KC Soccer Stadium construction update from Turner Construction.
Citation preview
Building the Future
Current Activities this Week:
Mass Excavation:
Remaining Mass Excavation Activities are nearly
complete. Removal of the Haul Road to Area C has
started.
.
Site Utilities:
Installation of the new electrical ductbank is ongoing.
Approximately 150 linear feet is installed.
Boring for the service line for Sanitary Main Line
D is ongoing. The boring and installation of pipe for
the Sanitary Lateral line is complete.
Foundations:
Area 1 Field Level – Column Pads excavation and
Concrete placement is complete to Column Line 24.
Soil Nail Wall:
Area 1 – Shotcrete installation is complete.
Area 2 – Shotcrete installation is complete on the 4th lift
up to approximately Column Line 14.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 4/7/2010
Re: Wizards Stadium Project
Update – Week of
4/5/2010
Haul Road – Removal of the temporary haul
road to Area C has commenced.
Field Level Area 1 – Isolated Footing
installation completed to 24-Line.
Concourse Level Area 2 – Electrical Duct
bank installation ongoing.
Building the Future
Projected Activities occurring next Week:
Mass Excavation:
Removal of the haul road will be nearing completion with
installation of sodding and seeding commencing.
Site Utilities:
Installation of the new electrical ductback will continue.
Installation of the Sanitary Manhole at the North end of
Area 1 will begin.
Installation of the Storm Line on the East Side (France
Family Drive) of the site will begin.
Foundations:
Area 1 Mezzanine Level – Layout and Excavation for
Footings for E-Line will begin.
Area 1 Field Level – A-Line footing will be completed.
Soil Nail Wall:
Area 2 – Excavation for remaining remaining lift of
Soil Nail Wall will begin, east of Column Line 14.
Structural Steel Erection:
Delivery and Installation of the Crane will begin
mid-week.
Field Level Area 1 – Concrete placement at
Player Field Entrance to the Pitch is
complete.
Area 2 – Drilling for Soil Nails on 4
th Lift on
South Wall.
Field Level Area 1 – Excavation for A-Line
Footing from Column Line 24 to Column Line
22.
Building the Future
Additional Photos:
Field Level Area 1 – Backfill at SSB-Line Wall
is complete.
Field Level Area 3 – Mass excavation, south
of Haul Road.
Concourse Level Area 2 – Capped water
main.
Field Level Area 1 – Waterproofing
installation on Elevator Pit for Elevators 2/3.
Field Level Area 1 – Hydrotherapy Pit
Excavation.
Area 1 – Shot of Area 1 looking North from
Concourse Level.