34
Pro-active Transmission Development: Bringing Benefits Online — Sooner Craig Cox Interwest Energy Alliance 18 September 2006

COX_TransmissionTF18

  • Upload
    mike97

  • View
    169

  • Download
    0

Embed Size (px)

Citation preview

Page 1: COX_TransmissionTF18

Pro-active Transmission Development:

Bringing Benefits Online — Sooner

Craig CoxInterwest Energy Alliance

18 September 2006

Page 2: COX_TransmissionTF18

Wind Energy: Providing Benefits to Colorado’s Consumers

• 2001: PUC orders development of Lamar windfarm, citing its potential rate benefits

• 2003: Xcel says that this 162MW project would save $4.6 million annually

• 2006: Xcel reports that wind saved its consumers $9.75 in 2005

• 2006: Interwest study reports anticipated savings of $251 million over next 20 years.

Page 3: COX_TransmissionTF18

Wind Energy: Providing Tangible Rural Economic Development Benefits

• In 2004, the 162MW Colorado Green project in Prowers County provided:– $884,000/year: new county revenues– $917,000/year: School General Fund– $235,000/year: School Bond Fund– $218,000/year: Prowers Medical Center– 26% Increase in County Tax Base– Tremendous Support from Community

Page 4: COX_TransmissionTF18

Colorado Wind Energy1998 to 2005…up to 2007

0

200

400

600

800

1000

1200

1998 1999 2000 2001 2002 2003 2004 2005 2006 2007

Page 5: COX_TransmissionTF18

Colorado Wind Energy1998 to 2005…up to 2007

0

200

400

600

800

1000

1200

1998 1999 2000 2001 2002 2003 2004 2005 2006 2007

Page 6: COX_TransmissionTF18

Current Colorado projects

Colorado Green, 162 MW, 2003

Ponnequin, 32 MW, 1999-2001

Peetz, 30 MW, 2001

Lamar, ARPA and Springfield, 7.5 MW, 2004

Spring Canyon, 60 MW, 2005

Total = 292 MW

Page 7: COX_TransmissionTF18

New projects, 2006-7

• 300 MW in Grover (Weld County)• 200-400 MW in Peetz• 75 MW in SE Colorado

Page 8: COX_TransmissionTF18

Hindrances to Wind Energy

• It’s a “new” technology• Perceived higher costs until

recently• Unfamiliar to many utilities and

consumers until recently• TRANSMISSION

Page 9: COX_TransmissionTF18

Xcel cites transmission hindrances

“PSCo was unable to obtain cost-effective third party transmission necessary to reliably deliver the full output of the facility to the PSCo transmission system. As a result, it was necessary to reduce the size of this proposed project [Invenergy] from 130 MW to 60 MW so that all of the energy could be delivered on existing PSCo facilities or under existing contractual arrangements.”

From “PSCo 2004 Renewable Energy RFP:Report on Winning Bids,” issued 24 March 2005

Page 10: COX_TransmissionTF18

Further transmission hindrances cited by Xcel

“…limitations were also identified for projects that proposed to interconnect at the Lamar substation in southeast Colorado. These limits applied to five wind bids that proposed to interconnect over 1,000 MW of wind at the Lamar substation…At some point, additional power injections at Lamar will require transmission upgrades that would take at least 53 months to complete. Accordingly, the larger Lamar-based wind projects (i.e., larger than 75 MW) were set-aside from further consideration.”

This was based on a 2007 in-service date for the wind bids, and transmission could not be completed in time for those bids.

However, in NE Colorado, Xcel is adding 400 MW of wind at Pawnee and redispatching gas units as necessary to deliver the full output of the wind. This is an excellent example of siting wind and peaking gas so that they utilize the same transmission paths.

Quoted language from “Public Version” All-Source RFP Bid Evaluation Report, December 2005,

available at http://www.dora.state.co.us/puc/docket_activity/filings/05A-543E_PublicAll-SourceBidEvaluationReport.pdf

Page 11: COX_TransmissionTF18

Curtailment Payments, 2004

In 2004, in Colorado PUC Docket No. 04A-214-216E, PSCo reported that its transmission system (particularly in the TOT 3 area) was insufficient to bring all cost-effective wind energy resources to market to offset high natural gas prices. Thus, the PUC approved curtailment payments to address this deficiency.

Curtailment payments have not been needed to this date.

