Upload
norah-baldwin
View
216
Download
0
Embed Size (px)
Citation preview
1 BROOKHAVEN SCIENCE ASSOCIATES
Conventional Facilities
Steve DierkerDirector, NSLS-II Conventional Facilities Division
NSLS-II User WorkshopJuly 17, 2007
2 BROOKHAVEN SCIENCE ASSOCIATES
Outline
• Conventional Facilities Scope– Site Plan– Building Program– Sustainable Design
• BNL Support• CF Schedule & Risk Analysis• Conventional Facilities Deliverables for Users
– Beamline Support Space – LOB’s– Experimental Floor– Utility Services for Beamlines– Stability Goals
• CF Path Forward
3 BROOKHAVEN SCIENCE ASSOCIATES
NSLS-II Siteplan
Access Tunnel
LOB (1 of 3)JPSI
NSLS
CFN
BLOC
NSLS-II
Service Bldgs (1 of 5)
CHW Plant
Bldg 603 Substation
Future LOB’s
4 BROOKHAVEN SCIENCE ASSOCIATES
View of NSLS-II
JPSI
Entry LobbyLOB
LINAC/Booster
5 BROOKHAVEN SCIENCE ASSOCIATES
NSLS-II Main Entry Lobby
JPSI
Entry LobbyLOB
LINAC/Booster
6 BROOKHAVEN SCIENCE ASSOCIATES
NSLS-II Floor PlanNSLS-II Floor Plan
1.BLOC – Booster/LINAC/ Operations Center
2.LOB – Lab Office Buildings (3 base scope up to 5 future)
3.Service Buildings (5)
4.RF Area
5.Tunnel Area
6.Electrical Mezzanine
7.Experimental Floor
8.Access Corridor
14
3
2
2
2 2
2
3
3
3
3
7 BROOKHAVEN SCIENCE ASSOCIATES
Facility Program
Base Scope Full Build-OutGSF GSF
Ring Building 242,000 242,000 Service Buildings 40,000 40,000 RF Area 10,000 10,000
Operations Center 12,000 12,000
Booster Ring 15,000 15,000
Linac 7,000 7,000
64,000 110,000
Total GSF 390,000 436,000
Building /Area/Function
Lab Office Buildings
Base plan provides 3 large LOB’s to support rapid build-out of beamlines with plan for 2 more LOB’s to be added in future
8 BROOKHAVEN SCIENCE ASSOCIATES
Sustainable Design
• DOE will require Certification to USGBC LEED “Gold” std.• Reviewing DOE guidance on how it will be applied to NSLS-II
process systems• Additional investment in these areas should achieve Gold
• Additional storm & potable water credits• Additional reuse/sustainable material credits• Systems for added energy efficiency
• Photovoltaics & renewable energy credits• Heat recovery
39 15 15 Project Totals (pre-certification estimates)
Certified 26-32 points Silver 33-38 points Gold 39-51 points Platinum 52-69 points
Y M N
9 BROOKHAVEN SCIENCE ASSOCIATES
BNL Support
•BNL Support to the project is important and demonstrable• Warehouse Demolition & Replacement
– Must remove Bldgs 86, 100, 210, 211, and 481 before FY 09– Warehouse facility replacement is underway as GPP project– Demolition planned for Spring FY08
• Chilled Water Plant Expansion– NSLS-II and Lab will share expansion cost as both need added capacity– A/E selected and ready to begin design– Design to run concurrent with NSLS-II T-I and T-II– Construction start in FY09 and complete early FY11
10 BROOKHAVEN SCIENCE ASSOCIATES
Existing Site Building 603
CCWF
Bldg 100
Bldg 209
Bldg 86
Bldg 210
Bldg 481
Bldg 211
11 BROOKHAVEN SCIENCE ASSOCIATES
CF Schedule
Title I Design
CD-2
Title II Design
CD-3
Site Prep. Const.
Ring Bldg Bid & Award
1st Pentant RFE (Pentant 1)
2nd Pentant RFE (Pentant 5)
3rd Pentant RFE (Pentant 2)
4th Pentant RFE (Pentant 3)
5th Pentant RFE (Pentant 4)
Booster/LINAC/Ops Ctr (BLOC)
Lab/Office Bldg’s (LOB’s)
CHW Plant Expansion
Mech & Elect Utilities
Integrated Ctrl & Comm.
