Upload
ariel-andrews
View
214
Download
0
Embed Size (px)
Citation preview
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Linac Coherent Light Source (LCLS)
Low Level RF System
Injector Turn-on January 2007
September 19, 2006
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Safety First and Second and Third…..to Infinity
Hazards in the LLRF systemRF 1kW at 120Hz at 5uS = 0.6 Watts average, 2 Watt average amps at 2856MHz, 60W average amps at 476MHz
Hazards – RF BurnsMitigation – Avoid contact with center conductor of energized connectors. All employees working with LLRF systems are required to have the proper training.
110VAC ConnectorHazards - Shock Mitigation - Don’t touch conductors when plugging into outlet.All chassis are inspected by UL trained inspector.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Scope of Work – Injector Turn-onLinac Sector 0 RF Upgrade
All 3 RF Chassis completed and Installed (Master Oscillator, Master Amp, PEP phase ShifterControl Module ready for test – higher phase noise levels if not installed
Sector 20 RF distribution systemPhase and Amplitude Controllers (PACs) – 6 unitsPhase and Amplitude Detectors (PAD) – 2 unitsPhased Locked Oscillator – Use SPPS unit for Turn OnLO Generator – Complete - 50% tested – looks good so farMultiplier – 476MHz to 2856MHz – Complete 50% Tested4 distribution chassis – Complete 102MHz, 2056MHz, 2830.5MHzLaser Phase Measurement – in Design, diagnostic, not required for turn on – Laser group wants it next week. Distribution Amplifiers – 10W, 2850MHz on order – 10W, 102MHz Amp in search Minicircuits has 5W and 50W
LLRF Control and Monitor System1 kW Solid State S-Band Amplifiers – 5 units – Design Complete, In FabPAD – 12 units – 6 required for turn on PAC – 6 unitsBunch Length Monitor Interface – awaiting Specs
Beam Phase CavityWill use single channel of PAD ChassisPill box cavity with 2 probes and 4 tuners – 2805MHz 3 units Complete
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
LCLS Layout
P. Emma
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
LLRF Control system spans Sector 20 off axis injector to beyond Sector 30
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
LCLS RF Jitter Tolerance BudgetLCLS RF Jitter Tolerance Budget
RMS tolerance budget for <12% rms peak-current jitter or
<0.1% rms final e− energy jitter. All tolerances are rms levels and the voltage and
phase tolerances per klystron for L2 and L3 are Nk larger,
assuming uncorrelated errors, where Nk is the number of
klystrons per linac.
P. Emma
Lowest Noise Floor Requirement 0.5deg X-Band = 125fSStructure Fill time = 100nSNoise floor = -111dBc/Hz @ 11GHz 10MHz BW-134dBc/Hz @ 476MHz
X-bandX-band XX--
0.500.50
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Slow Drift Tolerance LimitsSlow Drift Tolerance Limits
Gun-Laser TimingGun-Laser Timing 2.4*2.4* deg-Sdeg-S
Bunch ChargeBunch Charge 3.23.2 %%
Gun RF PhaseGun RF Phase 2.32.3 deg-Sdeg-S
Gun Relative VoltageGun Relative Voltage 0.60.6 %%
L0,1,X,2,3 RF Phase (approx.)L0,1,X,2,3 RF Phase (approx.) 55 deg-Sdeg-S
L0,1,X,2,3 RF Voltage (approx.)L0,1,X,2,3 RF Voltage (approx.) 55 %%
(Top 4 rows for (Top 4 rows for // < 5%, bottom 4 limited by feedback dynamic range) < 5%, bottom 4 limited by feedback dynamic range)
* for synchronization, this tolerance might be set to * for synchronization, this tolerance might be set to 1 ps (without arrival-time measurement)1 ps (without arrival-time measurement)
(Tolerances are peak values, not rms)(Tolerances are peak values, not rms) P. Emma, J, WuP. Emma, J, Wu
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Distribution system
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Concerns of Previous ReviewsInstallation of temperature stabilized cables can effect phase stability.
Working with cable shop on plan for installationTriggers required to be synchronous with 476MHz may jitter
The highest frequency that triggers need to be synchronous with is 102MHz. Procedurally triggers will be placed in the stable region
SPPS PLL design generates an internal pulse width based on a one-shot and uses an old track and hold chip
Redesign of this chassis will be done next year and these comments will be taken into consideration
LO Generator design uses internal trim caps and resistors to calibrate unit, synchronization needs to be addressed, should consider SSB modulator
We are using internal trim caps and resistors - have not had a problem in the past with these types of devicesThe synchronization will be monitored and can be reset if it gets out of syncThe unit is a SSB modulator
Concerns of Hardware and Software being disconnected from each other and the review committee would also like to better understand the software.
The LLRF Hardware effort has been moved to the controls group and is now being reviewed with the software.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Linac Sector 0 RF Upgrade
PEP PHASE SHIFT ON MAIN DRIVE LINE MDL RF with TIMING Pulse – Sync to DR
Master Oscillator is located 1.3 miles
from LCLS Injector
1.3 Miles to LCLS Injector
LCLS must be compatible with the existing linac operation including PEP timing shifts
MASTERAMPLIFIERS
MAIN LINAC (SECTOR 0) RF/TIMING SYSTEM
1
476MHzMASTEROSCILLATOR
PEP PHASESHIFTER+-720 Degreesin 0.5mS
SLC COUNTDOWNCHASSIS 476MHzDivide to 8.5MHz
Master TriggerGenerator MTGSyncs Fiducial to8.5MHz Damping Ringand 360Hz Power Line
8.5MHz
360Hz LineSync.
