3
Building the Future Current Activities this Week : Mass Excavation : Mass Excavation Activities in the Main Bowl continues In Areas 2 and 3. . Site Utilities : Installation of the new electrical ductbank has started. Excavation for the manhole on sanitary line D is complete. Boring for the service line for Sanitary Line D is ongoing. Foundations : Area 1 Field Level – Column Pads excavation and Concrete placement is ongoing. Area 1 Field Level – D-Line wall placement is complete. Soil Nail Wall : Area 1 – Shotcrete installation on the 4 th lift is ongoing. Area 2 – Shotcrete installation is ongoing on the 2 nd and 3 rd lifts. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 3/31/2010 Re: Wizards Stadium Project Update – Week of 3/29/2010 Area 3 – Excavation continues at south end of Area 3. Field Level Area 1 – D-Line Foundation Wall tie in at Soil Nail Shoring Wall. Concourse Level Area 2 – Electrical Duct bank re-location .

Construction Update 3-31-2010

Embed Size (px)

DESCRIPTION

KC Soccer Stadium construction update from Turner Construction.

Citation preview

Page 1: Construction Update 3-31-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Mass Excavation Activities in the Main Bowl continues

In Areas 2 and 3.

.

Site Utilities:

Installation of the new electrical ductbank has started.

Excavation for the manhole on sanitary line D is

complete. Boring for the service line for Sanitary Line

D is ongoing.

Foundations:

Area 1 Field Level – Column Pads excavation and

Concrete placement is ongoing.

Area 1 Field Level – D-Line wall placement is complete.

Soil Nail Wall:

Area 1 – Shotcrete installation on the 4th lift is ongoing.

Area 2 – Shotcrete installation is ongoing on the 2nd and

3rd lifts.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 3/31/2010

Re: Wizards Stadium Project

Update – Week of

3/29/2010

Area 3 – Excavation continues at south end

of Area 3.

Field Level Area 1 – D-Line Foundation Wall

tie in at Soil Nail Shoring Wall.

Concourse Level Area 2 – Electrical Duct

bank re-location .

Page 2: Construction Update 3-31-2010

Building the Future

Projected Activities occurring next Week:

Mass Excavation:

Remaining mass excavation activities will be nearing

completion. Removal of the haul road will begin.

Site Utilities:

Installation of the new electrical ductback will continue.

Boring under the Field Level D-Line Wall

for the Sanitary Main Line D will begin.

Foundations:

Area 1 Concourse Level – Backfilling of D-Line

wall will continue for section placed this week.

Area 1 Field Level – A-Line footing placement will

continue south towards 19.5 Line.

Soil Nail Wall:

Area 2 – Shotcrete placement on the 2nd and 3

rd lifts will

continue.

Field Level Area 1 – Formwork in place for

north vomitory wall at Player Field Entrance.

Area 2 – Shotcrete wall installation

continues on 2nd

and 3rd

lifts.

Field Level Area 1 – Concrete placement for

elevator 2/3 slab.

Page 3: Construction Update 3-31-2010

Building the Future

Additional Photos:

Field Level Area 1 – Backfill, compaction and

insulation behind D/SSB-Line Walls.

A shot of Area 1 from the Main Concourse

Level.

Area 1 – Column pad rebar cages pre-tied.

Field Level Area 1 – Column pad excavation

at C-Line.

Field Level Area 1 – Column pad ready for

concrete.

Area 2 – Preparation for the soil nail pull

test.