CONVENTIONAL FACILITIES STATUS. Jess Albino – Associate Project Director for Civil Construction June 9, 2009. Agenda. Status of Conventional Construction Turner Contract CF Remaining Work Turner Contract Closeout Office Space Procurement. Research Yard. Research Yard. - PowerPoint PPT Presentation
Citation preview
1 Jess Albinoalbino@slac.stanford.edu
1Conventional Facilities StatusFAC Review – Breakout Session
CONVENTIONAL FACILITIES
STATUS
Jess Albino – Associate Project Director for Civil ConstructionJune 9, 2009
2 Jess Albinoalbino@slac.stanford.edu
2Conventional Facilities StatusFAC Review – Breakout Session
Agenda
Status of Conventional Construction
Turner Contract
CF Remaining Work
Turner Contract Closeout
Office Space Procurement
3 Jess Albinoalbino@slac.stanford.edu
3Conventional Facilities StatusFAC Review – Breakout Session
Research Yard
4 Jess Albinoalbino@slac.stanford.edu
4Conventional Facilities StatusFAC Review – Breakout Session
Research Yard
5 Jess Albinoalbino@slac.stanford.edu
5Conventional Facilities StatusFAC Review – Breakout Session
Near Experimental Hall
6 Jess Albinoalbino@slac.stanford.edu
6Conventional Facilities StatusFAC Review – Breakout Session
Central Utility Plant
7 Jess Albinoalbino@slac.stanford.edu
7Conventional Facilities StatusFAC Review – Breakout Session
Beam Transport Hall
8 Jess Albinoalbino@slac.stanford.edu
8Conventional Facilities StatusFAC Review – Breakout Session
Undulator Hall
9 Jess Albinoalbino@slac.stanford.edu
9Conventional Facilities StatusFAC Review – Breakout Session
Undulator Hall
10 Jess Albinoalbino@slac.stanford.edu
10Conventional Facilities StatusFAC Review – Breakout Session
Undulator Stands
11 Jess Albinoalbino@slac.stanford.edu
11Conventional Facilities StatusFAC Review – Breakout Session
Electron Beam Dump
12 Jess Albinoalbino@slac.stanford.edu
12Conventional Facilities StatusFAC Review – Breakout Session
Electron Beam Dump
13 Jess Albinoalbino@slac.stanford.edu
13Conventional Facilities StatusFAC Review – Breakout Session
Front End Enclosure
14 Jess Albinoalbino@slac.stanford.edu
14Conventional Facilities StatusFAC Review – Breakout Session
Near Experimental Hall – Hutch 1
15 Jess Albinoalbino@slac.stanford.edu
15Conventional Facilities StatusFAC Review – Breakout Session
Near Experimental Hall Subbasement
16 Jess Albinoalbino@slac.stanford.edu
16Conventional Facilities StatusFAC Review – Breakout Session
Xray Transport and Diagnostic Tunnel
17 Jess Albinoalbino@slac.stanford.edu
17Conventional Facilities StatusFAC Review – Breakout Session
Far Experimental Hall
18 Jess Albinoalbino@slac.stanford.edu
18Conventional Facilities StatusFAC Review – Breakout Session
Substantial Completion
19 Jess Albinoalbino@slac.stanford.edu
19Conventional Facilities StatusFAC Review – Breakout Session
AMO moves into Hutch 1
20 Jess Albinoalbino@slac.stanford.edu
20Conventional Facilities StatusFAC Review – Breakout Session
LCLS CF Work Remaining
Construct Experimental Hutches in Far Experimental Hall
Structural Steel in fabrication – installation begins in June.
Build-out contract in award stage – NTP in July.
Office Space Alternatives ProjectBaseline Change approved – construct new building
Design/Build, Guaranteed Maximum Price contract
Contractor selected – NTP in June
21 Jess Albinoalbino@slac.stanford.edu
21Conventional Facilities StatusFAC Review – Breakout Session
WBS 1.9 Completed and Remaining
Completed Work
Admin/Mgmt
Design/Engr
Proc/Fab/Assy
Work Completed127,797,354
Admin/Mgmt1,302,273
Dsn/Engr909,466
Proc/Fab/Assy11,285,208
22 Jess Albinoalbino@slac.stanford.edu
22Conventional Facilities StatusFAC Review – Breakout Session
Turner Contract Closeout
Notice of Substantial Completion 11/17/2008
Notice of Completion ~4/24/2009
Remaining ActivitiesRedline mark-ups sent to Jacobs for Record Drawings
23 of 26 trade subcontracts require closeout binders
Retention amounts to be released upon closeout
Complete Lessons Learned
23 Jess Albinoalbino@slac.stanford.edu
23Conventional Facilities StatusFAC Review – Breakout Session
CF CMGC Stewardship – Lessons LearnedOctober ’06 thru April ’07 Ramp Up to Full Production : Procedural Violations
Stand Down of Construction Activities : All Hands MeetingReview of Work Planning Process for field work – JSA process inadequate
PMT changesDeficiency Notices
May ’07 thru November ’07 Full Production : DARTsMulti-day Stand Down of Construction Activities : Corrective Action Plan
Paperwork ineffectively utilized by CM/GC and trade contractorsPMT changesDeficiency Notices & FinesCommunication with Corporate TCCoSafety Stewardship Committee EstablishedFull time on-site medic (+30hr OSHA)UTRs added
December ’07 thru April ’08 : Some progress, then… Two DARTs associated with one sub
PM removed Work stopped
May ’08 thru December ’08 : No DARTs Effective work planning & execution sought Plan for joint observation developed
Attendance at daily morning work planning meetings JSA review with workers throughout the day Identification / monitoring of specific trades or tasks for safe work practices
24 Jess Albinoalbino@slac.stanford.edu
24Conventional Facilities StatusFAC Review – Breakout Session
end of presentation