23
John Seeman LCLS ARR [email protected] du December 2, 2008 1 Conduct of LCLS Accelerator Operations John Seeman Assistant Director LCLS Directorate Head of the Accelerator Systems Division LCLS Directorate

John Seeman LCLS [email protected] December 2, 2008 1 Conduct of LCLS Accelerator Operations John Seeman Assistant Director LCLS Directorate

Embed Size (px)

Citation preview

John Seeman

LCLS ARR [email protected]

December 2, 20081

Conduct ofLCLS Accelerator Operations

John Seeman

Assistant Director LCLS Directorate

Head of the Accelerator Systems Division

LCLS Directorate

John Seeman

LCLS ARR [email protected]

December 2, 20082

Accelerator System Division

Maintenance management

Down time planning

Overall schedule

Scheduling beam time

Delivered beam specification

Topics

John Seeman

LCLS ARR [email protected]

December 2, 20083

Accelerator Systems Division (ASD)

ASD has operated accelerators at SLAC for well over 30 years. The accelerators are:

Linac (50 GeV)PEP-ISPEAR-I and IISLCPEP-IIFFTBLCLS Injection and Linac

Programs, training, and documentation in place to carry out the programs carefully, safely, and with full technical rigor.The staff is trained to carry out these programs, holding all accelerators to the same standards.Formal procedures are in place to deal properly with DOE safety standards, Operations Directives, and the Citizen Committees.

John Seeman

LCLS ARR [email protected]

December 2, 20084

ASD Documentation

Guiding documents:SLAC Guidelines of Operations (Under constant updating)ASD Operations DirectivesLCLS/LINAC SADLCLS/LINAC ASEAccelerator Safety Assessment DocumentsES&H documentationUn-reviewed Safety Items (USI) handled by Guidelines of Operations and LCLS SADASD Operational documents

John Seeman

LCLS ARR [email protected]

December 2, 20085

USIs

LCLS SAD:Safety issues that are not covered in the above documentation, and for which a safety analysis has not been performed, could arise. Such an issue would constitute an Unreviewed Safety Issue under DOE Order 420.2B Section 4c. Activities that involve unreviewed safety issues must not be performed if significant safety consequences could result from either an accident or a malfunction of equipment that is important to safety. Such activitites would be formally reviewed and be subject to the approval of the appropriate safety officers and citizen safety committees, as required by SLAC Guidelines for Operations. Activities involving identified unreviewed safety issues must not commence before DOE has provided written approval.

A Working Group has been formed as follow up to the DOE ISMS Effectiveness Review in August 2008 with the aim of improving USI definition at SLAC with inputs from other laboratories programs with the target of Spring 2009.

John Seeman

LCLS ARR [email protected]

December 2, 20086

Authorization of operating the Linac Related Accelerators at SLAC follow the organization of the SLAC laboratory:

SLAC DOE Site Office

Laboratory Director

Deputy Directors for LCLS

Head of the Accelerator Systems Division

Head of the Operation Group

Engineering Operator In Charge (EOIC) in the Control Room

Operations Authorization

John Seeman

LCLS ARR [email protected]

December 2, 20087

ASD Staff

Admin: 4Safety office: 1Physicists: 9Mechanical engineers: 3Operations and reliability: 2Operators: 23Area managers: 7Technicians: 3Total = 52

John Seeman

LCLS ARR [email protected]

December 2, 20088

LCLS beam:

4 to 14 GeV e- beam to 120 Hz to 1 x 1010

Linac capabilities (if needed):

e- to 49 GeV at 120 Hz at 2 x 1010

e+ to 49 GeV at 120 Hz at 2 x 1010

Linac Operating Modes in FY2009

John Seeman

LCLS ARR [email protected]

December 2, 20089

Main Control Center for LCLS Operations

John Seeman

LCLS ARR [email protected]

December 2, 200810

Program Deputy• Duty rotates among Accelerator Division physicists.• Oversees program for 3 or 4 day period.• Not always present in the control room.

Operations Engineer• 1 EOIC per shift (from a group of 7), on rotating 7-week cycle. • Responsible for safely carrying out the scheduled program.• Exempt position; directs the Accelerator Systems Operators.• Must be present if accelerator is capable of producing beam.• All have experience as accelerator systems operators.

Accelerator Systems OperatorsTypically 3 operators per shift on rotating 5-week cycle:

Control Room Staffing

John Seeman

LCLS ARR [email protected]

December 2, 200811

Operators are trained to carry out certain well-defined tasks, following formally controlled procedures.

Examples:

• Interlock Checklists

• Search Procedures

• Entry and Exit Procedures

• Safety Inspection Checklists

Safety procedures:

• undergo a formal review and approval process.

• are updated as conditions change.

• are available on the AD Documentation web site, although the signed originals are preserved in paper form

Completed checklists and log books are archived.

Operator Safety Procedures

John Seeman

LCLS ARR [email protected]

December 2, 200812

8:00 Meeting every day, seven days a week, in MCC conference room.• Operations report by EOIC, including run time statistics, progress in

carrying out scheduled program, descriptions of problems, etc.• Reports by representatives of major experimental user groups.• Attended by PPA, Accel Div, and Operations management reps, Program

Deputy, System Physicists, Area Managers, and representatives of user groups and major technical support departments; typical attendance: 45 persons.

8:15 Maintenance Meeting, five days each week.• Run by Accelerator Operations Department maintenance managers.• Attended by supervisors of all maintenance groups, Area Managers, and

interested physicists and engineers.• Attendance: typically 45 persons.

