21
John N. Galayda LCLS FAC Review [email protected] .edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John N. Galayda Director of LCLS Construction

John N. Galayda LCLS FAC [email protected] 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

  • View
    216

  • Download
    2

Embed Size (px)

Citation preview

Page 1: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 20061

Linac Coherent Light SourceOverview and Charge

Facility Advisory Committee

John N. Galayda

Director of LCLS Construction

Page 2: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 20062

CD-3b Approved 28 March 2006

Page 3: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 20063

1.1 Project Management 12,890 12,843 14,085 -47 -1,242 1.00 0.91 27,741 32,316 4,575

1.2 Injector 12,387 10,417 10,582 -1,970 -165 0.84 0.98 20,584 22,951 2,367

1.3 Linac 6,105 5,372 4,286 -733 1,085 0.88 1.25 25,312 22,915 -2,397

1.4 Undulator 13,388 11,837 11,737 -1,551 100 0.88 1.01 41,095 40,972 -123

1.5 X-ray Transport 6,939 6,831 6,487 -107 345 0.98 1.05 24,149 27,027 2,878

1.6 X-ray Endstations 914 907 876 -6 31 0.99 1.04 14,140 14,715 575

1.9 Conventional Facilities 15,178 14,690 14,192 -488 498 0.97 1.04 107,204 112,688 5,484

1 LCLS Total Base Cost 67,800 62,898 62,245 -4,902 653 0.93 1.01 260,223 273,584 13,361

315,000 315,000

54,777 41,416

27.8% 19.7%

24.2% 23.0%

2.1 LCLS Project Mgmt, Planning & Admn (OPC) 5,076 5,152 5,094 76 58 1.01 1.01 33,425 33,582 -157

2.2 Injector (OPC) 733 667 669 -65 -2 0.91 1.00 5,754 5,805 -50

2.3 Linac (OPC) 1 1 31 0 -30 1.00 0.04 2,545 2,575 -29

2.4 Undulator (OPC) 1,050 747 794 -303 -47 0.71 0.94 5,502 5,502 0

2.5 X-ray Transport (OPC) 489 489 427 0 62 1.00 1.14 4,930 4,878 52

2.6 X-ray Endstations (OPC) 319 255 175 -64 80 0.80 1.45 5,246 5,164 82

2.9 Conventional Facilities (OPC) 0 0 0 0 0 621 621 0

2 LCLS Total Other Project Cost 7,668 7,312 7,191 -356 121 0.95 1.02 58,024 58,126 -103

64,000 64,000

5,976 5,874

11.8% 11.6%

12.6% 12.6%

LCLS Total Project Cost 75,468 70,210 69,436 -5,258 774 0.93 1.01 379,000 379,000

22.1% 21.2%*Management Estimate at Complete includes the Budget at Complete, a weighted CPI and SPI, proposed Baseline Change Requests and known risk contingencies.

WBS Variance

Schedule

Actual Cost Work

Performed

% Complete LCLS Base Cost

Avail. Contingency

% Complete LCLS TPC

28-Feb-06

SPI CPI

Performance Indices

Cumulative to Date ($K) At Completion ($K)

Budgeted

LCLS Cost/Schedule Status Report - Work Breakdown Structure

Work Performed

Variance

LCLS Total Estimated Cost

% Contingency / ETC

% Management Reserve / ETC

LCLS Other Project Cost

% Comp LCLS Other Project Cost

Avail. Management ReserveLCLS Total Obligations = $82,436.3K

Management Estimate at Complete*

Budgeted Cost

Work Scheduled

Cost

Earned Value: 23.0% of TEC 21.2% of TPC

Page 4: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 20064

Project Highlights and Key Considerations

Injector 45.3% completeGun fabrication at SLAC- Hot test at ASTA AugustLaser delivery in May 2006Linac BC-1 installation in Fall shutdownInjector installation schedule runs into 2006/2007 shutdown- BC-1 must have priorityPursue all prudent means to speed schedule and preemptively mitigate schedule problems

Add design staffOff-site fabrication, sources for rigging etc.

