Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 2
and Area 3.
Site Utilities:
Storm Sewer installation (Line 1000) is ongoing along
Village West Parkway.
Storm Line Installation (Line 600 and Sanitary Sewer
Line E installation is ongoing on east side of France
Family Dive is ongoing.
Foundations:
Area 3 Field Level – Isolated footing installation is
Ongoing and is currently to Column Line 6.
Area 4 Mezzanine Level – Excavation for D-Line footing
Is ongoing and is currently to Column Line 40.
Concrete Flatwork:
Area 1 – Mezzanine slab-on deck is complete, Main
Concourse structural slab is complete, Suite Level slab
on deck is complete, Press Level slab on deck is
complete. Preparation for 1st
pour of Field Level Area 1
slab-on-grade is ongoing.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 6.30.2010
Re: Wizards Stadium Project
Update – Week of
6.28.2010
Concourse Level Area 2 – Underground
plumbing rough-in for the Concourse
Buildings is ongoing.
Area 1 – Precast concrete treads and riser
installation is nearly complete between
column lines 32-24.
Field Level Area 1 – Vapor barrier
installation from column line 32-29 is placed
in preparation for slab-on-grade placement.
Building the Future
Structural Steel Erection:
Area 1 –Detailing and decking in sequence 1-3 is ongoing.
Erection of Steel Sequence 2-1 has started.
Area 1 – Roof deck installation for entire West Building is
nearly complete.
Underground MEP:
Electrical Secondary Distribution is ongoing in Area 3.
MEP Rough-in:
Area 1 – Shallow electrical and plumbing rough-in has
started at Field Level in preparation for 1st
slab-on-grade
pour.
Metal Stud Framing:
Area 1 Suite Level – Metal stud framing for Suites has
started.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue. Storm Line 1000
will continue. Installation of Sanitary Line E will continue.
Deep Underground MEP:
Deep Sanitary and Electrical Distribution installation
in Area 3 will continue.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Area 4 Mezzanine Level – Foundation Wall installation will
continue.
Area 1 – Shot of the West Building from the
southeast.
Roof Level Area 1 – Roof decking is nearly
complete.
Area 1 –Canopy Trusses are being delivered
and staged in the infield.
Building the Future
Concrete Flatwork:
Area 1 Field Level – Concrete placement for slab-on-grade
will begin.
Structural Steel Erection:
Erection of Structural Steel in Sequence 2-1 will
continue.
Delivery of Roof Trusses for sequence 1-7 will continue
throughout the week.
Structural Precast:
Erection of the precast tubs in Area 1 will begin.
Underground MEP:
Deep Sanitary installation will continue in Area 3.
Electrical Secondary will continue in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Area 1 Field Level slab
on grade will continue.
Metal Stud Framing:
Area 1 Suite Level – Metal stud framing for Suites will
continue.
Area 1 Press Level – Metal stud framing for Suites will
begin.
Area 2 – Shot looking south of Terrace Area
taking shape.
Field Level Area 3 – Foundation installation
is ongoing.
Building the Future
Additional Photos:
Field Level Area 3 – Field wall footing
concrete placed at column line 4.
Field Level Area 1 – Shot of Player’s field
entry.
Suite Level Area 1 – Metal stud framing for
suites has begun.
Area 1 – Subgrade preparation for on-grade
seating risers has started.
Suite Level Area 1 – Duct straps being
installed in preparation for ductwork
installation.
Roof Level Area 1 – Shot of steel framing for
Freight Elevator “High Hat”.