476MHz
360Hz
Fiducial GeneratorSyncronized to:360Hz Power Line8.5MHz Damping Ring476MHz RF Distribution
SumFiducialto RF
Main Drive Line (MDL)476MHz RF plus360Hz FiducialTo:Main Linac - 2 milesDamping RingsPEPNLCTAEnd Station AFFTBORION
Measurements on January 20, 2006at Sector 21show 30fS rms jitter in a bandwidth from 10Hz to 10MHz
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PEP II Phase Shifter10kHz freq shift 1.2Vpp IQ in
Agilent E4407B
-100
-90
-80
-70
-60
-50
-40
-30
-20
-10
0
10
20
475950000 475970000 475990000 476010000 476030000 476050000
Frequency
dB
m
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Linac Sector 0 RF Upgrade Status
New Low Noise Master Oscillator – Done
New Low Noise PEP Phase ShifterRF Chassis – Done
Control Chassis – Ready for installation
New Low Noise Master Amplifier – Done
Main Drive Line Coupler in Sector 21 – Done
Measurements Noise floor on 476MHz of -156dBc/Hz
Integrated jitter from 10Hz to 10MHz of 30fS
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
RF System Topology / Specifications
476MHz PLL2830.5MHz LOAmp / Splitter
Laser
RF Gun
L0A
Phase Cavity
L0B
L1S
L1X
L2 Ref
PAD
Laser
RF Gun
L0A
Phase Cavity
L0B
L1S
L1X
L2 Ref
Most Devicesare in tunnel
Laser
RF Gun
L0A
Phase Cavity
L0B
L1S
L1X
L2 Ref
1
Number of cables per deviceReference cables are8ft and can drift +-50fS
1
2
4
2
2
2
5
RF HUT
+-240fS
+-310fS
+-370fS
+-680fS
+-500fS
+-160fS
+-140fS
+-240fS
Cable Drift Based onTemperature variationsand temp co of 5ppm/degC
LinacSector 0 RF
MDL
L2 - 4 SectorsSpecifications70fS rms jitter+-5pS drift
L3 - 6 SectorsSpecifications150fS rms jitter+-5pS drift
L0, L1 - 5 KlystronsSpecifications100fS rms jitter+-2.3pS drift
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Sector 20 RF Distribution
RF CONTROLSPAC
380-208-22476MHz to 2856MHzMULTIPLIER
2830.5MHz LO Gen
RF MONITORPAD
119MHz Phase
119MHz
Main Drive Line (MDL)476MHz RF360Hz FiducialFrom Sector 0 (2km)
RF HUT Coupler476MHz Ref. 80uW
LASERReference
4x 476MHz13dBm OUT
ExistingTIMING SYSTEMFIDO Output
LCLS 476MHz PLL120HzTRBR
LCLS Sector 20 RF Reference System
+13dBm in
Track/HoldTRBR
2856MHz16 Way Distribution20dBm each
GunL0AL0BL0TCAVL1SL1X
+17dBm out
2856MHz2Watt Amplifier
102MHzDigitizer Clocks16 Way Distribution26dBm each
Diode Detector
476MHzLASER LOCKReference
119MHz0dBm OUT
LO Phase Monitor
102MHz2Watt Amplifier
RF MONITOR PAD
RF CONTROLSPAC
GunL0AL0BL0TCAVL1SL1XLINACEXPERIMENTS
Sample and Hold PLLwith DAC offset adjustand Error Monitor
RF CONTROLSPAC
2830.5MHz2Watt Amplifier
380-208-22476MHz to 2856MHzMULTIPLIER
2830.5MHz LO16 Way Distribution20dBm each
2856MHz in
IQ Modulator to adjust2830.5MHz to 2856MHz Phase
Divide 112 to 25.5MHzSSB Mix to 2830.5MHz4X to 102MHz
25.5MHz out
102MHz out 2830.5MHz out
Diode Detector
RF CONTROLSPAC
GunL0AL0BL0TCAVL1SL1X
Diode Detector
+13dBm in
LO Phase Monitor
LO Phase Monitor
RF CONTROLSPAC
RF MONITORPAD
+17dBm out
RF MONITOR PAD
MDL to Linac Sectors 21 to 30PEP and Research Yard
FSJ4-50 0.8dB/30ft
2856MHz from Sector 21
LCLS LLRF 476MHz Linac Ref.
4 x +13dBm out
380-208-38476MHz Amp30dB Gain 19dBm
LASER DiodeMeasurement
Phase Noise and Timing
2856MHz and 119MHz
LASER DiodeOutput
LO Phase MonitorRF MONITOR PAD
RF MONITOR PADLO Phase Monitor
LO and 102MHz resync by adjusting 2856MHz PAC while monitoring S21 2856MHz
Laser resync with laser PAC while monitoring difference in 119MHz laser and FIDO out
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
2830.5MHz Generator
B. Hong
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Phase Noise Measurements
By J. Frisch
Noise Floors Lower Than
Expected Values which are
Lower than Requirements
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Sector 20 RF Distribution System StatusPhase Locked Oscillator – 476MHz – Done for now
Initial Turn On use SPPS OscillatorWill modify control to achieve better stability during 2007
LO Generator – 2830.5MHz - Built – 50% testedMultipliers - 476MHz to 2856MHz – Built – 50% testedPhase and Amplitude Control (PAC) Unit
See next section
Phase and Amplitude Detector (PAD) UnitSee next section
Distribution Amplifiers 2850MHz due mid October102MHz search under way
Laser Phase Measurement SystemMay design DC PAD control board
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
LLRF Distribution Schedule
Racks to be installed in RF Hut – next week
RF Cables (On-site) to be pulled – mid October
RF Chassis – 50% complete10 more chassis required for turn on, to be installed by December
Remainder by March 2007
Testing of RF distribution system - DecemberPhase measurements of cables / looped
Ready for turn-on – Mid December
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Beam Phase Cavity Status
Electronics will use single channel of PAD ChassisPill box cavity with 2 probes and 4 tuners Cavity Electronics will use single channel of RF MonitorThree cavities fabricated
The cavity was moved to 2805MHz after concerns of the last review about Dark Current were analyzed. Measurement of beam phase to RF reference phase. The result will be used to correct timing of laser to RF reference. 2805MHz cavity is located between L0A and L0B. Will use RF PAD with 2830.5MHz LO for a 25.5MHz IF.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
LLRF Control System
Distributed Control System
Microcontroller based IOC Control (PAC) and Detector (PAD) Modules
Ethernet Switch
Central Feedback Computer
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Concerns of Previous Reviews
The Slow ADC can have problems with ground noise and should be mounted on the RF board.
