Building the Future Current Activities this Week : Mass Excavation : Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities : Storm Sewer Installation (Line 6000) has started again on the east side of France Family Drive. Foundations : Area 3 Field Level – Foundation installation continues on the east side of the site. Concrete Flatwork : Area 1 – South Mezzanine concrete placement is ongoing. Subgrade prep is ongoing for the next Field Level Slab-on-Grade pour (Column Line 29-25). Prep work for next Main Concourse structural slab (Column Line 23-19.5) is ongoing. Structural Steel Erection : Area 1 – Erection of Structural Steel Sequence 2-1 is ongoing. Main Canopy truss erection in Sequence 1-7 has started. Underground MEP : Electrical Secondary Distribution is ongoing in Areas 2 and 3. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 7.14.2010 Re: Wizards Stadium Project Update – Week of 7.12.2010 Concourse Level Area 2 – Underground plumbing and electrical rough-in for the Concourse Buildings is ongoing. Mezzanine Level Area 1 – Concrete for slab- depression at Food Service Cooler is placed at South Mezzanine. Field Level Area 1 – Cast-in-place concrete riser installation is ongoing.

Construction Update 07-14-2010

Embed Size (px)

Citation preview

Page 1: Construction Update 07-14-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Backfilling of on-grade seating is ongoing in Area 2

and Area 3.

Site Utilities:

Storm Sewer Installation (Line 6000) has started again

on the east side of France Family Drive.

Foundations:

Area 3 Field Level – Foundation installation continues on

the east side of the site.

Concrete Flatwork:

Area 1 – South Mezzanine concrete placement is

ongoing. Subgrade prep is ongoing for the next Field

Level Slab-on-Grade pour (Column Line 29-25). Prep

work for next Main Concourse structural slab (Column

Line 23-19.5) is ongoing.

Structural Steel Erection:

Area 1 – Erection of Structural Steel Sequence 2-1 is

ongoing. Main Canopy truss erection in Sequence 1-7

has started.

Underground MEP:

Electrical Secondary Distribution is ongoing in Areas 2

and 3.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 7.14.2010

Re: Wizards Stadium Project

Update – Week of

7.12.2010

Concourse Level Area 2 – Underground

plumbing and electrical rough-in for the

Concourse Buildings is ongoing.

Mezzanine Level Area 1 – Concrete for slab-

depression at Food Service Cooler is placed

at South Mezzanine.

Field Level Area 1 – Cast-in-place concrete

riser installation is ongoing.

Page 2: Construction Update 07-14-2010

Building the Future

MEP Rough-in:

Area 1 – Shallow electrical and plumbing rough-in is

ongoing. Ductwork installation on Suite Level has begun.

Metal Stud Framing:

Area 1 – Metal stud framing for Suite and Press

Levels are ongoing.

Projected Activities occurring next Week:

Mass Excavation:

Backfilling of on-grade seating areas will continue in Area

3. Grading in Area 3 (east of A-Line) will continue.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will continue.

Deep Underground MEP:

Deep Sanitary and Electrical Distribution installation

in Area 3 will continue.

Foundations:

Area 3 Field Level – Foundation installation will continue.

Concrete Flatwork:

Area 1 Field Level – Concrete placement for Slab-on-Grade

Will be completed from Column Lines 29-25.

Area 1 Field Level – Installation of on-grade seating risers

will continue.

Structural Steel Erection:

Erection of Structural Steel in Sequence 2-1 will

continue. Erection of Structural Steel Sequence 3-1

will begin.

Erection of the Canopy Trusses will continue in Sequence 1-7.

Area 1 – Shot of the West Building from the

south concourse area.

Suite/Press Levels Area 1 – Metal stud

framing for Suites are ongoing.

Area 2 –Steel erection in Sequence 2-1 is in

full ongoing. Installation of metal decking

has started.

Page 3: Construction Update 07-14-2010

Building the Future

Underground MEP:

Electrical Secondary will continue in Area 3.

MEP Rough-in:

Plumbing and Electrical rough-in for Area 1 Field Level slab

on grade will continue. MEP Rough-in at Suite Level will

continue.

Metal Stud Framing:

Area 1 – Metal stud framing for Suite and Press Levels will

continue.

Area 1 – Shot from Roof Level showing the

installation of the Canopy Roof Trusses.

Field Level Area 3 – F-Line Grade Beam is

ongoing.

Page 4: Construction Update 07-14-2010

Building the Future

Additional Photos:

Area 1 – Shot of the West Building from the

northeast corner of the project site.

Area 1 – Structural Steel erection is

complete at Stadium Suite now that the

precast seating tub is installed.

Suite Level Area 1 – Metal stud framing and

metal duckwork installation is ongoing.

Press Level Area 1 – Metal Stud Framing

installation is ongoing.

Area 1 – Prefabricated plumbing carriers are

being delivered to the project site.

Concourse Level Area 1 – Reinforcing Steel

being installed in preparation for upcoming

concrete pour (Column Lines 23-19.5).