Building the Future
Current Activities this Week:
Mass Excavation:
Mass Excavation Activities in the Main Bowl continues
In Areas 2 and 3.
.
Site Utilities:
Installation of the new electrical ductbank has started.
Excavation for the manhole on sanitary line D is
complete. Boring for the service line for Sanitary Line
D is ongoing.
Foundations:
Area 1 Field Level – Column Pads excavation and
Concrete placement is ongoing.
Area 1 Field Level – D-Line wall placement is complete.
Soil Nail Wall:
Area 1 – Shotcrete installation on the 4th lift is ongoing.
Area 2 – Shotcrete installation is ongoing on the 2nd and
3rd lifts.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 3/31/2010
Re: Wizards Stadium Project
Update – Week of
3/29/2010
Area 3 – Excavation continues at south end
of Area 3.
Field Level Area 1 – D-Line Foundation Wall
tie in at Soil Nail Shoring Wall.
Concourse Level Area 2 – Electrical Duct
bank re-location .
Building the Future
Projected Activities occurring next Week:
Mass Excavation:
Remaining mass excavation activities will be nearing
completion. Removal of the haul road will begin.
Site Utilities:
Installation of the new electrical ductback will continue.
Boring under the Field Level D-Line Wall
for the Sanitary Main Line D will begin.
Foundations:
Area 1 Concourse Level – Backfilling of D-Line
wall will continue for section placed this week.
Area 1 Field Level – A-Line footing placement will
continue south towards 19.5 Line.
Soil Nail Wall:
Area 2 – Shotcrete placement on the 2nd and 3
rd lifts will
continue.
Field Level Area 1 – Formwork in place for
north vomitory wall at Player Field Entrance.
Area 2 – Shotcrete wall installation
continues on 2nd
and 3rd
lifts.
Field Level Area 1 – Concrete placement for
elevator 2/3 slab.
Building the Future
Additional Photos:
Field Level Area 1 – Backfill, compaction and
insulation behind D/SSB-Line Walls.
A shot of Area 1 from the Main Concourse
Level.
Area 1 – Column pad rebar cages pre-tied.
Field Level Area 1 – Column pad excavation
at C-Line.
Field Level Area 1 – Column pad ready for
concrete.
Area 2 – Preparation for the soil nail pull
test.