The Slow ADC is mounted on a separate board for the PAD and the same board for the PAC. It is used to monitor various devices including external thermocouples, RF power levels, and power supply voltages.
The system is being designed with too little diagnostics, at a minimum the input power should be monitored for remote chassis.
The PAC is being designed with a monitor for input power. The LO on the PAD, when used, will also be monitored.
The PAD and PAC systems should report missing, unexpected or multiple trigger signals remotely.
The PAC currently has the ability to report missing triggers, but the features have not yet been tested. The processor on the PAD has the capability to do this also and this will be considered in the future if thought necessary.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
LLRF Control and Monitor System Klystron Station
13dBm
17dBm
SPARE
KLYSTRON STATION
21dBm
240ft = 17dB 1/2 Superflex= 10dB LDF4
240ft = 2.5dB 1/2 Superflex= 1.6dB LDF4= 3dB LDF1
3dBm
3dBm
140ft = 25dB 3/8 Superflex
Coupled Out
ENET
TRIG
TRIG
ENET
GATEfromBCS
GATE
LCLS RF HUT2830.5MHz LOAmp / Splitter
TCAV
RF Gun
L0A
L0B
L1S
L1X
RF HUT
PAC
20-5
20-6
20-7
20-8
21-1
21-2
LCLS RF HUT2856MHz RFAmp / Splitter
TCAV
RF Gun
L0A
L0B
L1S
L1X
20-5
20-6
20-7
20-8
21-1
21-2
LCLS RF HUT102MHz ClockAmp / Splitter
TCAV
RF Gun
L0A
L0B
L1S
L1X
20-5
20-6
20-7
20-8
21-1
21-2
PAD
In 2856MHz Out
102MHz Clock In
Trig & Ethernet
SSSB
102MHzClock In Out
LO
Trig & Ethernet
To IPAKlystron Drive
In 2856MHz Out
SSSB Control Control & Monitor
From Klystron Drive Coupler
KLY BEAM Voltage
PAC OUT
Coupled Out
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
RF & Temperature Signal Counts for FeedBack exclude Klystron PADs
ADC Chan Cnt/FBK Hut PADs Temp. Mon.
Distribution/Laser 7/0 1.5 6RF Gun 6/5 1.5 6Beam Phase Cavity 2/1 0.5 3L0-A Accelerator 2/2 0.5 3L0-B Accelerator 2/2 0.5 3L0-T Transverse Accelerator 2/0 0.5 3L1-S Station 21-1 B, C, and D Acc 4/4 1.0 6L1-X X-Band accelerator X-Band 2/2 0.5 3S25-Tcav 2/0 0.5 3S24-1, 2, & 3 Feedback 0S29 and S30 Feedback 0
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
LLRF Control and Monitor System Status
1 kW Solid State S-Band Amplifiers – 5 units1kW amplifier modules currently in test
Existing amplifier support design under review
Phase and Amplitude Detectors – 11 quad chan unitsControl Board – Pre production delivered – may require 2nd round.
RF Board – in layout
Phase and Amplitude Controllers – 6 unitsControl board – Sent out for Pre production
RF Board – Pre-production in Fab.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAD
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAD Block Diagram
Chan. 0
4 X 16 bit ADC102MHz ClockLTC2208Transformer Coupled Inputs
Chan. 1
WCLK
FIFO 64k words
16bit DATA
WCLK
CHAN 1RF INPUTRP N
CHAN 0RF INPUTRP N
16bit DATA
MIXER
LORF
IF
Control
Control Board
RF Board
FIFO 64k words
FIFO 64k words
FIFO 64k wordsWCLK
16bit DATA
WCLK
16bit DATA
CO
MR
AW
ETH
ER
NE
T
Chan. 3
Chan. 2
QSPI
5VDC0.5A Digital
5VDC0.8A x 2 Analog
LO OUTPUT2830.5MHzRP N
24Bit Analog InputBoard
QSPI
20 pin ribbonTRIG MonFP BNC
ANALOG IN ANALOG IN
CLOCK Mon102MHzFP N
CLOCK IN102MHzRP N
TRIG In120HzRP BNC
CS/CLK
16 bitDATA
CONTROL /Arcturus uC5282Microcontroller Modulewith 10/100 Ethernet
ETH
ER
NE
T
CPLD
10dBm
FILTER 25.5MHz BP
CPL7
CHAN 125.5MHz IFFP BNC
MIXER
LORF
IF
FILTER 25.5MHz BP
LO INPUT2830.5MHzRP N
LO DIODEDETECTORFP BNC
CHAN 1TEST PORTFP N
CHAN 0TEST PORTFP N
CHAN 025.5MHz IFFP BNC
CHAN 0TEST PORTRP SMA
CHAN 2RF INPUTRP N
CHAN 1TEST PORTRP SMA
CHAN 3RF INPUTRP N
MIXER
LORF
IF
RF Board
LO OUTPUT2830.5MHzRP N
FILTER 25.5MHz BP
CPL7
CHAN 325.5MHz IFFP BNC
MIXER
LORF
IF
FILTER 25.5MHz BP
LO INPUT2830.5MHzRP N
LO DIODEDETECTORFP BNC
CHAN 3TEST PORTFP N
CHAN 2TEST PORTFP N
CHAN 225.5MHz IFFP BNC
CHAN 3TEST PORTRP SMA
CHAN 2TEST PORTRP SMA
Most PADs will consist of 2 RF Modules to down convert 2856MHz to 25.5MHz, a 4 Channel, 16bit, digitizer control board, and an 8 channel 24bit slow analog input.