Commissioning start – end of CY2006Commissioning applications software will be rudimentary at start

Page 5: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 20065

Project Highlights and Key Considerations

Undulator production underwayPrototype at SLAC for measurementChamber finish tests underwaySingle Undulator Tests ongoingRFBPM fabrication test encouragingUndulator Measurements at SLACMMF startup in August

Page 6: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 20066

Project Highlights and Key Considerations

Photon Beam SystemsDeputy – Hal TompkinsX-ray Transport/Optics/Diagnostics

XTOD Liaison physicist- Peter StefanPrototype gas attenuator assembled, vac. testedDesign reviews for XRT vacuum, collimators

End Station SystemsStaffing up- Layout of experiments is settled downAMO Liaison physicist – John BozekDetector Liaison physicist - Niels van Bakel

Page 7: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 20067

Project Highlights and Key Considerations

Conventional Facilities Architectural design @ 100%

Construction manager on boardFinal Focus Test Beam operation to 10 April 2006

Bids for first major packages due in late March

Second group of bids due in late May

third group of bids (for CLOC) due in September

Beneficial occupancy of entire e-beam path and NEH by August 2007

Page 8: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 20068

Sector 20

Beneficial Occupancy next week

Installation underway in vaulttray

supports

floor

Page 9: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 20069

Magnet Measurement Facility Beneficial Occupancy 14 April 2006

Page 10: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200610

LCLS Civil Construction

100% cost estimate (not escalated)

Jacobs Turner$69M $72M

Above includes 3rd floor, Building 8.1expect further $5M savings $64M-$67M

Close enough to $62.5M VE target set after the 30% cost estimate

Page 11: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200611

Issues

InjectorTight schedule for production and installationInjector installation schedule overlaps BC-1 shutdown workLaser Commissioning supports 12/2006 injector commissioning

LinacBC-1 readiness for installationModification of machine protection and beam containment to permit use of deflecting cavityreal-time 120 Hz bunch length tuning diagnostic

Page 12: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200612

Issues

UndulatorSchedule for startup of measurements at SLAC

Thorough testing of leveling/alignment system

FEL commissioning diagnostics, especially x-ray

XTODRapid convergence on specifications and prioritization of design efforts to match challenges

Page 13: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200613

Issues

Endstation SystemsPlanning to accommodate LUSI program in light of de-scopes

Smooth shift of effort into ESS from injector/linac

Conventional FacilitiesTimely direction to CM

Efficient interface to A/E- Title-III lead selection

Staff up for paper workload

Page 14: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200614

Issues

ControlsEPICS work appears to be in hand

Hardware and Applications delayed

Need to clarify responsibilities/assignments for these areas

Page 15: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200615

PROJECT INJURY EXPERIENCE TO DATE

SubContractors 29 K Hours worked (03/31/2006)

Zero Injuries

LCLS Collaboration 460 K Hours worked (03/31/2006)

One shoulder strain

226 Days Worked Without Injuries (04/20/2006)

0

0.43 0.41

2.1

0

0.5

1

1.5

2

2.5

Project To Date

Contractors

LCLS

Total Project

DOEConstruction

Lost Time Injury Rate

Note: Injury rates based on 200 K hours (100 manyears) of effort.

Page 16: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200616

Charge to Committee

The LCLS Facility Advisory Committee will adviseSLAC, SSRL and LCLS management on thedevelopment of the LCLS Project through its several phases:

Accelerator systems design and constructionUndulator systems design and constructionX-ray transport, optics and diagnostics design and constructionExperiment station systems design and constructionConventional facilities design and constructionPlanning and execution of commissioning and early operations

Page 17: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200617

Areas of Concentration

Areas of concentration for this meetingAll aspects of injector, leading up to commissioning

