1 BROOKHAVEN SCIENCE ASSOCIATES
Conventional Facilities Status
Martin Fallier, Conventional Facilities Div. DirectorConventional Facilities Advisory Committee Review
October 5-6, 2010
2 BROOKHAVEN SCIENCE ASSOCIATES
Outline• Baseline Overview
• Scope, Cost & Schedule
• Organization• Progress Since Last Review
• Technical Progress• Cost & Schedule Performance
• Risks• Issues • Charge Items• Recommendation tracking
3 BROOKHAVEN SCIENCE ASSOCIATES
Baseline Scope
Description
1.5.1 Conventional Facilities Management CF Engineering & Construction Management Team1.5.2 Conventional Facilities Engineering & Design A/E Design, CM Estimating and BNL Design Support1.5.3 Conventional Facilities Construction All CF Construction Packages
1.5.3.1 Site Preparation Preparation of site for construction1.5.3.2 Ring Building Ring Bldg and supporting service and utility buildings1.5.3.2 Electrical Substation Expand BNL Substation by 20MVA for NSLS-II1.5.3.4 Chilled Water Plant Expand BNL Chilled Water Plant by 2500 tons for NSLS-II1.5.3.5 Chilled Water Piping CHW connecting piping from NSLS-II to BNL CHW main1.5.3.6 Lab-Office Buildings (LOBs) 2 fully fitted out and one shelled Lab & Office Bldg
1.5.4 Integrated Controls & Communications Control, communication and data infrastructure1.5.5 Standard Equipment Building furnishings and equipment1.5.6 Conventional Facilities Commissioning Start-up and testing service contract
WBS
WBS 1.5 Conventional Facilities
Added Scope 1.5.3.7 HXN Beamline Addition Addition to LOB 3 structure
4 BROOKHAVEN SCIENCE ASSOCIATES
NSLS-II Site Plan
N
0 100 200
NSLS-II With Full LOB Build-Out
5 BROOKHAVEN SCIENCE ASSOCIATES
Ring Bldg Overall Floor PlanStorage Ring & Booster TunnelExperimental FloorAccess CorridorService BuildingsLOB’s 1, 2, & 3 Base ScopeFuture LOB’sEarth Berm
RFInjection
LobbyLOB 1
Vehicle Tunnel
LOB
5
LOB 4LOB 3
LOB 2
Process Cooling Water Bldg
6 BROOKHAVEN SCIENCE ASSOCIATES
Ring Building Section
7 BROOKHAVEN SCIENCE ASSOCIATES
57 One person Offices6 Two people Offices7 Six people Offices3 Wet Laboratories7 Dry Laboratories8 Machine Shop9 Conference Rooms1 Loading/Storage Area
LOB First Floor Plan
Total = 38,000 gsf
Each Lab = 480 nsf
8 BROOKHAVEN SCIENCE ASSOCIATES
LOB Exterior Perspectives
LOB Entry
LOB Roofline
9 BROOKHAVEN SCIENCE ASSOCIATES
WBS 1.5 Cost BaselineWBS
BaselineLast CFAC (Nov‘09)
Current Baseline
($K)Change
($K)
1.5.1 Conventional Facilities Management 14,187 16,100 1,913
1.5.2 Conventional Facilities Engineering & Design 22,563 22,741 178
1.5.3 Conventional Facilities Construction 217,415 230,705 13,290
1.5.4 Integrated Controls, Communication & Data 561 1,256 695
1.5.5 Standard Equipment 1,026 1,026 0
1.5.6 Conventional Facilities Commissioning 578 578 0
Grand Totals 256,330 272,406 16,076
Major Increases or changes:1. Includes added CM staffing (~$0.9M) and holding place for const. safety incentive ($1M)2. Incorporated cost for larger LOBs after LOB award (~$9M)3. Incorporated post bid addendum and miscellaneous scope and field changes 4. Incorporated HXN beamline building cost (~$1.6M)5. Incorporated full data and communication cost in Integrated control, comm & data
1
2,3,45
10 BROOKHAVEN SCIENCE ASSOCIATES
CF Schedule WBS
CD-3 Approve Start of Construction Jan 09
Detailed Design CompleteBegin Detailed Design Issue RFP
Dec 07 Sept 08 Award Ring Bldg Contract Award LOBs Bore Pentant 1 Ring Building Complete CF CompleteFeb 09 Sept 10 Feb 11 April 12 June 12 LOB Complete
1.5.1 Design Phase ManagementCF Management Construction Phase Management
Close Out
Ring Bldg Detailed Design LOB Detailed Design
1.5.2Contractor Outreach/Prep RFP Prepare CF Bid Packages
Design Prepare LOB RFP&
Procurement Bid & Award Ring Bldg Contract Bid & Award CF Const. Pkgs & LOBs
Site Prep
