Building the Future
Current Activities this Week:
Mass Excavation:
Mass Excavation Activities in the Main Bowl continues
In Areas 1, 2 and 3. Clarkson is excavating and hauling
Sandstone and Rock to Area C.
Area 4 Mezzanine Level – Rough grading of the Slab on
Grade Seating has begun.
Site Utilities:
BPU has removed the power from switchgear to
manhole.
Foundations:
Area 1 Field Level – D-Line wall have been placed to
Column Line 30.5.
Area 1 Field Level – A Line wall placement has begun
at Column Line 32.
Area 1 Field Level – A-Line footing placement has
begun south of Player Field Entrance.
Area 1 Concourse Level - D-Line Wall Placement is
currently placed to Column Line 29.5.
Area 2 Concourse Level – D-Line Wall Placement
is completed to Column Line 14, along with associated
waterproofing.
Soil Nail Wall:
Area 1 – Soil Nail installation has started on the 3rd lift.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 3/17/2010
Re: Wizards Stadium Project
Update – Week of
3/15/2010
A shot from Mid-Field Looking South
Area 2 – Shotcrete Installation on 2
nd Lift
Concourse Level Area 1 – Pumping Concrete
for D-Line Walls (near Column Line 24)
Building the Future
Area 2 – Working platform for soil nail installation is
currently being removed so soil nail drilling can begin.
Projected Activities occurring next Week:
Mass Excavation:
Area 1 and 2 Field Level - As the soil nail wall progresses,
the working platform (sandstone bench) will continue
to be removed.
Site Utilities:
Installation of the new electrical ductback will begin.
Boring under the Field Level D-Line Wall
for the Sanitary Lateral Line D will begin.
Foundations:
Area 1 Concourse Level – Waterproofing of D-Line
wall will begin.
Area 1 Field Level – A-Line wall placement will continue.
Soil Nail Wall:
Area 1 – Shotcrete installation on 3rd lift will begin.
Area 2 – Drilling for the soil nails on the 2nd lift will begin.
Area 3 – Sandstone Excavation behind A-
Line
Area 1 – E-Line Grade Beam Reinforcing off
of D-Line Wall
Area 1 – Field Level D-Line Wall with forms
stripped
Building the Future
Additional Photos:
Area 1 Field Level – Setting wall dowels for
A-Line Footing
Area 1 – Pump truck setting up for A-Line
Footing Pour
Area 2 – Concourse Level D-Line Walls
getting backfilled
Area 1 – Rock Excavation, Footing
Excavation and Hauling Operations
Area 2 – Concourse Level Waterproofing
installation on D-Line Walls
Area 4 – View of the Future Cauldron Club
Area