    Gorgon Project Update: Selected Images

    December 6, 2012

    1

  • 2012 Chevron Corporation

    Overview: The Gorgon Project Is 55 Percent Complete

    The causeway extends 1.3 miles (2.1 km) from the plant site, with foundation structures for the liquefied natural gas (LNG) jetty rising from the water (bottom left

    of image).

    2

  • 2012 Chevron Corporation

    Plant Site

    Construction of the LNG plant continues on the 408-acre (1.65-km-sq) site.

    3

  • 2012 Chevron Corporation

    LNG Storage Tanks

    Construction of the two LNG tanks is progressing well.

    4

  • 2012 Chevron Corporation

    LNG Tanks (continued)

    The roof on the second LNG tank was raised into its final position in November.

    5

  • 2012 Chevron Corporation

    Pre-Assembled Racks and Units

    Seventy-five pre-assembled rack (PAR) and two pre-assembled unit (PAU) modules have been delivered to Barrow Island. In total, 236 PARs and PAUs will be installed.

    The installation and connection process is well under way.

    6

  • 2012 Chevron Corporation

    Gas Turbine Generator No. 1

    Gas Turbine Generator No. 1 was loaded onto transport vessel Yamato on October 8, 2012.

    7

  • 2012 Chevron Corporation

    Gas Turbine Generator No. 1 (continued)

    Gas Turbine Generator No. 1 was loaded onto transport vessel Yamato on October 8, 2012.

    8

  • 2012 Chevron Corporation

    Materials-Offloading Facility

    The materials-offloading facility on Barrow Island consists of the recently completed heavy lift facility, the roll-on roll-off berth, a module carrier berth and a tug pen.

    9

  • 2012 Chevron Corporation

    Construction Village

    Ten of the 12 accommodation clusters in the cyclone-rated construction village are now occupied.

    10

  • 2012 Chevron Corporation

    Installation of the Offshore Pipelines

    In November, the main offshore pipe-lay activities were completed for the domestic gas pipeline.

    Two purpose-built rigs are now installing stabilization anchors, known as rock bolts, along the pipeline.

    11

  • 2012 Chevron Corporation

    Domestic Gas Pipeline Works

    Stringing, welding and coating activities continue for the onshore section of the domestic gas pipeline. Construction also has begun on the domestic gas metering

    station, located near the tie-in to the Dampier-to-Bunbury natural gas pipeline.

    12