3
Building the Future Current Activities this Week : Mass Excavation : Remaining Mass Excavation Activities are nearly complete. Removal of the Haul Road to Area C has started. . Site Utilities : Installation of the new electrical ductbank is ongoing. Approximately 150 linear feet is installed. Boring for the service line for Sanitary Main Line D is ongoing. The boring and installation of pipe for the Sanitary Lateral line is complete. Foundations : Area 1 Field Level – Column Pads excavation and Concrete placement is complete to Column Line 24. Soil Nail Wall : Area 1 – Shotcrete installation is complete. Area 2 – Shotcrete installation is complete on the 4 th lift up to approximately Column Line 14. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 4/7/2010 Re: Wizards Stadium Project Update – Week of 4/5/2010 Haul Road – Removal of the temporary haul road to Area C has commenced. Field Level Area 1 – Isolated Footing installation completed to 24-Line. Concourse Level Area 2 – Electrical Duct bank installation ongoing.

Construction Update 4-7-2010

Embed Size (px)

DESCRIPTION

KC Soccer Stadium construction update from Turner Construction.

Citation preview

Page 1: Construction Update 4-7-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Remaining Mass Excavation Activities are nearly

complete. Removal of the Haul Road to Area C has

started.

.

Site Utilities:

Installation of the new electrical ductbank is ongoing.

Approximately 150 linear feet is installed.

Boring for the service line for Sanitary Main Line

D is ongoing. The boring and installation of pipe for

the Sanitary Lateral line is complete.

Foundations:

Area 1 Field Level – Column Pads excavation and

Concrete placement is complete to Column Line 24.

Soil Nail Wall:

Area 1 – Shotcrete installation is complete.

Area 2 – Shotcrete installation is complete on the 4th lift

up to approximately Column Line 14.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 4/7/2010

Re: Wizards Stadium Project

Update – Week of

4/5/2010

Haul Road – Removal of the temporary haul

road to Area C has commenced.

Field Level Area 1 – Isolated Footing

installation completed to 24-Line.

Concourse Level Area 2 – Electrical Duct

bank installation ongoing.

Page 2: Construction Update 4-7-2010

Building the Future

Projected Activities occurring next Week:

Mass Excavation:

Removal of the haul road will be nearing completion with

installation of sodding and seeding commencing.

Site Utilities:

Installation of the new electrical ductback will continue.

Installation of the Sanitary Manhole at the North end of

Area 1 will begin.

Installation of the Storm Line on the East Side (France

Family Drive) of the site will begin.

Foundations:

Area 1 Mezzanine Level – Layout and Excavation for

Footings for E-Line will begin.

Area 1 Field Level – A-Line footing will be completed.

Soil Nail Wall:

Area 2 – Excavation for remaining remaining lift of

Soil Nail Wall will begin, east of Column Line 14.

Structural Steel Erection:

Delivery and Installation of the Crane will begin

mid-week.

Field Level Area 1 – Concrete placement at

Player Field Entrance to the Pitch is

complete.

Area 2 – Drilling for Soil Nails on 4

th Lift on

South Wall.

Field Level Area 1 – Excavation for A-Line

Footing from Column Line 24 to Column Line

22.

Page 3: Construction Update 4-7-2010

Building the Future

Additional Photos:

Field Level Area 1 – Backfill at SSB-Line Wall

is complete.

Field Level Area 3 – Mass excavation, south

of Haul Road.

Concourse Level Area 2 – Capped water

main.

Field Level Area 1 – Waterproofing

installation on Elevator Pit for Elevators 2/3.

Field Level Area 1 – Hydrotherapy Pit

Excavation.

Area 1 – Shot of Area 1 looking North from

Concourse Level.