Standard Equipment
Commissioning
Activity FY07 FY08 FY09 FY010 FY11 FY12 FY13
Begin Accelerator Installation
Full Ring Bldg Available for Accelerator & Beamline Installation
Control Room RFE
LOB’s Complete
BO for all CF Construction
12 BROOKHAVEN SCIENCE ASSOCIATES
Risk Assessment
• Technical Risk• Primarily building stability, vibration & temperature control
• Schedule Risks• Title I & II Engineering are on the critical path• Construction of Ring Building is critical path
• Cost Risks• Technical and schedule risks can impact costs• Construction and material markets are still volatile
• Risk registry has been prepared • Risk assessment database integrated with cost estimate database
• Current Contingency allocated for Conventional Facilities ~ 40%
13 BROOKHAVEN SCIENCE ASSOCIATES
CF Deliverables for Users
• Provide a facility that promotes collaborative leading edge research in a pleasant working environment
• Structurally stable facility with low vibration (<25 nm rms)• Experimental floor temperature stability of +/- 1.0 deg F• Utility capacity & shielding for 3 GeV operation• Facility layout that enables future long beamlines• Facility design enabling future expansion to support full beamline
build-out• A reasonably quiet Experimental Floor - noise level <NC 60• Convenient parking and access to Labs/Offices/Beamlines
14 BROOKHAVEN SCIENCE ASSOCIATES
LOB Features
• Modular design – can be added when needed without interrupting operation
• 3 @ 22,800 SF each – Each serves six sectors• 72 offices w/ conference space, interaction areas, lavs, showers• 6 labs - intended for shared use• Shipping/Receiving/Storage area & chemical storage area• Potential for expansion for 2 more LOB’s
• Egress provided for personnel and large items at each LOB• Loading area with exterior roll-up door• Double-door from each lab onto the experimental floor• Rolling access to all beamline areas
15 BROOKHAVEN SCIENCE ASSOCIATES
LOB Layout
22,800 SF
16 BROOKHAVEN SCIENCE ASSOCIATES
LOB Elevation
17 BROOKHAVEN SCIENCE ASSOCIATES
Ring Building Section
Ratchet or Shield Wall
Electrical Mezzanine
Bldg structure Isolated from tunnel and experimental Floor
Earth Shield Berm
Experimental Floor
Access Corridor
Tunnel Floor
“Monolithic Joint”
Isolation Joint
Isolation Joint or Void Space
Tunnel Roof
Isolated Pier for Column
Isolated Grade BeamBeamline Utility Services
18 BROOKHAVEN SCIENCE ASSOCIATES
Beamline Utility Support
• Services provided at each BL include:• Electric Power Panel at Ratchet Wall, 75-95 kW/Cell, 120/208V• Cooling Water, HVAC Supply Air, Exhaust• Compressed Air, LN2, GN2
• DI Water (Copper and Aluminum)
19 BROOKHAVEN SCIENCE ASSOCIATES
Stability Dependent on Conventional Facilities
• Stability goals driven by conventional facility design• Stability of storage ring tunnel floor
• Vibration < 25 nm rms from PSD from 4-50 hz (vertical)• Stability of experimental floor
• Vibration level of ~ 25 nm rms (vertical) from PSD from 4-50 hz for general floor area• Vibration level for 1 nm resolution beam lines requires further definition but appears
achievable with proper correlation• Thermal stability of storage ring tunnel environment
• +/- 0.1o C• Thermal stability of experimental floor
• +/- 0.5o C
20 BROOKHAVEN SCIENCE ASSOCIATES
CF Path Forward
• Design well underway for November CD-2 reviews• Additional focused technical studies underway for:
• Vibrational stability of tunnel & experimental floor• Stability needed for 1 nm resolution beamlines• Optimization of thermal stability• Methods to achieve sustainability goals • CF design and cost if extra-long straits are installed
• Value engineering review & technical review planned for September