Upload
fredericka-miller
View
32
Download
1
Embed Size (px)
DESCRIPTION
LCLS Ultrafast Science Instruments (LUSI). Project Management Control System. Felix B. Fernandez – Project Controls August, 2008. PMCS. Topics: System Overview PMCS Development Process PMCS Current Status Summary and Questions. PMCS Overview. The LUSI Project Management Control System: - PowerPoint PPT Presentation
Citation preview
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 1
LCLS Ultrafast Science InstrumentsLCLS Ultrafast Science Instruments (LUSI)(LUSI)
Felix B. Fernandez – Project ControlsAugust, 2008
Project Management Control System
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 2
PMCS
Topics:
System Overview
PMCS Development Process
PMCS Current Status
Summary and Questions
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 3
PMCS Overview
The LUSI Project Management Control System:
Complies with DOE Order 413.3A
Complies with the 32 criteria from ANSI/EIA-748-A
Complies with the LUSI Project Execution Plan
Modeled after the LCLS Project PMCS
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 5
PMCS Overview
SLAC/LCLSPMCS
Procedures
ScheduleReports
ScheduleBaseline
SLACAccounting
System
AnalysisTool
“Hammer”
CostReports
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 6
PMCS Overview
LUSI PMCS is defined and controlled by LCLS Procedures:
Earned Value Management System Description – LCLS 1.1-015
CA and WP Planning Procedure – LCLS 1.1-018
Change Control Procedure – LCLS 1.1-019
Project Schedule Procedure – LCLS 1.1-020
Cost Estimating Procedure – LCLS 1.1-021
Monthly Status and Reporting Procedure – LCLS 1.1-022
Subcontract Management Procedure – LCLS 1.1-023
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 7
PMCS Overview
Using Primavera (P3) as the Scheduling tool
Have established a Project group with supporting project files maintained independently:
LUSI Project Group
Project Management (SLAC)
XPP Instrument (SLAC)
CXI Instrument (SLAC)
XCS Instrument (SLAC)
Diagnostics and Common Optics (SLAC)
Controls and Data Acquisition (SLAC)
XPP and XCS Detector Systems (BNL)
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 8
PMCS Overview
Using Cobra as the Budgeting tool
Have created a Cobra project file for MIE funded effort.
The project also uses a web based tool called the “PMCS Hammer” that integrates Primavera, Cobra and Accounting data.
The “PMCS Hammer” is updated monthly following the month end cycle and provides team members a way of accessing/analyzing their data and writing their VARs.
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 10
PMCS Overview
Jeff Chan Craig Brackett Jay Doubrava Pat Dunn Hok Leung Cathy Lavelle
LCLSProject Office XConv Facilities X xControls XLinac X xXE X
Controls XXTOD X
Controls XUndulator XInstallation X xCommisioning XDatabase X x
LUSIProject Office XXPP XCXI X xXCS XDCO XControls XBNL XDatabase X x
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 11
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 12
PMCS Development Process
Define Schedule and Budget assumptions
Finalize the WBS, WBS Dictionary
Finalize a Responsibility Assignment Matrix (RAM)
Finalize the Milestone Hierarchy and Dictionary
Finalize the set of SLAC/BNL Resources and Rates
Finalize the resource loaded Integrated Master Schedule
Use the Schedule baseline to create a Budget baseline
Establish a prelim Performance Measurement Baseline
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 13
PMCS Development Process
Schedule AssumptionsWithin the funding limitations, get to an Early Science capability with the Instruments as early as possible.
Establish priority order of Instruments as XPP, CXI and XCS.
Establish multiple CD-4 milestones, one for each Instrument.
Components not required for Early Science operations can be installed for final CD-4 milestone.
Establish multiple CD-3 milestones to allow procurement of components for each Instrument as early as possible.
Establish a complete performance measurement baseline for all project equipment and conduct one CD-2.
Assume a Long Lead Authorization approval for Key critical components following CD-2 and prior to CD-3.
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 14
PMCS Development Process
Budget Assumptions
Plan for an MIE funding profile of:
Plan for a Continuing Resolution for the first half of FY2009 (approx. $500k/month).