Page 12: COX_TransmissionTF18

Public Support for New Transmission, and Creative Thinking

• Transmission “compared to what”• Need to exploit non-wires solutions, use

existing lines more efficiently, upgrade existing routes, build intra state and two state routes to open options for multi state lines

• Consider the “NIMBY” case

Page 13: COX_TransmissionTF18

Transmission and Wind Energy

A classic chicken and egg problem…

Page 14: COX_TransmissionTF18

Typical Construction Time for Large Wind Project: 1-2 Years

Page 15: COX_TransmissionTF18

Typical Time to Complete Transmission Facilities: 5+ Years

Page 16: COX_TransmissionTF18

Cost of Delay

3,066,000,000 153,300,000 15,330,000 5,000

269,808,000

13,490,400 1,349,040 440

122,640,000

6,132,000 613,200 200

613,200

30,660 3,066 1

$ for 20 years$/yr @

$10.00/MWhMWh/yr @ 35% NCF

MW

Page 17: COX_TransmissionTF18

How to Overcome Wind and Transmission Time Mismatch?

• Texas and Minnesota offer two excellent recent examples.

• Let’s look at what Texas did last year with SB 20…

Page 18: COX_TransmissionTF18

Texas SB20: Facilitating Transmission

Provides Special Transmission Provisions for RPS• Transmission supporting RPS is recoverable in rates• PUC “shall require” transmission to meet RPS• Expedited CCN (6 months)

Fixes chicken-and-egg problem• PUC designates best development zones throughout Texas• Transmission planned to zones (built using special provisions)• “Consider” financial commitment of generators• Simplified CCN Process

Long-Term Transmission & Capacity Needs• For conventional resources and renewables

Page 19: COX_TransmissionTF18

CREZ Proactive Transmission Approach

1. Identify the Best Resource Zones

2. Develop a Transmission Master Plan

3. Begin Building Transmission to Zones

Thanks to Mike Sloan of The Wind Coalition (www.windcoalition.org) for information on the

Texas CREZ experience

Page 20: COX_TransmissionTF18

#1 - Identify the Best Wind Zones

Page 21: COX_TransmissionTF18

Windy Counties

Page 22: COX_TransmissionTF18

MEDIAN CAPACITY FACTOR (%)(Of the best 2,000 MW in zone;

* = less than 2,000 MW of total potential)

DRAFT

34 *

34 *38 *

37 *

37

39 *

42 44

44

37 35

38

35

3535

39

37

32 (???)

4442

404136

44

40

Based on AWS wind data from ERCOT

Page 23: COX_TransmissionTF18

Initial Groupings of Wind Resources

By AWS Truewind

Page 24: COX_TransmissionTF18

4000 MW AreasEach color represents approximately 4,000 MW of wind generation potential

ERCOT will reduce to 6 to 8 candidate zones & provide wind data

Page 25: COX_TransmissionTF18

#2 - Develop Transmission Master

Plan

Page 26: COX_TransmissionTF18

Preliminary Areas for ERCOT Transmission

Analysis4

2

7

1410 12

6

5

24

9

10 = Area Proposed by ERCOT to Study Transmission Upgrades

Page 27: COX_TransmissionTF18

CREZSelection(ILLUSTRATIVE)

Hypothetical

CREZ Package to achieve a total of

10,000 MW1,500

1,5002,500

1,500

1,500

1,500

Page 28: COX_TransmissionTF18

• 3,000

• 2,000• 2,000

• 2,000• 3,000

• 3,000

• 3,000

• 2,000

Hypothetical

CREZ Package to achieve a total of

20,000 MW

CREZ PLAN(ILLUSTRATIVE)

Page 29: COX_TransmissionTF18

#3 - Build Transmission to

Zones

Page 30: COX_TransmissionTF18

ERCOT’s OLD Approach - Did NOT Work

Page 31: COX_TransmissionTF18

PUC Strawman (Original) Proposal for CREZ

Page 32: COX_TransmissionTF18

DNOSAJJMAMFJ

LT System Study

Wind Consultant RFP

CREZ Criteria Development CREZ Determination

Stakeholder Input on CREZs

CREZ Analysis

ERCOT

PUCT

Generation Scenarios

Wind Integration RFP

Potential C

RE

Z ID

ERCOT CREZ Timeline - 2006

Page 33: COX_TransmissionTF18

What would a CREZ-Style Quantification of Colorado’s Wind

Resource Look Like?

2,800

3,100

4,200

4,200

2,700

1,000

900200

600400

Numbers for illustrative, conceptual, purposes only

Wyoming and New Mexico have additional rich wind resources.

Page 34: COX_TransmissionTF18

Thank you!

Craig CoxInterwest Energy Alliance

[email protected]