Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating and foundations are
ongoing in Area 3.
Site Utilities:
Storm and Sanitary Sewer Installation is complete
on the east side of France Family Drive.
Foundations:
Area 3 Field Level – Foundation installation continues on
the east side of the site (Truck Dock Area).
Concrete Flatwork:
Area 2 – Prep work for next slab pour is underway from
Column Line 15 – 12.
Area 3 – Slab-on-Metal Deck is placed to Column Line 1.
Structural Steel Erection:
Area 1 – Main Canopy Truss Erection are set to Column
Line 20.
Area 2 – South Scoreboard support steel is set between
Column Lines 15 – 18.
Precast Concrete:
Area 3 – Precast erection is ongoing and is currently set
to Column Line 7.
Underground MEP:
Electrical for Electrical Room 01.12.01 is ongoing. Deep
Plumbing has started in Area 3.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 8.18.2010
Re: Wizards Stadium Project
Update – Week of
8.16.2010
Area 3 – Installation of Storm and Sanitary
Lines are complete. Cleanup and repair of
France Family Drive has started.
Area 3 – Precast riser erection has turned
the corner is ongoing on the East side and is
currently to Column Line 7.
Field Level Area 3 – Foundations are
continuing on East side. Switchback ramp to
Cauldron Club installation is ongoing.
Building the Future
MEP Rough-in:
Area 2 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite and Press Levels
are ongoing. Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Suite Level.
Metal Stud Framing:
Area 1 – Metal stud framing for Concourse, Suite and Press
Levels are ongoing. Metal stud framing has started at Field
Level.
Masonry:
Area 1 Field Level – Masonry wall installation is ongoing
in Areas F, G and H.
Area 3 Concourse Level – Picture framing has started
for south concourse buildings. Layout for north buildings
are ongoing.
Projected Activities occurring next Week:
Grading:
Area 4 – Grading for field wall foundations will continue.
Site Utilities:
Gas Service installation will begin.
Deep Underground MEP:
Deep Plumbing installation will continue in Area 3.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Concrete Flatwork:
Area 3 Field Level – Concrete placement for Slab-on
Grade between Column Lines 15 - 12.
Area 1, 2 and 3 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Area 1 – Shot of the West Building from the
east concourse.
Field Level Area 1 – Metal Stud Framing has
started at the Field Level.
Area 1 – South Scoreboard support steel is
erected.
Building the Future
Structural Steel Erection:
Area 2 – Canopy installation at South side of Stadium will
continue.
Underground MEP:
Deep underground plumbing will continue in Area 3.
MEP Rough-in:
MEP Rough-in at Suite and Press Levels will continue.
Ductwork installation on Press Level will continue. Fire
Sprinkler installation will continue on Suite Level.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue.
Area 1 – Installation of curtainwall framing
at West Building has started.
Suite Level Area 1 – Stair 10 is installed at
Stadium Suite.
Building the Future
Additional Photos:
Press Level Area 1 – Shot of curtainwall
framing from inside the Club.
Suite Level Area 1 – Stair 6 installed to Press
Level.
Field Level Area 1 – Backfill for east side on-
grade seating is ongoing.
Field Level Area 3 – Dock Leveler concrete
bases are placed.
Field Level Area 3 – Grease Interceptor Pit is
installed.
Mezzanine Level Area 1 – Masonry
installation is ongoing at south mezzanine.