1.5.3 Ring Building ASD Installation
Construction Elect. Substation Expansion
Packages CHW Plant
CHW Piping
LOB's
1.5.4 Integ. Ctrls & Comm. Integrated Controls & Communications
1.5.5 Standard Equipment Std Equip
1.5.6 Commissioning Ring Bldg & LOB Cx
Legend Actual Completed Planned Level 0 Control Schedule Critical Milestone Milestone Contingency Path
FY13FY08 FY09 FY10 FY11 FY12
11 BROOKHAVEN SCIENCE ASSOCIATES
CF Organization
12 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress• Ring Building contract
Excellent progress, maintaining status on or ahead of schedule– SR Tunnel concrete complete except opening at Pentant 5
- Opening used for interior courtyard access– Experimental Floor complete to Pentant 5– Structural steel complete except opening at P5 and Injection Bldg– Building enclosure, roofing and siding making good progress– Utility system installation nearing completion in interior of ring– Unit substations 6 of 8 are installed, last two in progress– Cooling Tower Building enclosure 95% complete, MEP underway– Mechanical, electrical, plumbing underway in P1, P2, P3, & P4– Booster and Linac tunnel concrete nearly complete
13 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress• Chilled Water Plant Expansion Contract
Running on/ahead of schedule – CCWF, Cooling Tower and Pump-house Buildings complete– Equipment installation in all areas nearly complete– Instruments and controls installation underway– Equipment start-up and commissioning to begin in October
• Electrical Substation Expansion ContractRunning on schedule– Ductbank installed & 15kV switchgear installed in building – 20 MVA transformer delivered, placed & tied-in– Installation of cabling in progress– Major cable pull to NSLS-II site in October
14 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress cont’d• Chilled Water Piping
Tie-in at central main and NSLS-II site complete– Last section of pipe to be installed and tested this week– Site restoration and contract completion in October– Chilled water available for the site for start-up and commissioning
• LOB ConstructionContract awarded, mobilization underway– Bonds and insurance received – HASP reviewed and being revised, NTP likely within 1 week– Held Torcon/EW Howell site coordination mtg– Held kick-off and schedule planning mtgs– Submitted HXN Building addition pkg to GC’s for price proposal– Construction underway in October, complete spring of 2012
15 BROOKHAVEN SCIENCE ASSOCIATES
One Year Ago
Photo From BGRR Stack 9-21-09Vehicle Tunnel
SR Tunnel Wall FormsSR Tunnel Slab
Status of construction Site at FY09 End
16 BROOKHAVEN SCIENCE ASSOCIATES
Technical ProgressTodayPhoto From BGRR Stack 9-20-10
Opening @ P5
Booster Tunnel Roof DeckRoof Insulation
Exterior Siding
• SR tunnel and structural steel complete except P5 opening• Roof deck complete, Insulation to P5, Finished SSM Roof at P1• P1, & 2,Cooling Twr, RF & Compressor Bldg Enclosure all underway• Utility installation ~80% complete in inner courtyard
Lobby Curtain-wall
Clg Twr Bldg
Finished SSM Roof
Opening for LOB 1
17 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress cont’d
Exterior Siding
Pentant -1 – Ductwork & Piping In Place
SR Tunnel – Painted, Conduit , Lighting & Ductwork Installed
18 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress cont’d
Vehicle Tunnel Nearly Ready For Use
Injection Bldg Booster Ring Tunnel
RF Area Unit Substation
19 BROOKHAVEN SCIENCE ASSOCIATES
Overall Cost and Schedule Assessment• Cost Assessment: Cumulative cost variance $+2.3M or +1.8%
• On budget - CPI =1.02• Schedule Assessment: Cumulative schedule variance $+5.9M or +4.7%
• On or slightly ahead of schedule - SPI =1.05
20 BROOKHAVEN SCIENCE ASSOCIATES
Variance Analysis