RF Board Mixers Marki Microwave M1-2040MEZ : Amplifiers Sirenza SBW-5089 : Slow ADC TI/BB ADS1218 : Fast ADC LT LTC2208
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAD RF Power Levels # ADCs RF Power
PAD PowerDistribution 4 10mW-100mWRF Gun Forward 1 10MW 10W-30WRF Gun Probes 4 10MW 10W-30WBeam Phase Cavity 2 100mW 30mWL0-A Accelerator 2 60MW 120WL0-B Accelerator 2 60MW 120WL0-T Transverse Accelerator 2 0.5MW 0.5W-30WL1-S Station 21-1 B, C, and D Acc 4 15MW 30W-120WL1-X X-Band accelerator X-Band 2 20MW 2WS25-Tcav 2 10MW 10WS24-1, 2, & 3 Feedback 0S29 and S30 Feedback 0
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAD 4 Chan ADC Board25.5MHz 4 point IQ Data Analysis – SNR – 76dB Amplitude 76dB Phase
Noise Floor from below plots < -147dBc/Hz - SNR 65dB
25.5MHz Cross Talk from below plots < 100dB
Channel 0 data: Signal = -7.1dB Noise Level = -72.1dBChannel 1 data: Signal = -112dB Noise Level = -79.3dB
Bin Width 1816Hz, 33dB
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAD Software
Different LLRF apps need different calculationsThere are 5 different algorithms:
AVG+STD – calculate average I and Q and variance of I and QRF WF – calculate average I and QWF – calculate average of sampleRF WF2 – calculate average I and Q of two samplesIQ Cal – send 64K raw data waveform
Each channel on a PAD can run a different algorithmEach PAD can run in CALIBRATION or RUNNING mode, which use different algorithms
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAD Software
Data acquisition begins via timing trigger
Each PAD needs its own trigger so that it can have its own delay
4 channels of 1024 16-bit integers at 102 MHz read in within 2 ms
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAC
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAC Block Diagram
Amp
SSSBChassisRP 15 Pin D
RA
WE
THE
RN
ET
CO
M
AmpMAX58752 X 16 bit DAC119MHz Clock(1MHz to 200MHz)
I
RF LO
Q
I&Q MODULATOR
1
2
3
4
Q
I XILINXSPARTAN 3FPGA
16bit DATA
CS/CLK
16bit DATA
16 bitDATA
CLK
CLK CONTROL /Arcturus uC5282Microcontroller Modulewith 10/100 Ethernet
ETH
ER
NE
T
Control
RF OUTPUTTo SSSBRP N
Control
TRIGGERMonitor TTLFP BNC
MATCHINGFILTERNETWORK
EXT TRIG120HzRP BNC
2856MHzRef InRP N
I MONITORFP BNC
RF OUTPUTMonitorFP N
RF INPUTMonitorFP N
NC
Q MONITORFP BNC
RF INPUTMonitor DiodeFP BNC
AD8099 Diff Amp
SSSBTrigTTL17 to 30uS
SSSBGate MonitorFP BNC
J4
H12
H10H9
J5
H7 J3J2 P5H6
CLOCK119MHzRP N
RF Module
t
TemperatureMonitor
MATCHINGFILTERNETWORK
t
Control Board
TemperatureMonitor
SLOW ADCsPAC TempIQ TempSSSB TempSSSB P-FWDSSSB P-RFLSSSB PWR+5V-12V
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAC SSB Modulator Tests
PAC SSB Modulator TestsSN 3 May 5, 2006
-120
-110
-100
-90
-80
-70
-60
-50
-40
-30
-20
-10
0
475400000 475600000 475800000 476000000 476200000 476400000 476600000
Frequency
dB
m
58kHz lower side band test – Suppression of fundamental and opposite side band is better than 60dB.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAC Software
PACs can run in either CALIBRATING or RUNNING mode. A state machine keeps track.
If CALIBRATING, calibration waveforms are loaded into FPGA and I and Q gains and offsets can be adjusted.
If RUNNING, I and Q gains and offsets are fixed, operational waveforms are loaded into FPGA and I and Q adjustments can be applied at the operational frequency.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
VME
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
VME Software
Generic Feedback algorithm:Phase and amplitude are calculated from I and Q averages from each channel of the PADPhases are corrected by phase offset correctionAmplitudes are corrected by amplitude power correctionPhase and amplitudes are weighted by configurable weighting factors to determine one average phase and amplitudeLocal or global feedback corrections are appliedCorrected phase and amplitude is converted to I and QCorrected I and Q values are sent to PAC
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
VME SoftwareBeam Phasing Cavity algorithm (for Laser Timing):
Two sets of I and Q averages arrive (since there are two windows of interest)Phase1 is calculated from I1 and Q1Phase2 is calculated from I2 and Q2Measured beam phase is the y-intercept of the equation to the line of phase as a function of FIFO positionFrequency is the slope of the line Amplitude is calculated from I1 and Q1 (only)Phase is corrected by phase offset correctionAmplitude is corrected by amplitude power correctionLocal feedback corrections are appliedCorrected phase and amplitude is converted to I and QCorrected I and Q values are sent to laser PAC
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
VME Software
Other calculationsFor RF Reference Distribution
Phase and amplitude are calculated from I and Q averages from each channel of the PAD
Phases are corrected by phase offset correction
Amplitudes are corrected by amplitude power correction
Standard deviation of I and Q is calculated from I and Q variances from each channel of the PAD
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Linac Station 21-1 Tests
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Linac 21-1 Test Set-up
Linac Ref Amp
MDL
6x Multiplier 2830.5MHzGenerator
PAC
102MHz 2830.5MHz
PADCLK LO
CLK OUT
CLK
SSSB
ExistingIPA
5045 KLYSTRON
RF
IN1
RF
OU
T2
KlystronForward RF
Accelerator x3
SLED
New Equipment AddedFor Tests
Power Coupled out from 476MHz MDL drives a 476MHz Amplifier which feeds a 6X Multiplier from 476MHz to 2856MHz.
The 2856MHz out drives both the LO generator and the PAC.
The 2830.5MHz LO and 102MHz CLK Generator supplies the LO and CLK to the PAD. A CLK output of the PAD drives the PAC CLK.
The PAC output drives the SSSB.
The SSSB drives the existing IPA chassis
The klystron output coupler is used to measure phase and amplitude with the new PAD.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Linac 21-1 Test ResultsTests were done in the gallery with no temperature regulation on cables. Average RMS value of 2 second sliding average is 0.068 degrees.
