4
Building the Future Current Activities this Week : Mass Excavation : Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities : Storm Sewer Installation (Line 6000) is ongoing on the east side of France Family Drive. Foundations : Area 3 Field Level – Foundation installation continues on the east side of the site. Concrete Flatwork : Area 1 – North Mezzanine concrete placement is Complete at VIP Entrance. Prep work is ongoing for Next Slab-on-Grade pour (Column Line 26-24). Prep work is ongoing for Main Club topping slab placement. Structural Steel Erection : Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-7) Area 2 - Structural Steel Erection Sequence 2-1 is ongoing. Area 3 – Structural Steel Erection Sequence 3-1 has started. Underground MEP : Electrical Secondary Distribution is ongoing in Areas 2. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 7.21.2010 Re: Wizards Stadium Project Update – Week of 7.19.2010 Area 3 – Installation of Storm Line 6000 is ongoing on the east side of France Family Drive. Mezzanine Level Area 1 – Concrete for slab- on-grade at VIP Entrance is placed at North Mezzanine. Field Level Area 1 – Cast-in-place concrete riser installation is ongoing.

Construction Update 07-21-2010

Embed Size (px)

Citation preview

Page 1: Construction Update 07-21-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Backfilling of on-grade seating is ongoing in Area 2

and Area 3.

Site Utilities:

Storm Sewer Installation (Line 6000) is ongoing

on the east side of France Family Drive.

Foundations:

Area 3 Field Level – Foundation installation continues on

the east side of the site.

Concrete Flatwork:

Area 1 – North Mezzanine concrete placement is

Complete at VIP Entrance. Prep work is ongoing for

Next Slab-on-Grade pour (Column Line 26-24). Prep

work is ongoing for Main Club topping slab placement.

Structural Steel Erection:

Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-7)

Area 2 - Structural Steel Erection Sequence 2-1 is

ongoing. Area 3 – Structural Steel Erection Sequence

3-1 has started.

Underground MEP:

Electrical Secondary Distribution is ongoing in Areas 2.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 7.21.2010

Re: Wizards Stadium Project

Update – Week of

7.19.2010

Area 3 – Installation of Storm Line 6000 is

ongoing on the east side of France Family

Drive.

Mezzanine Level Area 1 – Concrete for slab-

on-grade at VIP Entrance is placed at North

Mezzanine.

Field Level Area 1 – Cast-in-place concrete

riser installation is ongoing.

Page 2: Construction Update 07-21-2010

Building the Future

MEP Rough-in:

Area 1 – Shallow electrical and plumbing rough-in is

ongoing. Ductwork installation on Suite Level is ongoing.

Metal Stud Framing:

Area 1 – Metal stud framing for Suite and Press

Levels are ongoing.

Projected Activities occurring next Week:

Mass Excavation:

Backfilling of on-grade seating areas will continue in Area

3. Grading in Area 3 (east of A-Line) will continue.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will be complete.

Deep Underground MEP:

Deep Electrical Distribution installation will start again

in Area 3.

Foundations:

Area 3 Field Level – Foundation installation will continue.

Concrete Flatwork:

Area 1 Field Level – Concrete placement for Slab-on-Grade

will be completed to 24 Line.

Area 1 Field Level – Installation of on-grade seating risers

will continue.

Structural Steel Erection:

Erection of Structural Steel in Sequence 2-1 will

continue. Erection of Structural Steel Sequence 3-1

will continue.

Erection of the Canopy Trusses will begin in Sequence 1-8.

Area 1 – Shot of the West Building from the

south concourse area.

Suite Level Area 1 – Shot at the front of the

Suites of metal stud framing progress.

Field Level Area 1/2 – Steel Erection ongoing

in both Sequence 2-1 (right side of picture)

and 3-1 (left side of picture).

Page 3: Construction Update 07-21-2010

Building the Future

Underground MEP:

Electrical Secondary will continue in Area 3.

MEP Rough-in:

Plumbing and Electrical rough-in for Area 1 Field Level slab

on grade will continue. MEP Rough-in at Suite Level will

continue.

Metal Stud Framing:

Area 1 – Metal stud framing for Suite and Press Levels will

continue.

Area 1 – Shot from Roof Level showing the

installation of the Canopy Roof Trusses.

Suite Level Area 1 – Ductwork installation is

ongoing.

Page 4: Construction Update 07-21-2010

Building the Future

Additional Photos:

Area 1 – Shot of the West Building showing

Canopy Trusses, Stadium Suite and Suites

metal stud framing.

Roof Level Area 1 – Shot looking between

Canopy Trusses at 29 and 30 showing the

bridging trusses, purlins and chevron braces.

Concourse Level Area 1 – Main Club slab-on-

grade is placed.

Field Level Area 1 – Shot looking north of

on-grade seating.

Area 1 – Metal decking installation is

ongoing at Terrace Seating Area.

Field Level Area 1 – Shot of Supporter’s Club

Seating Area and Cauldron Club entrances.