Upload
kansas-city-wizards
View
246
Download
0
Tags:
Embed Size (px)
Citation preview
Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of foundations is nearly complete in Area 3.
Site Utilities:
Tie in of domestic and fire line services are complete
on the east side of France Family Drive. Installation of
the gas service has commenced.
Foundations:
Area 4 Field Level – Field wall installation up to the
crane road is complete.
Concrete Flatwork:
Area 2 Concourse – Prep work for next slab pour for
South Concession Buildings is nearly complete.
Area 3 Field Level – Prep work for slab pour at upper
dock is nearly complete.
Structural Steel Erection:
Area 2 – Main Canopy Truss Erection are set to Column
Line 10.
Structural Precast Concrete:
Area 3 – Precast tread/riser erection complete.
Underground MEP:
Area 3 - Deep underground Plumbing is ongoing.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 9.1.2010
Re: Wizards Stadium Project
Update – Week of
8.30.2010
Area 4 – North field wall complete to the
Crane Road.
Area 3 – Precast tread/riser erection is
complete.
Area 2 – Stage concrete slab placement is
complete.
Building the Future
MEP Rough-in:
Area 3 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite and Press Levels
are ongoing. Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Suite and Press Levels. Electrical rough-in is ongoing on
Suite and Press Levels.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing. Exterior metal stud framing
and sheathing installation is ongoing at Field, Suite, and
Press Levels.
Masonry:
Area 1 Field Level – Masonry wall installation is ongoing
in Areas F, G and H.
Area 3 Concourse Level – Masonry wall installation at
Main Concourse Buildings are underway.
Curtainwall:
Area 1 – Curtainwall framing installation will continue
at West Elevation. Installation of Curtainwall glass is
ongoing.
Projected Activities occurring next Week:
Site Utilities:
Gas Service installation will continue on France Family Drive.
Deep Underground MEP:
Deep Plumbing installation will continue in Area 3.
Foundations:
Area 4 Field Level – Foundation wall installation for Main
Stair will begin.
Area 1 – Shot of the West Building from the
Stage (Field Level).
Area 1 – Exterior Metal Stud Framing and
sheathing installation ongoing at north side
of Stadium Suite.
Area 2 – Canopy Truss erection is complete
in Sequence 2-2 (installation of Truss to 10
Line shown).
Building the Future
Concrete Flatwork:
Area 2 Concourse Level – Concrete placement for Slab-on
Grade for Main Concourse Buildings will begin.
Area 1, 2 and 3 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Structural Steel Erection:
Area 2 – Canopy truss installation at South side of Stadium
will continue. Area 3 – Canopy Truss installation will begin.
Underground MEP:
Deep underground plumbing will continue in Area 3.
MEP Rough-in:
MEP Rough-in at Suite and Press Levels will continue.
Ductwork installation on Press Level will continue. Fire
Sprinkler installation will continue on Suite and Press Levels.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue. Exterior Framing and
sheathing installation will continue.
Curtainwall:
Area 1 – Curtain Framing and Glass installation will
continue.
Area 1 – Installation of curtainwall framing
and Glass at West Building is ongoing.
Roof Level Area 1 – Installation of decking
on Canopy Trusses has started.
Building the Future
Additional Photos:
Area 2 – Shot looking south from roof above
Stadium Suite.
Field Level Area 1 – Curtainwall glass, metal
stud framing and exterior sheathing being
installation at and above Main Club
Entrance.
Concourse Level Area 1 – Masonry at Main
Concourse Level is underway (Stair 4
shown).
Field Level Area 1 – Subroof framing
installation is ongoing.
Field Level Area 3 – Upper Dock Formwork
and MEP rough-in is ongoing in preparation
for concrete slab placement.
Field Level Area 2 – Masonry installation at
Field Level (underneath terrace seating).