ControlsApplications

LLRF

PLC/PPS

Undulator system integration

Page 18: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200618

End of Presentation

Page 19: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200619

Page 20: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200620

WBS System FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 Total

1.1 Project Mgmt., Admin. & Integration BCWS 0.00 1.45 2.39 5.75 8.36 4.36 3.69 1.74 27.74

1.2 Injector System BCWS 0.00 0.65 1.91 4.60 11.18 2.23 0.01 0.00 20.58

1.3 Linac System BCWS 0.00 0.19 1.15 1.92 9.13 9.69 3.24 0.00 25.31

1.4 Undulator System BCWS 0.00 0.59 1.58 5.86 15.88 13.49 3.56 0.13 41.09

1.5 X-Ray Transport & Diagnostics BCWS 0.00 0.71 0.82 3.28 5.94 11.64 1.34 0.42 24.15

1.6 X-Ray Endstations BCWS 0.00 0.00 0.20 0.54 1.46 5.71 6.65 0.05 14.61

1.9 Conventional Facilities BCWS 0.00 0.12 1.60 4.45 22.54 60.79 16.41 1.19 107.11

Estimated Base Cost BCWS 0.00 3.71 9.65 26.40 74.48 107.93 34.90 3.54 260.60

Contingency BCWS 0.00 0.00 0.02 23.28 11.06 -2.03 15.60 6.46 54.39

% Contingency BCWS 0.0% 0.0% 0.0% 88.2% 14.8% -1.9% 44.7% 182.8% 17.3%

Total Estimated Cost (Base + Contingency) BCWS 0.00 3.71 9.67 49.68 85.54 105.90 50.50 10.00 315.00

2.1 Project Mgmt., Admin. & Integration BCWS 1.50 0.00 1.15 1.84 1.44 7.12 7.78 12.60 33.43

2.2 Injector System BCWS 0.00 0.00 0.13 0.57 0.17 2.36 2.17 0.34 5.75

2.3 Linac System BCWS 0.00 0.00 0.00 0.00 0.00 1.37 0.82 0.36 2.55

2.4 Undulator System BCWS 0.00 0.00 0.45 0.30 0.64 2.82 0.87 0.43 5.50

2.5 X-Ray Transport & Diagnostics BCWS 0.00 0.00 0.27 0.22 0.00 1.15 1.70 1.59 4.93

2.6 X-Ray Endstations BCWS 0.00 0.00 0.00 0.13 0.75 1.34 2.47 0.55 5.25

2.9 Conventional Facilities BCWS 0.00 0.00 0.00 0.00 0.01 0.16 0.36 0.08 0.62

Other Project Costs BCWS 1.50 0.00 2.00 3.07 3.02 16.32 16.17 15.95 58.02

Management Reserve BCWS 0.00 0.00 0.00 0.93 0.48 -0.32 -0.67 5.55 5.98

% Management Reserve BCWS 0.0% 0.0% 0.0% 30.4% 16.1% -2.0% -4.2% 34.8% 9.3%

Total Other Project Cost (Base + MR) BCWS 1.50 0.00 2.00 4.00 3.50 16.00 15.50 21.50 64.00

Total Project Costs (Base + Cont. + OPC) BCWS 1.50 3.71 11.67 53.68 89.04 121.90 66.00 31.50 379.00

FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 TotalTEC Funding 0.00 5.93 7.46 49.68 85.54 105.90 50.50 10.00 315.00OPC Funding 1.50 0.00 2.00 4.00 3.50 16.00 15.50 21.50 64.00Total Funding 1.50 5.93 9.46 53.68 89.04 121.90 66.00 31.50 379.00

Linac Coherent Light Source BCWS Profile (AYM$) JANUARY 2006

Linac Coherent Light Source Funding Profile (AYM$)

Page 21: John N. Galayda LCLS FAC Reviewgalayda@slac.stanford.edu 20 April 2006 1 Linac Coherent Light Source Overview and Charge Facility Advisory Committee John

John N. Galayda

LCLS FAC Review [email protected]

20 April 200621