• Cost Variance +$2.3M• Temporary positive cost variance due to differences in accrued vs
monthly invoiced values • Actual positive cost variance ~ $400k due to miscellaneous small
underruns - >91% of remaining work is under fixed price contract• This variance expected to go to zero $ as contracts are closed out
• Schedule Variance +$5.6 M• Work in P1 – P5 ahead of plan for concrete, steel, enclosure and
mechanical, electrical & plumbing• Work on Cooling Tower & Process Water Systems ahead of plan• Remaining contracts on or close to plan
21 BROOKHAVEN SCIENCE ASSOCIATES
Risks
• Construction Safety - program must continue to be effective• Substantial performance improvement since 9/30/09 accident• Increased number of construction safety engineers to 3, soon to be 4• Continually working with GC to improve program
• Potential for field changes, errors/omissions thru construction• Running ~ 1.5% - see following slide for breakdown of status to date
• Potential for design changes from ASD & XFD• Running ~ 1.5% - see following slide for breakdown of status to date• System coordination is now complete – risk reduced
• Risks of Ring Bldg GC and LOB GC conflicts• Effective plan and requirements for coexisting on the site
22 BROOKHAVEN SCIENCE ASSOCIATES
Ring Bldg Contract Change status
• As of 9/30/10 will have completed $101M work – 57%• Changes due to approved scope changes or design maturity
• $1.58M to date or ~1.5% of work to date• Weekly interface mtgs effective at identifying changes early
• Changes due to design errors & omissions• $1.56M to date or ~1.5% of work to date• This includes projected estimate of changes not yet agreed upon
• Changes due to existing conditions• Very low at just $130k – no more of these changes likely
• Weekly mtg w/GC to expedite resolution of changes
23 BROOKHAVEN SCIENCE ASSOCIATES
Issues• Continued focus on contractor safety performance is essential• Need to maintain close oversight of detailed contractor schedule
activities needed to achieve BORE’s• Engineering staff heavily loaded
– Process of resolving and implementing contract changes is labor intensive– Possible added scope from ASD & XFD will add to load– Engineering involvement required for start-up and commissioning
Mitigating factors– LOB document submittal/review phase starting up as Ring bldg winds down– Workload should ease soon as CHW and Electric Utility pkgs are completed
24 BROOKHAVEN SCIENCE ASSOCIATES
Conclusions
• CF activities are on budget and on or ahead of schedule• Contractor safety program has improved substantially
– Applying lessons learned to LOB safety program• Construction proceeding well
– CHW & elect substation winding down – move focus to LOB• LOB mobilization underway and progressing well• Getting ready for equipment start-up and commissioning• On track for 1st Ring Bldg beneficial occupancy 2/11 & Ring
Bldg construction completion 4/12
25 BROOKHAVEN SCIENCE ASSOCIATES
Charge Items1. Are Conventional Facilities Division’s plans & performance consistent
with achieving project cost, schedule, and technical objectives• Covered in multiple status presentations
2. Are the plans and measures to assure construction worker safety appropriate and effective at minimizing potential for worker injury?
• See Ken Krasner Presentation on Construction safety 3. Are the proper plans, measures and resources in place for effectively
managing the coexistence of the Ring Building and LOB contractors on the same construction site?
• See Mike Bromfield Presentation on LOB and Ring Bldg GC Coexistance4. Are the plans and measures to assume beneficial occupancy of the
facilities sufficient to enable orderly installation of accelerator systems and eventual transition to operations?
• Covered in multiple presentations on BORE, ASD Installation & Ops planning