Exponential Smoothing Yields the Following Results. Lowest noise is with a time constant of about 2 points.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
END of TALK
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
EPICS PANELS
Single Pulse Diagnostic Panels for PADs are RunningRemaining Software
History Buffer Select PVsMulti pulse data analysis, correlation plotsLocal RF Feedback loopsLinks to global Feedback loops
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
End of LLRF RF TalkBackup for RF Talk
Mostly Correct
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
DESIGN PHILOSOPHY
Reliability is inversely proportional to the number of connectors.
Stability is inversely proportional to the number of connectors.
Measurement accuracy is inversely proportional to the number of connectors and the amount of Teflon, which is typically found in connectors.
Cost of maintenance is proportional to the number of connectors.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Electro-Optical SamplingElectro-Optical Sampling
170 fs rms170 fs rms
Single-ShotSingle-Shot
Timing JitterTiming Jitter(20 Shots)(20 Shots)
200 200 m thick ZnTe crystalm thick ZnTe crystal
ee
Ti:Sapphire Ti:Sapphire laserlaser
Adrian Cavalieri et al., Adrian Cavalieri et al., U. Mich.U. Mich.
<300 fs<300 fs
ee temporal information is encoded on temporal information is encoded on transverse profile of laser beamtransverse profile of laser beam
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
MPS – PPS Issues Addressed by Controls Group
Not Reviewed Here Vacuum
New vacuum system summary to be fed to each klystron existing MKSU.
PPS SystemInjector modulators will be interlocked by Injector PPS system.PPS requirements for radiation from the injector transverse accelerator needs to be determined. Radiation levels will be measured during testing in the Klystron Test Lab – Feb 06.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Bandwidth of S-Band System
Upper Frequency Limit – 10MHzBeam-RF interaction BW due to structure fill time
< 1.5MHz S-Band Accelerators and Gun
~10MHz X-Band and S-Band T Cav
Structure RF Bandwidth ~ 16MHz
5045 Klystron ~ 10MHz
Lower Frequency Limit – 10kHzFill time of SLED Cavity = 3.5uS about 100kHz
Laser – Needs to be measured ~ 10kHz
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Noise LevelsRF Reference Single Side Band (SSB) Noise Floor
2856MHz RF Distribution -144dBc/Hz-174dBc/Hz @ 119MHz (24x = +28dB +2 for multiplier)
2830.5MHz Local Oscillator -138dBc/Hz
Integrated Noise-138dBc/Hz at 10MHz = -65dBc = 32fS rmsSNR = 65dB for phase noise
Added noise from MIXER (LO noise same as RF)SNR of 62dB
ADC noise levelsSNR of 70dB – 14bit ADS5500 at 102MSPS
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Phase Noise – Linac Sector 0
OLD MASTER OSCILLATOR-133dBc/Hz at 476MHz 340fSrms jitter in 10MHz BW
NEW MASTER OSCILLATOR-153dBc/Hz at 476 MHz34fSrms jitter in 10MHz BW
Integrated Noise - Timing Jitter fs rmsIntegral end 5MHz 10kHzIntegral start 1M 100k 10k 1k 100 10Aug 17, 2004Sector 30 27 30 33 38 75 82Jan 20, 2006Sector 21 15 19 20 20 8 17
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Sector 20 RF Distribution Cable ErrorsTemperature Coefficient of 2.8ppm/ºF and Cable length is 1200ºS/ftAll Cables except LASER are less than 100ft
Distances feet and errors in degrees S total range
RF Hut Down Linac Wall Injector TotalUnit Ft degS ft degS ft degS ft degS ft degS DegSLaser 8 0.054 25 0.017 10 0.014 10 0.007 85 0.58 0.68Gun 8 0.054 25 0.017 10 0.014 10 0.007 40 0.27 0.37L0-A 8 0.054 25 0.017 10 0.014 10 0.007 30 0.21 0.31B Phas 8 0.054 25 0.017 10 0.014 10 0.007 20 0.14 0.24L0-B 8 0.054 25 0.017 10 0.014 10 0.007 20 0.14 0.24L0-T 8 0.054 25 0.017 10 0.014 10 0.007 10 0.07 0.17L1-S 8 0.054 25 0.017 50 0.068 0.14L1-X 8 0.054 25 0.017 60 0.081 0.16Temperature Variations: RF Hut ±1ºF : Penetration ±0.1ºF : Linac : ±0.2ºF
Shield Wall ±0.1ºF : Injector ±1ºF
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
RF System Topology / Specifications
476MHz PLL2830.5MHz LOAmp / Splitter
Laser
RF Gun
L0A
Phase Cavity
L0B
L1S
L1X
L2 Ref
PAD
Laser
RF Gun
L0A
Phase Cavity
L0B
L1S
L1X
L2 Ref
Most Devicesare in tunnel
Laser
RF Gun
L0A
Phase Cavity
L0B
L1S
L1X
L2 Ref
1
Number of cables per deviceReference cables are8ft and can drift +-50fS
1
2
4
2
2
2
5
RF HUT
+-240fS
+-310fS
+-370fS
+-680fS
+-500fS
+-160fS
+-140fS
+-240fS
Cable Drift Based onTemperature variationsand temp co of 5ppm/degC
LinacSector 0 RF
MDL
L2 - 4 SectorsSpecifications70fS rms jitter+-5pS drift
L3 - 6 SectorsSpecifications150fS rms jitter+-5pS drift
L0, L1 - 5 KlystronsSpecifications100fS rms jitter+-2.3pS drift
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
RF Monitor Signal CountsADC Chan Cnt Chassis
Count/LocationDistribution (5~2850MHz, 4<500MHz) 4 1HutRF Gun 9 1Kly 1.5HutBeam Phase Cavity 2 0.5HutL0-A Accelerator 4 1Kly 0.5HutL0-B Accelerator 4 1Kly 0.5HutL0-T Transverse Accelerator 4 1Kly 0.5HutL1-S Station 21-1 B, C, and D Acc 6 1Kly 1.0HutL1-X X-Band accelerator X-Band 5 1Kly 0.5HutS25-Tcav 4 1KlyS24-1, 2, & 3 Feedback 0S29 and S30 Feedback 0
Total Chassis 7Kly 6HutTotal into Hut IOC 12
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
RF Control Signal CountsDistribution (3~2850MHz, 3<500MHz) 6 IQ ModRF Gun 1 Klystron Beam Phase Cavity 1 IQ modL0-A Accelerator 1 KlystronL0-B Accelerator 1 KlystronL0-T Transverse Accelerator 1 KlystronL1-S Station 21-1 B, C, and D accelerators 1 Klystron
L1-X X-Band accelerator X-Band 1 IQ ModS25-Tcav 1 KlystronS24-1, 2, & 3 Feedback 3 KlystronsS29 and S30 Feedback 2 IQ modulators 476MHz
Total modulators 11 Fast 8 Slow 19 modulatorsTotals at ~2856MHz 14 modulatorsTotal into Hut IOC 14 modulators
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
LLRF Control and Monitor System
LLRF Control and Monitor System1 kW Solid State S-Band Amplifiers – 5 units
Phase and Amplitude Monitors – 12 units
Phase and Amplitude Controllers – 6 units
Bunch Length Monitor Interface – Need Specifications
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
RF Control
RF Control Module consist of the following:
Input Coupler, IQ Modulator, Amplifier, Output Coupler
Filters for I and Q inputs
I
RFLO
Q
1
2
34
BXMP1007
2856MHz Input Monitor 2856MHz Output Monitor
Q Control
RF InRF Out
I Control
17dBm 0dBm
2850MHz IQ Modulator
17dBm
Required 13 UnitsIncludes Distribution
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
RF MonitorRequired 13 Chassis for Injector – Includes DistributionLO 2830.5MHz : RF 2856MHzIF 25.5MHz (8.5MHz x 3 in sync with timing fiducial)Double-Balanced MixerMixer IF to Amp and then Low Pass FilterFilter output to ADC sampling at 102MSPS
MIXER
LOR
F IF
Amplifier
25.5MHz BP FILTER
2830.5MHz Local Osc.
