advisory Committee galayda@slac.stanford.edu 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements

John N. Galayda

LCLS Facility Advisory Committee [email protected]

27 October 2005

End of Presentation