Accelerator Plans Meeting, weekly.• Review of operational progress, problems, and plans.• Attended by Accel Systems Div and Dept Heads, Program Coordinators,

Accelerator Section Heads and ADSO.

Planning with Accelerator Users and Maintenance Staff

John Seeman

LCLS ARR [email protected]

December 2, 200813

Planned Maintenance Days• Whenever possible, identified maintenance, repair, and installation jobs

are pre-planned. • Coordination• Daily 8:15am meeting.• Coordinated by Operations Maintenance Office.• Area Managers are advocates for their areas.

Standby Maintenance List (SML)• Jobs that are planned and can be launched on short notice.• Provides options for EOIC to take advantage of unscheduled

interruptions.• ARTEMIS/CATER Electronic Database records items.

Accelerator Maintenance

John Seeman

LCLS ARR [email protected]

December 2, 200814

ARTEMIS (Accelerator Remedy Trouble Entry and Maintenance Information System) is an Oracle database with a Remedy interface, accessible over the internet by everyone involved with SLAC accelerator maintenance.

Operators report problems as they occur by making entries in ARTEMIS.

Repair work is launched immediately if the problem is inhibiting the scheduled accelerator program.

Jobs are tracked using ARTEMIS until they are finally closed.

ARTEMIS entries since Jan 1989: ~84000.

ARTEMIS entries in one year (2006):

• 3166 new problems (8.7 per day).

• 3296 problems closed (9.0 per day).

ARTEMIS/CATER

John Seeman

LCLS ARR [email protected]

December 2, 200815

Long Down Times usually occur once each year and typically last two to three months.

Area Managers collect job requests from system physicists, project engineers, maintenance groups, and the ARTEMIS database.

A comprehensive schedule is prepared, updated, and reviewed at weekly meetings, starting about four months before the down time.

This schedule lists each job with an assigned shop, and lists the Project or Group Manager, Responsible Task Person, and Area Manager.

Schedule specifies time and duration of each job (with 1 day time resolution), and number of persons required.

Schedule specifies authorizations required (WAF, RSWCF, EWP, etc.).

Detailed (shift by shift) schedule of pre-run testing, safety certifications, and turn-on activities is prepared by the Operations Dept and revised as needed on a real-time basis.

Long Down Time Planning

John Seeman

LCLS ARR [email protected]

December 2, 200816

Accelerator Improvement Projects (AIP)

John Seeman

LCLS ARR [email protected]

December 2, 200817

John Seeman

LCLS ARR [email protected]

December 2, 200818

Goal for what typical LCLS operations will look like in two years.

John Seeman

LCLS ARR [email protected]

December 2, 200819

Re-establishRe-establishee to SL2 to SL2

LTU/LTU/UndUnd

Comm. Comm.

Firs

t Li

ght

in

Firs

t Li

ght

in

FEE

FEE

Firs

t Li

ght

in F

EH

Firs

t Li

ght

in F

EH

NEH Ops & NEH Ops & CommissioningCommissioning

JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS OOOO NNNN DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJOONNAA

2008 2009 20102008 2009 2010 2008 2009 20102008 2009 2010DownDownPPS

PPS

Linac/BC2 Linac/BC2 CommissioninCommissionin

g g FEL/FEEFEL/FEECommissioniCommissioni

ng ng Nov. 3, 2008Nov. 3, 2008

Inst

all

Inst

all U

ndula

tors

Undula

tors

MMDD

LCLSLCLS Installation and Commissioning Time-Line Installation and Commissioning Time-Line

LTU

/Und

In

stall

LTU

/Und

In

stall

PEP-I

I ru

n

PEP-I

I ru

n

ends

ends

FEE/N

EH

In

stall

FEE/N

EH

In

stall

PPS C

ert

. LT

U/D

um

pPPS C

ert

. LT

U/D

um

p

CD-4

CD-4

(7

/31

/201

0)

(7/3

1/2

01

0)

X-R

ays

in N

EH

X-R

ays

in N

EH

no

wn

ow

DDDown?Down?

FEH

Hutc

h B

OFE

H H

utc

h B

O

John Seeman

LCLS ARR [email protected]

December 2, 200820

John Seeman

LCLS ARR [email protected]

December 2, 200821

X-ray User Performance Drivers for ASD

Reliable operation with high uptime (>95%).

Steady beam parameters when operating.

Rapid but reasonable change of beam parameters when needed by the user.

Maintain alternate user programs when expected user program changes.

John Seeman

LCLS ARR [email protected]

December 2, 200822

Proposed Initial Beam Parametersfor Users

Early ops MatureElectron energy 4.3 GeV 4.3 GeV

Repetition rate 30 Hz 120 Hz

Bunch length 200 fs FWHM 200 fs FWHM

FEL peak power 500 MW 5 GW

FEL bandwidth 0.25% 0.2%

Energy per pulse 0.1 mJ 2 mJ

Photons/0.1%BW 3 1011 1 1013

Peak brightness 3 1030 3 1031

Average brightness 2 1019 2 1021

J. Galayda

John Seeman

LCLS ARR [email protected]

December 2, 200823

Linac operations are managed by the Accelerator Systems Division under the LCLS Directorate.Documented policies and procedures exit for all safety-related activities.Maintenance and installation work is accomplished through a matrix organization, drawing on engineers, technicians, and ES&H and shop services from the ETS Directorate.We have developed organizational structures, software tools, and documentation that enable us to manage an ambitious accelerator-based science program safely and effectively.A beam-time scheduling mechanism is being developed to resolve operational beam parameter specifications and changes.We are ready to operate the LCLS LTU, Undulator, and e- Beam Dump.

Conclusions