The balance of FY2009 funding will be available in the third quarter($12M).
Use Resources and Rates (Direct/Indirect) provided by SLAC and BNL.
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 15
PMCS Development Process
Project WBS and WBS Dictionary
The Work Breakdown Structure has been placed under change control
PM-391-000-96
The WBS Dictionary has been updated to reflect the latest structure and has been placed under change control
PM-391-001-12
The Responsibility Assignment Matrix (RAM) has been developed that identifies Control Accounts and CA Managers
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 16
Control Account Managers
T. Fornek - WBS 1.1 Project Management
J. Langton - WBS 1.2 XPP Instrument *
P. Montanez - WBS 1.3 CXI Instrument
E. Bong - WBS 1.4 XCS Instrument *
E. Ortiz - WBS 1.5 Diagnostics & Common Optics
G. Haller - WBS 1.6 Controls & Data Acquisition
Niels van Bakel - WBS 1.2.03 & 1.4.03 BNL Detectors
* Except for BNL Detector effort
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 17
PMCS Development Process
Project Milestone Hierarchy and Dictionary
The Milestone Hierarchy has been created and defines the
relationship between the levels of milestones.
Six levels of milestones have been identified
Level 1 & 2 - DOE
Level 3 – Project
Level 4 – Instruments/Systems
Level 5 – Interface / Handoff
Level 6 – Commitments / Awards
The Milestone Dictionary has been developed to assure a
thorough understanding of agreements
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 18
PMCS Development Process
Several types of Level 5, Interface / Handoff Milestones have been defined and represent contractual agreements.
LUSI is currently monitoring 904 Interface Milestones
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 19
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 20
PMCS Development Process
Level 6 milestones have been identified as the Awards of subcontracts / procurements and supports funding reconciliations efforts.
Planning when the budget is to be spent will support performance measurement.
LUSI is currently monitoring 224 Award Milestones.
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 21
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 22
PMCS Development Process
Project Resources and Rates
Define a set of Resources for effort to be performed by SLAC
with the appropriate planning rates.
Define a set of Resources for effort to be performed by BNL with
the appropriate planning rates.
Use the appropriate indirect rates, as defined by SLAC/BNL, and
apply to the direct rates as defined.
Apply a consistent escalation to activities as they get scheduled.
The Bay Area uses a 4% escalation rate for labor
Used standard 2.3% escalation for non-labor
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 23
Integrated Schedule Development Process
Use WBS as foundation to assure 100% of scope covered
Define the detailed tasks required to accomplish the scope
Define the required resources to accomplish the tasksBased on the detailed Basis of Estimates
Define the optimal logic relationships between tasks
Incorporate all levels of DOE and Project milestones
Incorporate all Interface / handoff milestones.
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 24
Integrated Schedule Development Process (cont.)
Validate links to confirm timephasing and float calculations are accurate and appropriate.
Where applicable, base activity durations on recent LCLS and/or related experience.
Define and use standard calendars throughout with all the appropriate non-work days.
Plan for a standard work week (8 hours/day & 5 days/week) except where appropriate.
Develop flexible and appropriate activity coding for reporting and summarizations
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 25
Integrated Schedule Development Process (cont.)Because the project recognizes the importance of managing schedule contingency like it manages money contingency, blocks of time will be built into the schedule to mitigate the inevitable schedule issues.
These reserves of time will be planned as activity relationship lags between the Project controlled Level 3 milestones and the DOE controlled Level 2 milestones.
These blocks of schedule contingency were used during the development of the detail schedules and were removed to set preliminary baseline dates. The blocks will be added back into the schedule to impose control over float utilization.
