Building the Future
Current Activities this Week:
Foundations:
Area 4 Field Level – Foundations for “infill” area
between Column Lines 39-1 are ongoing.
Concrete Flatwork:
Area 3 Field Level – Concrete for slab-on-grade up to
Stair 1 will be placed this week.
Masonry:
Area 1 – Field level masonry installation is ongoing in
Area H, G, F, E and D. Area 2/3 – Concourse building
masonry installation is ongoing.
Steel Erection:
Area 4 – Steel erection for “infill” area is ongoing
(Sequence 3-3). Truss installation has started.
Area 2 – Steel joist and metal decking installation for
concourse buildings is ongoing. Canopy decking
installation is ongoing. Canopy gutter enclosure framing
installation is ongoing.
Roofing and Sheetmetal:
Area 1 – Permanent roofing installation at West
Building is ongoing. Area 2/3 – Canopy gutter installation
is ongoing.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 10.6.2010
Re: Wizards Stadium Project
Update – Week of
10.4.2010
Field Level Area 3 – Concrete slab-on grade
prep is ongoing to column line 4.
Area 4 – Trusses 41 and 42 being set and
connected. 1 more truss remains (40 Line).
Field Level Area 3 – Masonry in Section D is
ongoing.
Building the Future
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing. Exterior metal stud framing
and sheathing installation is ongoing at Field, Suite, and
Press Levels.
Glass:
Area 1 - Curtainwall framing and glass installation is
ongoing at West Building on west, south and east
elevations. South “wing” framing has started.
MEP Rough-in:
Area 3 – Underground MEP rough-in is ongoing.
West Building - Ductwork installation on
Concourse, Suite and Press Levels are ongoing.
Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Concourse, Suite and Press Levels. Electrical rough-in is
ongoing on Concourse, Suite and Press Levels.
Projected Activities occurring next Week:
Foundations:
Area 3/4 Field Level – Foundations for “infill” area
Between Column Lines 39-1 will be complete.
Concrete Flatwork:
Area 3 Field Level – Concrete placement for Slab-on
Grade from lower dock area to Column Line 1.
Area 3 and 4 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Masonry:
Area 1 – Field level masonry installation will continue in
Area H, G, F, E and D. Area 2/3 – Concourse building
masonry installation will continue.
Area 3 – Shot of the Canopy decking
installation that has started on the east side.
Area 1 – Curtainwall “wing” framing at south
end is being constructed.
Field Level Area 4 – Structural steel and
foundations are ongoing at Cauldron Club.
Building the Future
Structural Steel Erection:
Area 4 – Structural steel erection for “infill” area will
be ongoing. Area 2 – Steel joist and metal decking
installation for concourse buildings will continue.
Canopy decking installation will continue. Canopy gutter
enclosure framing installation will continue.
Roofing and Sheetmetal:
Area 1 – Permanent roofing installation at West
Building will continue. Area 3 – Canopy gutter installation
will continue.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue. Exterior Framing and
sheathing installation will continue.
Glass:
Area 1 – Curtain Framing and Glass installation around West
Building will continue. Curtainwall framing on Suite and
Press Level balconies will continue. Curtainwall framing
at Field Side of Main Concourse will continue.
MEP Rough-in:
MEP Rough-in at Concourse, Suite and Press Levels will
continue. Ductwork installation on Concourse, Suite, and
Press Level will continue. Fire Sprinkler installation will
continue on Concourse, Suite and Press Levels.
Field – Installation of the Storm Loop around
playing field has started.
Area 1 – Shot of the west building showing
the progress of the exterior envelope.
Building the Future
Additional Photos:
Area 3 – Burnished CMU wall topped out at
Stair 1.
Area 3– On-grade seating installation is
ongoing at north elevation.
Area 1 – Concrete in Stair 9 is placed.
Concourse Level Area 3 – Canopy gutter and
gutter enclosure framing is ongoing.
Area 2 – Shot of the Canopy decking and
gutter at the SE corner.
Area 4 – Shot of Column Line 42 truss be
raised into place.