© 2015 Chevron Corporation. All rights reserved. Gorgon Project Update October 30, 2015

Gorgon Project Update

Embed Size (px)

Citation preview

Page 1: Gorgon Project Update

© 2015 Chevron Corporation. All rights reserved.

Gorgon Project Update

October 30, 2015

Page 2: Gorgon Project Update

© 2015 Chevron Corporation. All rights reserved.

Jansz-Io Wells Opened to Pipeline

The Jansz-Io field subsea infrastructure is fully complete, and the first two wells

have been opened into the pipeline. Below is a photo of a remote operated vehicle

preparing the first subsea tree for gas to flow to the plant site.

2

Page 3: Gorgon Project Update

© 2015 Chevron Corporation. All rights reserved.

Gas Turbine Generator 2 Startup

The second of five gas turbine generators (GTG 2) has started up and is now

synchronized with GTG 1.

3

GTG 1

GTG 2

Page 4: Gorgon Project Update

© 2015 Chevron Corporation. All rights reserved.

LNG Train 3

Delivery of modules required for LNG Train 3 continues with nine of the 13 modules

on Barrow Island. Only four of the total 51 modules remain to be delivered.

4

LNG Train 2 LNG Train 1 LNG Train 3

Page 5: Gorgon Project Update

© 2015 Chevron Corporation. All rights reserved.

Fired Heaters

Commissioning activities are complete on the Fired Heater required to start up

the Train 1 Acid Gas Removal Unit.

5

Page 6: Gorgon Project Update

© 2015 Chevron Corporation. All rights reserved.

LNG Jetty

Pre-commissioning activities are well under way on the eight LNG and two

condensate loading arms.

6