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 26
The project has reserved time between DOE level 2 milestones and DOE level 1 milestones to allow for DOE processing:
“Project Ready” + 40 days = DOE Review + 40 days = CD-3a
“Project Ready” + 60 days = DOE Review + 40 days = CD-4a
“Project Ready” + 40 days = DOE Review + 40 days = CD-3b
“Project Ready” + 60 days = DOE Review + 40 days = CD-4b
“Project Ready” + 40 days = DOE Review + 40 days = CD-3c
“Project Ready” + 60 days = DOE Review + 40 days = CD-4a
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 27
For the purposes of managing Total Float, time reserves will be set aside between project level 3 milestones and DOE level 2 milestones:
“Project Ready” + 40 days = DOE Review + 40 days = CD-3a
“Project Ready” + 60 days = DOE Review + 40 days = CD-4a
“Project Ready” + 40 days = DOE Review + 40 days = CD-3b
“Project Ready” + 60 days = DOE Review + 40 days = CD-4b
“Project Ready” + 40 days = DOE Review + 40 days = CD-3c
“Project Ready” + 60 days = DOE Review + 40 days = CD-4a
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 28
PMCS Development Process
Each one of the 3 Instruments will have 100 days of schedule contingency controlled by the project office.
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 29
In addition to the WBS, project phase coding for each activity will facilitate the creation of summary schedules as well as define the budget work packages.
Management / Administration
Design / Engineering
Procurement
Subcontract
Fabrication / Assembly
Testing
Installation
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 30
Additional activity coding will facilitate sorting, filtering and additional summarizations
Work Breakdown StructureControl Account numberWork Package numberProject PhaseMilestone LevelControl Account Manager namePerformance Measurement TechniqueEarned Value Milestone (EVM) ID numberEVM WeightDesign MaturityJudgment Factor
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 31
Funding Reconciliation
The project started with a “bottom-up” planning approach which
required budget authority inconsistent with the levels that were
established.
Reconciliation required the identification of opportunities and the
prioritizations of effort to adjust for funding issues at the lowest
level.
The project next used a iterative “top-down” approach to shift
entire blocks of effort to optimize the schedule flow while
accelerating the Instrument availability.
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 32
Once the schedule was iterated and a reasonable
schedule was achieved that met the project objectives
and stayed within the available funding, the
preliminary schedule baseline was established.
With a baseline established in the Primavera file, the
next step was to import the schedule data into Cobra
to create the budget baseline and to establish a
preliminary performance measurement baseline
(PMB).
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 33
Control Account and Work Package planning is based entirely on the time-phasing as defined by the schedule.
Work packages are based on the project phase and represents the cost collection intersection with the SLAC accounting system.
The work package is the lowest level at which earned value is calculated.
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 34
The majority of the near term effort for the project will be focused on Engineering and Design.
Procurement, Subcontract, Fabrication & Assembly, Testing and Installation work packages are coded as Planning Packages.
The detail planning for work packages coded as planning packages will be reassessed at the appropriate time.
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 35
LUSI uses only a subset of the Performance Measurement Technique (PMT) codes used by Cobra to calculate Earned Value are coded into the
schedule as a reference
PMCS Development Process
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 37
Critical Decision Requirements
• Employ an Earned Value Management System that is compliant with ANSI/EIA-748-A-1998 for projects with a Total Project Cost or Environmental Management Total Project Cost greater than or equal to $20M. Projects having a Total Project Cost or Environmental Management Total Project Cost between $20M and $50M must have an Earned Value Management System that is self-certified by the contractor as ANSI/EIA-748-A-1998 compliant. Projects having a Total Project Cost or Environmental Management Total Project Cost greater than or equal to $50M require an ANSI/EIA-748-A-1998 compliant system certified by the Office of Engineering and Construction Management. For projects not required to utilize an Earned Value Management System (e.g., firm fixed-price contract projects), an alternative performance management system must be described in the Project Execution Plan.• Completed – SLAC/LCLS Project was reviewed and successfully
demonstrated compliance at a review in June 2008• Subsequent to the June review a formal letter from DOE was received
confirming the compliance of the SLAC Earned Value Management System.