2856MHz RF Signal
To ADC
LTC2208 SNR = 77dBFS
102MSPS
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
1 kW Solid State S-Band Amplifiers
Design Complete Two Units on the ShelfModules in house – and testedSupport parts – Some parts in house
Power Supplies, relays, chassis on order
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
SLAC Linac RF – New ControlThe new control system will tie in to the IPA Chassis with 1kW of drive power available. Reference will be from the existing phase reference line or the injector new RF reference
I and Q will be controlled with a 16bit DAC running at 119MHz. Waveforms to the DAC will be set in an FPGA through a microcontroller running EPICS on RTEMS.
Existing System Accelerator
Klystron
Next Sector
MDL 476MHz
SubBooster
6 X2856MHz
Sub Drive Line
High PowerPhase ShifterAttenuator
SLED
Phase &AmplitudeDetector
ExistingPhaseReferenceLine
-45dB200MW
3kW
20mW
1W1mW
To NextKlystron
I
RF LO
Q
1
2
3
4
IQ Modulator
1kW Amp2856MHz
IPA
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Controls Talk
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
LLRF Controls
OutlineRequirementsExternal InterfacesSchedule
Date NeededPrototype Completion DateHardware Order DateInstallationTest Period
Design Design Maturity (what reviews have been had) State of Wiring Information State of Prototype
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Requirements
At 120 Hz, meet phase/amp noise levels defined as:
0.1% rms amplitude 100 fs rms in S-band (fill time = 850 ns) 125 fs rms in X-band (fill time = 100 ns)All tolerances are rms levels and the voltage and phase tolerances per klystron for L2 and L3 are Nk larger, assuming uncorrelated errors, where Nk is the number of klystrons per linac (L2 has 28; L3 has 48)
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Engineering Requirements
When beam is present, control will be done by beam-based longitudinal feedback (except for T-cavs); when beam is absent, control will be done by local phase and amplitude controller (PAC)
Adhere to LCLS Controls Group standards: RTEMS, EPICS, Channel Access protocol
Ref: Why RTEMS? Study of open source real-time OS
Begin RF processing of high-powered structures May 20, 2006
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
External Interfaces
LLRF to LCLS global control system PVs available for edm screens, archiving, etc over controls network
LLRF VME to beam-based longitudinal feedback from feedback: phase and amplitude corrections at 120 Hz over private ethernet from LLRF: phase and amplitude values
(internal) LLRF VME to LLRF microcontrollers from VME: triggers, corrected phase and amplitude from microcontrollers: phase and amplitude averaged values at 120 Hz, raw phase and amplitude values for debug
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
External Interfaces: Laser - Tcav
I and Q Demo-dulator
CPU
FIFOs
DAC
slow
Temperature monitors
EVR
Laser and RF ref
L0-AL0-B
L1-SL1-X
T Cav
gun
Controls gigabit ethernet (interface to MCC)
Private ethernet8 kBytes at 120 Hz
PAD
ADC
FPGADAC
1 trigger for 4
channels of 1k
samples
Private ethernet4 kBytes at 120 Hz
In-house modules sharing VME crate for timing triggers
476 MH
z RF R
eferen
ce clo
ck dis
tribute
d to all
30 se
ctors i
n the L
inac a
nd bey
ond
RF Reference/4 = 119 MHzstabilized to 50 fs jitter
RF Reference*6 = 2856 MHzstabilized to 50 fs jitter
Coldfire CPU
running RTEMS
and EPICS
Coldfire CPU
running RTEMS
and EPICS
PAC
RF Phase and Amplitude correction at 120 Hz for:laser, gun, L0-A, L0-B, L1-S, L1-X, T cav
10' accelerator
IQ Modulator gives phase
and amplitude control
1 kW 1 kW
Solid State Sub Booster
Klystron
SLED cavity
60 MW
HPRF240 MW
60 MW
1 kW
All except laser RF
100 mW
119 MHz Laser
Oscillator
Amps
GunNB: For the gun, SLED
cavity is shorted out
119 MHz120 Hz
UV
photodiode
photodiode
1 trigger to travel up to ½ sector
away
DAC
slow
VME Crate at S20 running
longitudinal, beam-based
feedback
Private ethernet
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
External Interfaces: L2-L3
I and Q Demo-dulator
CPU
FIFOs
DAC
slow
Temperature monitors
EVR
Laser and RF ref
L0-AL0-B
L1-SL1-X
T Cav
gun
Controls gigabit ethernet (interface to MCC)
Private ethernet8 kBytes at 120 Hz
PAD
ADC
FPGADAC
1 trigger for 4
channels of 1k
samples
Private ethernet4 kBytes at 120 Hz
In-house modules sharing VME crate for timing triggers
476 MH
z RF R
eferen
ce clo
ck dis
tribute
d to all
30 se
ctors i
n the L
