Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 2
and Area 3.
Site Utilities:
Storm Sewer Installation (Line 6000) has started again
on the east side of France Family Drive.
Foundations:
Area 3 Field Level – Foundation installation continues on
the east side of the site.
Concrete Flatwork:
Area 1 – South Mezzanine concrete placement is
ongoing. Subgrade prep is ongoing for the next Field
Level Slab-on-Grade pour (Column Line 29-25). Prep
work for next Main Concourse structural slab (Column
Line 23-19.5) is ongoing.
Structural Steel Erection:
Area 1 – Erection of Structural Steel Sequence 2-1 is
ongoing. Main Canopy truss erection in Sequence 1-7
has started.
Underground MEP:
Electrical Secondary Distribution is ongoing in Areas 2
and 3.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 7.14.2010
Re: Wizards Stadium Project
Update – Week of
7.12.2010
Concourse Level Area 2 – Underground
plumbing and electrical rough-in for the
Concourse Buildings is ongoing.
Mezzanine Level Area 1 – Concrete for slab-
depression at Food Service Cooler is placed
at South Mezzanine.
Field Level Area 1 – Cast-in-place concrete
riser installation is ongoing.
Building the Future
MEP Rough-in:
Area 1 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite Level has begun.
Metal Stud Framing:
Area 1 – Metal stud framing for Suite and Press
Levels are ongoing.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3. Grading in Area 3 (east of A-Line) will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue.
Deep Underground MEP:
Deep Sanitary and Electrical Distribution installation
in Area 3 will continue.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Concrete Flatwork:
Area 1 Field Level – Concrete placement for Slab-on-Grade
Will be completed from Column Lines 29-25.
Area 1 Field Level – Installation of on-grade seating risers
will continue.
Structural Steel Erection:
Erection of Structural Steel in Sequence 2-1 will
continue. Erection of Structural Steel Sequence 3-1
will begin.
Erection of the Canopy Trusses will continue in Sequence 1-7.
Area 1 – Shot of the West Building from the
south concourse area.
Suite/Press Levels Area 1 – Metal stud
framing for Suites are ongoing.
Area 2 –Steel erection in Sequence 2-1 is in
full ongoing. Installation of metal decking
has started.
Building the Future
Underground MEP:
Electrical Secondary will continue in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Area 1 Field Level slab
on grade will continue. MEP Rough-in at Suite Level will
continue.
Metal Stud Framing:
Area 1 – Metal stud framing for Suite and Press Levels will
continue.
Area 1 – Shot from Roof Level showing the
installation of the Canopy Roof Trusses.
Field Level Area 3 – F-Line Grade Beam is
ongoing.
Building the Future
Additional Photos:
Area 1 – Shot of the West Building from the
northeast corner of the project site.
Area 1 – Structural Steel erection is
complete at Stadium Suite now that the
precast seating tub is installed.
Suite Level Area 1 – Metal stud framing and
metal duckwork installation is ongoing.
Press Level Area 1 – Metal Stud Framing
installation is ongoing.
Area 1 – Prefabricated plumbing carriers are
being delivered to the project site.
Concourse Level Area 1 – Reinforcing Steel
being installed in preparation for upcoming
concrete pour (Column Lines 23-19.5).