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 38
Critical Decision Requirements
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 39
• Perform a Performance Baseline Validation External Independent Review or a Performance Baseline Validation Independent Project Review. External Independent Reviews are conducted by the Office of Engineering and Construction Management to validate the Performance Baseline for projects with a Total Project Cost or Environmental Management Total Project Cost greater than or equal to $100M. Independent Project Reviews are conducted by the Project Management Support Office to validate the Performance Baseline for projects with a Total Project Cost or Environmental Management Total Project Cost less than $100 M.• The Independent Review is to be accomplished as part of the CD-2
review
Critical Decision Requirements
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 40
EIR Lines of InquiryEIR ELEMENT COMMENT CD2
Ready
1. Work Breakdown Structure PM-391-000-96 (Structure)
2. Project Cost & Resource Loaded Schedule
Working baselines set as of month end March 2008 for both the schedule in P3 and the project cost in Cobra
3. Cost & Schedule Assumptions Covered in this presentation
4. Critical Path Critical paths for CD-4a, CD-4b and CD-4c available
5. Risk Management Mgmt presentation
6. Funding Profile Mgmt presentation
7. Project Controls/EVMS Overview and status covered in this presentation
8. Basis of Design Engineering presentation
9. Design Review Engineering presentation
10. System Functions & Reqs Engineering presentation
11. Sustainability Not applicable
12. Hazards Analysis PM-391-001-01
13. Value Management/Engineering LUSI Value Management Plan (Doc No. PM-391-000-02)
14. Start-up Test Plan SP-391-001-15, -16, -17 (XPP, CXI, XCS)
15. Project Execution Plan Draft ready for signature pending CD-2 review changes
16. Acquisition Strategy
17. Integrated Project Team This presentation & the PEP
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 42
PMCS Status
Using Primavera (P3) as the Scheduling tool
Currently the statistics for the LUSI Project group with supporting project files are:
LUSI Project Group - 4131 activities & 6159 relationships
Project Management (SLAC) - 191 activities
XPP Instrument (SLAC) - 531 activities
CXI Instrument (SLAC) - 899 activities
XCS Instrument (SLAC) - 539 activities
Diagnostics and Common Optics (SLAC) - 599 activities
Controls and Data Acquisition (SLAC) - 1297 activities
XPP and XCS Detector Systems (BNL) - 75 activities
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 43
LUSI Project Summary Schedule
=Level 1 & 2 DOE
=Level 3 Project Ready
XCS
FY12FY07
XPP
CXI
FY08 FY09 FY10 FY11
Ready for CD-4bApr 2011
Ready for CD-4cMar 2012
Ready for CD-4aJul 2010
Ready for CD-3cFeb 2010
Ready for CD-3bOct 2009
Ready for CD-3aFeb 2009
CD-2 ReviewAug 2008
CD-1 ApprovalSep 2007
Design Procure / Fab / Assy / Install (Components not part of CD-4a)
Procure / Fab / Assy / Install (Comp. not part of CD-4b)
Procure / Fab / Assy / InstallDesign
Design
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 44
Schedule Critical Path(s)
Because each Instrument represents a separate major
deliverable, critical paths have been identified and are
being monitored to the Approve Start of Operations
milestones:
CD-4a for the XPP Instrument
CD-4b for the CXI Instrument
CD-4c for the XCS Instrument
As a general rule, critical paths/envelopes are
regularly monitored for all three instruments and the
two supporting systems.
LUSI Critical Paths/Envelopes
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 45
XPP Schedule Critical Path
Driving Milestones
LL Approval,CD-3 & CD-4
Diffractometer Design Effort
Diffractometer Awards &
Vendor effort
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 46
XPP Schedule Critical Path
Diffractometer deliveries to the
Installation effort
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 47
CXI Schedule Critical Path
Driving Milestones
LL Approval,CD-3 & CD-4
KB Mirrors Reqmts/Design
Effort
KB Mirrors AWARD &
Vendor Design
Post Vendor Effort and Installation
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 48
CXI Schedule Critical Path
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 49
XCS Schedule Critical Path
Driving Milestones
LL Approval, CD-3, CD-4 & Funding M/S
Delayed Design Start due to
Funding
XCS Path moves to DCO
Procurements
XCS Instrument Installation effort
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 50
XCS Schedule Critical Path
Procurement of DCO components delayed to FY11 due to funding
Design & initial procurement was completed for the XPP Instrument
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 51
XCS Schedule Critical Path
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 52
DCO Schedule Critical Envelope
DCO has one design effort and multiple procurements to support the Instrument reqmts. The project will
monitor strings of activities with the least float
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 53
DCO Schedule Critical Envelope
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 54
CDA Schedule Critical Envelope
CDA has multiple deliveries to the instruments and is
heavily driven by their needs. The project will
monitor strings of activities with the least float
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 55
CDA Schedule Critical Envelope
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 58
PMCS Status
Measurable Effort
Level of Effort
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 59
PMCS Status
Labor
Non-Labor
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 62
Statusing and Reporting
SLAC/LCLSPMCS
Procedures
ScheduleReports
ScheduleBaseline
SLACAccounting
System
AnalysisTool
“Hammer”
CostReports
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 63
Statusing and Reporting
LUSI Project data is now stored on the LCLS website.