inac a
nd bey
ond
RF Reference/4 = 119 MHzstabilized to 50 fs jitter
RF Reference*6 = 2856 MHzstabilized to 50 fs jitter
Coldfire CPU
running RTEMS
and EPICS
Coldfire CPU
running RTEMS
and EPICS
PAC
RF Phase and Amplitude correction at 120 Hz for:laser, gun, L0-A, L0-B, L1-S, L1-X, T cav
10' accelerator
IQ Modulator gives phase
and amplitude control
1 kW 1 kW
Solid State Sub Booster
Klystron
SLED cavity
60 MW
HPRF240 MW
60 MW
1 kW
All except laser RF
100 mW
119 MHz Laser
Oscillator
Amps
GunNB: For the gun, SLED
cavity is shorted out
119 MHz120 Hz
UV
photodiode
photodiode
1 trigger to travel up to ½ sector
away
DAC
slow
VME Crate at S20 running
longitudinal, beam-based
feedback
Private ethernet
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
DesignDesign maturity (what reviews have been had):
RF/Timing Design, DOE Review, August 11, 2004 Akre_FAC_Oct04_RF_Timing, FAC Review, October, 2004 Low Level RF Controls Design, LCLS Week, January 25-27, 2005 Low Level RF, Lehman Review, May 10-12, 2005 LLRF Plans for Development and Testing of Controls, LCLS Week, July 21, 2005 Low Level RF Design, Presentation for Controls Group, Sept. 13, 2005 LLRF Preliminary Design review, SLAC, September 26, 2005 LCLS LLRF Control System - Kotturi, LLRF Workshop, CERN, October 10-13, 2005 LCLS LLRF System - Hong, LLRF Workshop, CERN, October 10-13, 2005 LLRF and Beam-based Longitudinal Feedback Readiness - Kotturi/Akre, LCLS Week, SLAC, October 24-26, 2005 LCLS Week LLRF and feedback - Kotturi/Allison, LCLS Week, SLAC, October 24-26, 2005 LLRF, LCLS System Concept Review/Preliminary Design Review, SLAC, November 16-17, 2005 Comments LLRF Beam Phase Cavity Preliminary Design review, SLAC, November 30, 2005
Docs at: http://www.slac.stanford.edu/grp/lcls/controls/global/subsystems/llrfState of wiring: percent complete Captar input will be given at time of presentation State of prototype: PAD (1 chan ADC) and PAC boards built (shown on next pages).Testing.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAD – the monitor board
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAD – the monitor board
2 X 16 bit ADC119 or 102MHz ClockLTC2208Transformer Coupled Inputs
Chan. 2
Chan. 1
FIFO 2 X 1k words
WCLK
16bit DATA
16bit DATA
WCLK
RF CHAN 1INPUT
RF CHAN 2INPUT
Line DriversFilters
MIXER
LORF
IF
MIXER
LORF
IF
RF Board
25.5MHz IF
Control Board
Control
EXTERNALTRIGGER120Hz
EXTERNALCLOCK102MHz
CS/CLK
16 bitDATA
CONTROL /Arcturus uC5282Microcontroller Modulewith 10/100 Ethernet
ET
HE
RN
ET
LO INPUTRF - 25.5MHz
CPLD
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAC – the control board
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
PAC – the control board
SSSBChassis
Temperature MonitorForward Power 0-?VReflected Power 0-?VOver Temp 0 or 12V Power Supplie +12VPower Supply -12V
I
R F L O
Q
I&Q MODULATOR
1
2
3
4
MAX58752 X 16 bit DAC119MHz Clock(1MHz to 200MHz)
I
Q
XILINXSPARTAN 3FPGA
16bit DATA
CS/CLK
16bit DATA
16 bitDATA
CLK
CLK CONTROL /Arcturus uC5282Microcontroller Modulewith 10/100 Ethernet
ET
HE
RN
ET
Control Control
RF OUTPUTTo SSSB
TRIGGERMonitor TTL
EXTERNALTRIGGER120Hz60nS NIM
2856MHz Ref
MONITORPORTS
AD8099 Diff Amp
SSSBTrigTTL17 to 30uS
Thermocouples
CLOCK119MHz
RF BOARD
t
MATCHINGFILTERNETWORK
TemperatureMonitor t
DC PowerSupplies
DC PowerSupplyMonitors
Control BoardADCs
TemperatureMonitor
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Additional Slides
The following two pages show an overview of the LLRF control modules. From these diagrams, counts of module types, as well as function and location are seen.
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Eth recvr
EVR
VME Crate at S20 running
longitudinal, beam-based
feedback.
CPU
PAC
Gun
PADPADPAD
SPAC
RF Dist’n
Laser
PAC
L0-B
PADPAD
PAC
L1-S
PADPAD
PACL0-Tcav
PADPAD
PACL0-A
PADPAD
SPAC
PAD
PAD PAC
Beam Phase Monitor
PAD
SPACSPACSPAC
SPACPAD
Fast PACs: Slow PACs (SPACs): PADs: VME crates:
RF phase and amplitude correction and global feedback at 120 Hz for LCLS LINAC S20
PAC
L1-X
PADPADPAD
PAD
PAC
Key:
Indicates may be needed
86191
S20
The maybe is included in counts below
Indicates located in RF HutOtherwise at Klystron
Overview of LLRF at Sector 20
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Overview of LLRF at Sector 24
Fast PACs: Slow PACs (SPACs): PADs: VME crates:
Eth recvr
EVR
CPU
PAC
L24-1
PACL24-2
PACL24-3
PACTcav L24-8
SPAC
S29
SPAC
S30
PADPAD
VME Crate at S24 running
longitudinal, beam-based
feedback.
