Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 2
and Area 3.
Site Utilities:
Storm Sewer Installation (Line 6000) is ongoing
on the east side of France Family Drive.
Foundations:
Area 3 Field Level – Foundation installation continues on
the east side of the site.
Concrete Flatwork:
Area 1 – North Mezzanine concrete placement is
Complete at VIP Entrance. Prep work is ongoing for
Next Slab-on-Grade pour (Column Line 26-24). Prep
work is ongoing for Main Club topping slab placement.
Structural Steel Erection:
Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-7)
Area 2 - Structural Steel Erection Sequence 2-1 is
ongoing. Area 3 – Structural Steel Erection Sequence
3-1 has started.
Underground MEP:
Electrical Secondary Distribution is ongoing in Areas 2.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 7.21.2010
Re: Wizards Stadium Project
Update – Week of
7.19.2010
Area 3 – Installation of Storm Line 6000 is
ongoing on the east side of France Family
Drive.
Mezzanine Level Area 1 – Concrete for slab-
on-grade at VIP Entrance is placed at North
Mezzanine.
Field Level Area 1 – Cast-in-place concrete
riser installation is ongoing.
Building the Future
MEP Rough-in:
Area 1 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite Level is ongoing.
Metal Stud Framing:
Area 1 – Metal stud framing for Suite and Press
Levels are ongoing.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3. Grading in Area 3 (east of A-Line) will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will be complete.
Deep Underground MEP:
Deep Electrical Distribution installation will start again
in Area 3.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Concrete Flatwork:
Area 1 Field Level – Concrete placement for Slab-on-Grade
will be completed to 24 Line.
Area 1 Field Level – Installation of on-grade seating risers
will continue.
Structural Steel Erection:
Erection of Structural Steel in Sequence 2-1 will
continue. Erection of Structural Steel Sequence 3-1
will continue.
Erection of the Canopy Trusses will begin in Sequence 1-8.
Area 1 – Shot of the West Building from the
south concourse area.
Suite Level Area 1 – Shot at the front of the
Suites of metal stud framing progress.
Field Level Area 1/2 – Steel Erection ongoing
in both Sequence 2-1 (right side of picture)
and 3-1 (left side of picture).
Building the Future
Underground MEP:
Electrical Secondary will continue in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Area 1 Field Level slab
on grade will continue. MEP Rough-in at Suite Level will
continue.
Metal Stud Framing:
Area 1 – Metal stud framing for Suite and Press Levels will
continue.
Area 1 – Shot from Roof Level showing the
installation of the Canopy Roof Trusses.
Suite Level Area 1 – Ductwork installation is
ongoing.
Building the Future
Additional Photos:
Area 1 – Shot of the West Building showing
Canopy Trusses, Stadium Suite and Suites
metal stud framing.
Roof Level Area 1 – Shot looking between
Canopy Trusses at 29 and 30 showing the
bridging trusses, purlins and chevron braces.
Concourse Level Area 1 – Main Club slab-on-
grade is placed.
Field Level Area 1 – Shot looking north of
on-grade seating.
Area 1 – Metal decking installation is
ongoing at Terrace Seating Area.
Field Level Area 1 – Shot of Supporter’s Club
Seating Area and Cauldron Club entrances.