https://slacspace.slac.stanford.edu/sites/LCLS%20Document%20Storage/default.aspx
Toward the bottom there’s a PMCS section.
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 64
Statusing and Reporting
PMCS data will be stored and available in the folders as described. The PMCS Hammer is an interactive tool team members will use to view, analyze data and write
VARs
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 65
Statusing and Reporting
The PMCS Hammer is a utility that was customized for SLAC/LCLS that integrates Primavera, Cobra and Accounting data for any team member to use. The LCLS
Hammer and LUSI Hammer pages are access controlled and access is granted as appropriate.
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 66
Statusing and Reporting
The Drilldown CPR and DCE will probably be the most often used utilities, but other information is available.
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 67
Statusing and Reporting
The CPR Drilldown identifies areas that have broken a threshold that requires a VAR.
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 68
Statusing and Reporting
By double-clicking on the highlight variance, the VAR form will be enabled.
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 69
In Conclusion
The project set preliminary schedule and budget baselines as of March 2008.
The project team is ready for CD-2. We are ready to formally establish a performance measurement baseline and to proceed with the project.
Thank you for your participation
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 72
PMCS Status
Labor
Non-Labor
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 74
PMCS Status
Labor-SLAC
Non-Labor-SLAC
Labor-BNL
Non-Labor-BNL
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 76
PMCS Status
Labor
Non-Labor
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 78
PMCS Status
Labor-SLAC
Non-Labor-SLAC
Labor-BNL
Non-Labor-BNL
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 80
PMCS Status
Labor
Non-Labor
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 82
PMCS Status
Labor
Non-Labor
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 83
Milestones with PO ContingencyActivity ID Activity description MS Level
Early Finish
Late FinishTotal float
PM000000 CD-0 MISSION NEED APPROVAL L1 08/10/05A 08/10/05A
PM001000 CD-1 COST RANGE APPROVAL L1 09/27/07A 09/27/07A
PM002000 CD-2 PERFORMANCE BASELINE APPROVED L1 10/13/2008 3/2/2009 88
PM002100 COMPLETE CD-2 REQUIREMENTS - XPP / CXI / XCS L2 8/18/2008 1/5/2009 88
PM002150 PROJECT READY FOR CD-2 APPROVAL L3 7/28/2008 12/1/2008 88
PM002200 LONG LEAD PROCUREMENT APPROVED-Early Science L1 12/10/2008 4/27/2009 88
PM002210 LONG LEAD AWARD - XPP DIFFRACTOMETER L3 7/1/2009 7/21/2009 14