4221
S24
RF phase and amplitude correction and global feedback at 120 Hz for LCLS LINAC S20
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Beam Phase MonitorR. Akre
A. Haase
B. Hong
D. Kotturi
V. Pacak
H. Schwarz
Preliminary Design Review
November 30, 2005
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Outline
•Purpose
•Specifications
•System outline
•Cavity
•Noise Levels
•Analysis
•Long Term Drifts
•Summary
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Laser Timing Stabilization Feedback
Beam timing information from the beam phase monitor will be used to apply corrections to the timing of the laser on the RF Gun.
PHAS AMPL
TOROID
BUNCH CHARGE
BEAM PHASE CAVITY
GUN RF FEEDBACK
InputsGUN-CELL1-PHAS/AMPLGUN-CELL2-PHAS/AMPL
ActuatorsGUN RF ACTUATORS
2856MHz R ef
GUN RF ACTUATORS
LCLS RF Oscilla tor
LINAC MDL Ref.
GUN RF REF.
LASER RF R EF.
PHAS
PHASEERROR
ActuatorL0, L1 to L2, L3Phase
LASER POWERACTUATOR
OUT
GUN-CELL2
GUN-CELL1
KLYSTRONAMPLIFIER / SLC CONTROL
LASER OSC
Reference
LASER PHASE & AMPLITUDE?
LASER AMPLIFIER
LASER OSC. PHASE
WATER TEMP
RF GUN
LASER PHASE ACTUATOR
LASER OSCILLATOR PHASEFEEDBACK
InputsBEAM PHASE CAVITY
ActuatorsLASER PHASE ACTUATOR
PHASE ERROR BetweenL0, L1 and L 2, L3
AMPL
LASER OSCILLATOR PHASEand LASER POWERFEEDBACK
InputsLASER OSC. PHASEBUNCH CHARGEGUN-CELL1-AMPL/PHASGUN-CELL2-AMPL/PHASLASER PHASE & AMPLITUDEGUN RF ACTUATORSBEAM PHASE CAVITY
ActuatorsLASER POWERLASER PHASE ACTUATOR
GUN TUNE FEEDBACK
InputsGUN-FOR-PHASGUN-CELL1-PHASGUN-CELL2-PHAS
ActuatorsWATER TEMP
GUN-FOR
2856MHzRF REF.
LASER
GUN
L0A
L0B
L0-TCAV1
L1-X
L1-S
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Specifications
Short term (2 second) timing jitter: 100fS rms
Long term (4 day) timing jitter: ±1pS
Range of the above accuracies is ±10pS
Data available at 120Hz
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
System Outline
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Cavity
Frequency = 2856MHz
Q = 6000
Time Constant = 700nS
Temperature Coefficient = 50kH/°C
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
System Critical Noise Levels and Bandwidths
Cavity Signal – Bandwidth 500kHz
Local Oscillator – Noise Floor –143dBc/Hz
IF Filter – Bandwidth 4MHz
ADC – SNR at input 76dB
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
System Critical Noise Levels and Bandwidths
2830.5MHz Oscillator
1
Beam Phase Cavity
Attenuator
Monitor Port
Coupler
MIXER
LO
RF
IF
Monitor Port
In TunnelAmp
Filter - Butterworth3rd order BandPass2.5.5MHz Center4.0MHz BW2dB IL at 25.5MHz
30dBm pk
ADC LTC22082.25Vpp FSTransformer coupled102MHz Clock
30dBm pk
Attenuator
3dBm pk23dBm pk
2Vpp 10dBm pk
13dBm
-3dBm pk 17dBm pk
-130dBm/Hz-143dBc/Hz
-174dBm/Hz-174dBm/Hz
-129dBm/Hz-143dBc/Hz
-146dBm/Hz-143dBc/Hz Within filters BW
-135dBm/Hz-143dBc/HzBeyond 5MHz from CF<-155dBm/Hz<-163dBc/HzIntegrated Noise-77dBc
Generated from 119MHz OscillatorExpected SSB Phase Noise LevelsOffset Hz dBc/Hz @ 2830.5MHz10 -82100 -961k -12410k -14420k -146
ADC SNR 77dBFS
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
ADC Linear Technologies LTC2208
16Bit 130MHz
SNR 77.6dBFS 30MHz in Clock 130MHz SFDR 95dB
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
AnalysisPhas
e
Calculated Beam Phase at Beam Time
Measured Data Point 1
Measured Data Point 2
Time
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
I & Q from WaveformDigital Down Mixing and Normalization
0 10 20 30 40 50 600.6
0.4
0.2
0
0.2
0.4
0.6
0.8
125.5MHz Digitized Signal
Point Number
Fra
ctio
n A
DC
Ful
l Sca
le
.
Digitized
Input Signal
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Optimization
Optimal Points to use for analysis is 16 point average at points 18 and 120
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Analysis Results
Standard deviation of result = 1.1e-4 or 6.3fS rms jitter
Signal level 20dB lower will give 63fS rms jitter
Sensitivity to frequency change = 0.6fS/2.8kH freq change
Sensitivity to timing change over +-10deg = 1:1
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
80ft (1M deg) of ½ inch superflex has TC of 4ppm/degCWater temp tolerance is +-0.1degF = +-400fS drift
Long Term Drifts
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Summary
Short term (2 second) timing jitter: 100fS rms
63fS rms
Long term (4 day) timing jitter: ±1pS
±0.8pS
Range of the above accuracies is ±10pS
Results
Data available at 120Hz
Simple algorithm in integer arithmetic will allow this
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Feedback Page 1
LOCAL FEEDBACK
LOCAL FEEDBACK
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Feedback Page 2
LOCAL FEEDBACK
GLOBAL FEEDBACK
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Feedback Page 3LOCAL FEEDBACK
LOCAL FEEDBACK
GLOBAL FEEDBACK
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Feedback Page 4GLOBAL FEEDBACK
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Feedback Page 5GLOBAL FEEDBACK
Ron Akre, Dayle Kotturi
LCLS LLRF Review [email protected], [email protected]
September 19, 2006
Feedback Page 6