Building the Future Current Activities this Week : Mass Excavation : Mass Excavation Activities in the Main Bowl continues In Areas 1, 2 and 3. Clarkson is excavating and hauling Sandstone and Rock to Area C. Area 4 Mezzanine Level – Rough grading of the Slab on Grade Seating has begun. Site Utilities : BPU has removed the power from switchgear to manhole. Foundations : Area 1 Field Level – D-Line wall have been placed to Column Line 30.5. Area 1 Field Level – A Line wall placement has begun at Column Line 32. Area 1 Field Level – A-Line footing placement has begun south of Player Field Entrance. Area 1 Concourse Level - D-Line Wall Placement is currently placed to Column Line 29.5. Area 2 Concourse Level – D-Line Wall Placement is completed to Column Line 14, along with associated waterproofing. Soil Nail Wall : Area 1 – Soil Nail installation has started on the 3 rd lift. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 3/17/2010 Re: Wizards Stadium Project Update – Week of 3/15/2010 A shot from Mid-Field Looking South Area 2 – Shotcrete Installation on 2 nd Lift Concourse Level Area 1 – Pumping Concrete for D-Line Walls (near Column Line 24)

Construction Update 3-17-2010

Embed Size (px)

DESCRIPTION

KC Soccer Stadium construction update from Turner Construction.

Citation preview

Page 1: Construction Update 3-17-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Mass Excavation Activities in the Main Bowl continues

In Areas 1, 2 and 3. Clarkson is excavating and hauling

Sandstone and Rock to Area C.

Area 4 Mezzanine Level – Rough grading of the Slab on

Grade Seating has begun.

Site Utilities:

BPU has removed the power from switchgear to

manhole.

Foundations:

Area 1 Field Level – D-Line wall have been placed to

Column Line 30.5.

Area 1 Field Level – A Line wall placement has begun

at Column Line 32.

Area 1 Field Level – A-Line footing placement has

begun south of Player Field Entrance.

Area 1 Concourse Level - D-Line Wall Placement is

currently placed to Column Line 29.5.

Area 2 Concourse Level – D-Line Wall Placement

is completed to Column Line 14, along with associated

waterproofing.

Soil Nail Wall:

Area 1 – Soil Nail installation has started on the 3rd lift.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 3/17/2010

Re: Wizards Stadium Project

Update – Week of

3/15/2010

A shot from Mid-Field Looking South

Area 2 – Shotcrete Installation on 2

nd Lift

Concourse Level Area 1 – Pumping Concrete

for D-Line Walls (near Column Line 24)

Page 2: Construction Update 3-17-2010

Building the Future

Area 2 – Working platform for soil nail installation is

currently being removed so soil nail drilling can begin.

Projected Activities occurring next Week:

Mass Excavation:

Area 1 and 2 Field Level - As the soil nail wall progresses,

the working platform (sandstone bench) will continue

to be removed.

Site Utilities:

Installation of the new electrical ductback will begin.

Boring under the Field Level D-Line Wall

for the Sanitary Lateral Line D will begin.

Foundations:

Area 1 Concourse Level – Waterproofing of D-Line

wall will begin.

Area 1 Field Level – A-Line wall placement will continue.

Soil Nail Wall:

Area 1 – Shotcrete installation on 3rd lift will begin.

Area 2 – Drilling for the soil nails on the 2nd lift will begin.

Area 3 – Sandstone Excavation behind A-

Line

Area 1 – E-Line Grade Beam Reinforcing off

of D-Line Wall

Area 1 – Field Level D-Line Wall with forms

stripped

Page 3: Construction Update 3-17-2010

Building the Future

Additional Photos:

Area 1 Field Level – Setting wall dowels for

A-Line Footing

Area 1 – Pump truck setting up for A-Line

Footing Pour

Area 2 – Concourse Level D-Line Walls

getting backfilled

Area 1 – Rock Excavation, Footing

Excavation and Hauling Operations

Area 2 – Concourse Level Waterproofing

installation on D-Line Walls

Area 4 – View of the Future Cauldron Club

Area