PM002220 LONG LEAD AWARD - CXI KB MIRROR SYSTEMS L3 7/6/2009 12/8/2009 109
PM003000 CD-3a CONSTRUCTION START APPROVED - XPP L1 5/28/2009 7/2/2009 25
PM003010 COMPLETE CD-3a REQUIREMENTS - XPP L2 4/2/2009 5/7/2009 25
PM003020 PROJECT READY FOR CD-3a APPROVAL - XPP L3 2/5/2009 3/12/2009 25
PM003030 CD-3b CONSTRUCTION START APPROVED - CXI L1 3/8/2010 4/1/2010 18
PM003040 COMPLETE CD-3b REQUIREMENTS - CXI L2 1/11/2010 2/4/2010 18
PM003050 PROJECT READY FOR CD-3b APPROVAL - CXI L3 10/29/2009 11/24/2009 18
PM003060 CD-3c CONSTRUCTION START APPROVED - XCS L1 6/9/2010 10/5/2010 84
PM003070 COMPLETE CD-3c REQUIREMENTS - XPP / CXI / XCS L2 4/14/2010 8/10/2010 84
PM003080 PROJECT READY FOR CD-3c APPROVAL - XCS L3 2/17/2010 6/15/2010 84
PM004000 CD-4a START OF OPERATIONS APPROVED XPP L1 12/17/10* 12/17/10* 0
PM004010 APPROVED: Instrument Readiness Review - CD-4a L2 9/30/2010 10/20/2010 14
PM004020 PROJECT READY FOR CD-4a APPROVAL L3 7/8/2010 7/28/2010 14
PM004100 CD-4b START OF OPERATIONS APPROVED-CXI L1 09/30/11* 09/30/11* 0
PM004110 APPROVED: Instrument Readiness Review - CD-4b L2 7/12/2011 8/5/2011 18
PM004120 PROJECT READY FOR CD-4b APPROVAL L3 4/19/2011 5/13/2011 18
PM004200 CD-4c START OF OPERATIONS APPROVED-XPP/CXI/XCS L1 08/31/12* 08/31/12* 0
PM004210 APPROVED: Instrument Readiness Review - CD-4c L2 6/8/2012 7/6/2012 20
PM004220 PROJECT READY FOR CD-4c APPROVAL L3 3/16/2012 4/13/2012 20
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 84
Milestones without PO ContingencyActivity ID Activity description MS Level
Early Finish
Late FinishTotal float
PM000000 CD-0 MISSION NEED APPROVAL L1 08/10/05A 08/10/05A
PM001000 CD-1 COST RANGE APPROVAL L1 09/27/07A 09/27/07A
PM002000 CD-2 PERFORMANCE BASELINE APPROVED L1 10/13/2008 7/17/2009 187
PM002100 COMPLETE CD-2 REQUIREMENTS - XPP / CXI / XCS L2 8/18/2008 5/22/2009 187
PM002150 PROJECT READY FOR CD-2 APPROVAL L3 7/28/2008 5/1/2009 187
PM002200 LONG LEAD PROCUREMENT APPROVED-Early Science L1 12/10/2008 9/11/2009 187
PM002210 LONG LEAD AWARD - XPP DIFFRACTOMETER L3 6/23/2009 10/6/2009 75
PM002220 LONG LEAD AWARD - CXI KB MIRROR SYSTEMS L3 7/6/2009 3/16/2010 169
PM003000 CD-3a CONSTRUCTION START APPROVED - XPP L1 4/2/2009 9/24/2009 125
PM003010 COMPLETE CD-3a REQUIREMENTS - XPP L2 2/5/2009 7/30/2009 125
PM003020 PROJECT READY FOR CD-3a APPROVAL - XPP L3 2/5/2009 7/30/2009 125
PM003030 CD-3b CONSTRUCTION START APPROVED - CXI L1 1/11/2010 6/24/2010 118
PM003040 COMPLETE CD-3b REQUIREMENTS - CXI L2 10/29/2009 4/29/2010 118
PM003050 PROJECT READY FOR CD-3b APPROVAL - CXI L3 10/29/2009 4/29/2010 118
PM003060 CD-3c CONSTRUCTION START APPROVED - XCS L1 4/14/2010 1/13/2011 184
PM003070 COMPLETE CD-3c REQUIREMENTS - XPP / CXI / XCS L2 2/17/2010 11/2/2010 184
PM003080 PROJECT READY FOR CD-3c APPROVAL - XCS L3 2/17/2010 11/2/2010 184
