Click here to load reader

Gorgon Project Update

  • View
    221

  • Download
    1

Embed Size (px)

Text of Gorgon Project Update

  • 2015 Chevron Corporation. All rights reserved.

    Gorgon Project Update

    October 30, 2015

  • 2015 Chevron Corporation. All rights reserved.

    Jansz-Io Wells Opened to Pipeline

    The Jansz-Io field subsea infrastructure is fully complete, and the first two wells

    have been opened into the pipeline. Below is a photo of a remote operated vehicle

    preparing the first subsea tree for gas to flow to the plant site.

    2

  • 2015 Chevron Corporation. All rights reserved.

    Gas Turbine Generator 2 Startup

    The second of five gas turbine generators (GTG 2) has started up and is now

    synchronized with GTG 1.

    3

    GTG 1

    GTG 2

  • 2015 Chevron Corporation. All rights reserved.

    LNG Train 3

    Delivery of modules required for LNG Train 3 continues with nine of the 13 modules

    on Barrow Island. Only four of the total 51 modules remain to be delivered.

    4

    LNG Train 2 LNG Train 1 LNG Train 3

  • 2015 Chevron Corporation. All rights reserved.

    Fired Heaters

    Commissioning activities are complete on the Fired Heater required to start up

    the Train 1 Acid Gas Removal Unit.

    5

  • 2015 Chevron Corporation. All rights reserved.

    LNG Jetty

    Pre-commissioning activities are well under way on the eight LNG and two

    condensate loading arms.

    6