PM004000 CD-4a START OF OPERATIONS APPROVED XPP L1 12/17/10* 12/17/10* 0
PM004010 APPROVED: Instrument Readiness Review - CD-4a L2 7/7/2010 10/20/2010 75
PM004020 PROJECT READY FOR CD-4a APPROVAL L3 7/7/2010 10/20/2010 75
PM004100 CD-4b START OF OPERATIONS APPROVED-CXI L1 09/30/11* 09/30/11* 0
PM004110 APPROVED: Instrument Readiness Review - CD-4b L2 3/25/2011 8/5/2011 95
PM004120 PROJECT READY FOR CD-4b APPROVAL L3 3/25/2011 8/5/2011 95
PM004200 CD-4c START OF OPERATIONS APPROVED-XPP/CXI/XCS L1 08/31/12* 08/31/12* 0
PM004210 APPROVED: Instrument Readiness Review - CD-4c L2 3/16/2012 7/6/2012 80
PM004220 PROJECT READY FOR CD-4c APPROVAL L3 3/16/2012 7/6/2012 80
Felix B. [email protected]
LUSI DOE Review August 20, 2008PMCS Overview p. 85
Milestones with no Funding LimitsActivity ID Activity description MS Level
Early Finish
Late FinishTotal float
PM000000 CD-0 MISSION NEED APPROVAL L1 08/10/05A 08/10/05A
PM001000 CD-1 COST RANGE APPROVAL L1 09/27/07A 09/27/07A
PM002000 CD-2 PERFORMANCE BASELINE APPROVED L1 10/13/2008 7/17/2009 187
PM002100 COMPLETE CD-2 REQUIREMENTS - XPP / CXI / XCS L2 8/18/2008 5/22/2009 187
PM002150 PROJECT READY FOR CD-2 APPROVAL L3 7/28/2008 5/1/2009 187
PM002200 LONG LEAD PROCUREMENT APPROVED-Early Science L1 12/10/2008 9/11/2009 187
PM002210 LONG LEAD AWARD - XPP DIFFRACTOMETER L3 6/23/2009 10/6/2009 75
PM002220 LONG LEAD AWARD - CXI KB MIRROR SYSTEMS L3 4/2/2009 3/16/2010 236
PM003000 CD-3a CONSTRUCTION START APPROVED - XPP L1 4/2/2009 9/24/2009 125
PM003010 COMPLETE CD-3a REQUIREMENTS - XPP L2 2/5/2009 7/30/2009 125
PM003020 PROJECT READY FOR CD-3a APPROVAL - XPP L3 2/5/2009 7/30/2009 125
PM003030 CD-3b CONSTRUCTION START APPROVED - CXI L1 1/11/2010 6/24/2010 118
PM003040 COMPLETE CD-3b REQUIREMENTS - CXI L2 10/29/2009 4/29/2010 118
PM003050 PROJECT READY FOR CD-3b APPROVAL - CXI L3 10/29/2009 4/29/2010 118
PM003060 CD-3c CONSTRUCTION START APPROVED - XCS L1 1/11/2010 1/13/2011 251
PM003070 COMPLETE CD-3c REQUIREMENTS - XPP / CXI / XCS L2 10/29/2009 11/2/2010 251
PM003080 PROJECT READY FOR CD-3c APPROVAL - XCS L3 10/29/2009 11/2/2010 251
PM004000 CD-4a START OF OPERATIONS APPROVED XPP L1 12/17/10* 12/17/10* 0
PM004010 APPROVED: Instrument Readiness Review - CD-4a L2 7/7/2010 10/20/2010 75
PM004020 PROJECT READY FOR CD-4a APPROVAL L3 7/7/2010 10/20/2010 75
PM004100 CD-4b START OF OPERATIONS APPROVED-CXI L1 09/30/11* 09/30/11* 0
PM004110 APPROVED: Instrument Readiness Review - CD-4b L2 2/23/2011 8/5/2011 117
PM004120 PROJECT READY FOR CD-4b APPROVAL L3 2/23/2011 8/5/2011 117
PM004200 CD-4c START OF OPERATIONS APPROVED-XPP/CXI/XCS L1 08/31/12* 08/31/12* 0
PM004210 APPROVED: Instrument Readiness Review - CD-4c L2 10/6/2011 7/6/2012 182
PM004220 PROJECT READY FOR CD-4c APPROVAL L3 10/6/2011 7/6/2012 182