85
Felix B. Fernandez [email protected] LUSI DOE Review August 20, 2008 PMCS Overview p. 1 LCLS Ultrafast Science Instruments LCLS Ultrafast Science Instruments (LUSI) (LUSI) Felix B. Fernandez – Project Controls August, 2008 Project Management Control System

LCLS Ultrafast Science Instruments (LUSI)

Embed Size (px)

DESCRIPTION

LCLS Ultrafast Science Instruments (LUSI). Project Management Control System. Felix B. Fernandez – Project Controls August, 2008. PMCS. Topics: System Overview PMCS Development Process PMCS Current Status Summary and Questions. PMCS Overview. The LUSI Project Management Control System: - PowerPoint PPT Presentation

Citation preview

Page 1: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 1

LCLS Ultrafast Science InstrumentsLCLS Ultrafast Science Instruments (LUSI)(LUSI)

Felix B. Fernandez – Project ControlsAugust, 2008

Project Management Control System

Page 2: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 2

PMCS

Topics:

System Overview

PMCS Development Process

PMCS Current Status

Summary and Questions

Page 3: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 3

PMCS Overview

The LUSI Project Management Control System:

Complies with DOE Order 413.3A

Complies with the 32 criteria from ANSI/EIA-748-A

Complies with the LUSI Project Execution Plan

Modeled after the LCLS Project PMCS

Page 4: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 4

PMCS Overview

Page 5: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 5

PMCS Overview

SLAC/LCLSPMCS

Procedures

ScheduleReports

ScheduleBaseline

SLACAccounting

System

AnalysisTool

“Hammer”

CostReports

Page 6: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 6

PMCS Overview

LUSI PMCS is defined and controlled by LCLS Procedures:

Earned Value Management System Description – LCLS 1.1-015

CA and WP Planning Procedure – LCLS 1.1-018

Change Control Procedure – LCLS 1.1-019

Project Schedule Procedure – LCLS 1.1-020

Cost Estimating Procedure – LCLS 1.1-021

Monthly Status and Reporting Procedure – LCLS 1.1-022

Subcontract Management Procedure – LCLS 1.1-023

Page 7: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 7

PMCS Overview

Using Primavera (P3) as the Scheduling tool

Have established a Project group with supporting project files maintained independently:

LUSI Project Group

Project Management (SLAC)

XPP Instrument (SLAC)

CXI Instrument (SLAC)

XCS Instrument (SLAC)

Diagnostics and Common Optics (SLAC)

Controls and Data Acquisition (SLAC)

XPP and XCS Detector Systems (BNL)

Page 8: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 8

PMCS Overview

Using Cobra as the Budgeting tool

Have created a Cobra project file for MIE funded effort.

The project also uses a web based tool called the “PMCS Hammer” that integrates Primavera, Cobra and Accounting data.

The “PMCS Hammer” is updated monthly following the month end cycle and provides team members a way of accessing/analyzing their data and writing their VARs.

Page 9: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 9

PMCS Overview

Page 10: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 10

PMCS Overview

Jeff Chan Craig Brackett Jay Doubrava Pat Dunn Hok Leung Cathy Lavelle

LCLSProject Office XConv Facilities X xControls XLinac X xXE X

Controls XXTOD X

Controls XUndulator XInstallation X xCommisioning XDatabase X x

LUSIProject Office XXPP XCXI X xXCS XDCO XControls XBNL XDatabase X x

Page 11: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 11

PMCS Development Process

Page 12: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 12

PMCS Development Process

Define Schedule and Budget assumptions

Finalize the WBS, WBS Dictionary

Finalize a Responsibility Assignment Matrix (RAM)

Finalize the Milestone Hierarchy and Dictionary

Finalize the set of SLAC/BNL Resources and Rates

Finalize the resource loaded Integrated Master Schedule

Use the Schedule baseline to create a Budget baseline

Establish a prelim Performance Measurement Baseline

Page 13: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 13

PMCS Development Process

Schedule AssumptionsWithin the funding limitations, get to an Early Science capability with the Instruments as early as possible.

Establish priority order of Instruments as XPP, CXI and XCS.

Establish multiple CD-4 milestones, one for each Instrument.

Components not required for Early Science operations can be installed for final CD-4 milestone.

Establish multiple CD-3 milestones to allow procurement of components for each Instrument as early as possible.

Establish a complete performance measurement baseline for all project equipment and conduct one CD-2.

Assume a Long Lead Authorization approval for Key critical components following CD-2 and prior to CD-3.

Page 14: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 14

PMCS Development Process

Budget Assumptions

Plan for an MIE funding profile of:

Plan for a Continuing Resolution for the first half of FY2009 (approx. $500k/month).

The balance of FY2009 funding will be available in the third quarter($12M).

Use Resources and Rates (Direct/Indirect) provided by SLAC and BNL.

Page 15: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 15

PMCS Development Process

Project WBS and WBS Dictionary

The Work Breakdown Structure has been placed under change control

PM-391-000-96

The WBS Dictionary has been updated to reflect the latest structure and has been placed under change control

PM-391-001-12

The Responsibility Assignment Matrix (RAM) has been developed that identifies Control Accounts and CA Managers

Page 16: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 16

Control Account Managers

T. Fornek - WBS 1.1 Project Management

J. Langton - WBS 1.2 XPP Instrument *

P. Montanez - WBS 1.3 CXI Instrument

E. Bong - WBS 1.4 XCS Instrument *

E. Ortiz - WBS 1.5 Diagnostics & Common Optics

G. Haller - WBS 1.6 Controls & Data Acquisition

Niels van Bakel - WBS 1.2.03 & 1.4.03 BNL Detectors

* Except for BNL Detector effort

PMCS Development Process

Page 17: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 17

PMCS Development Process

Project Milestone Hierarchy and Dictionary

The Milestone Hierarchy has been created and defines the

relationship between the levels of milestones.

Six levels of milestones have been identified

Level 1 & 2 - DOE

Level 3 – Project

Level 4 – Instruments/Systems

Level 5 – Interface / Handoff

Level 6 – Commitments / Awards

The Milestone Dictionary has been developed to assure a

thorough understanding of agreements

Page 18: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 18

PMCS Development Process

Several types of Level 5, Interface / Handoff Milestones have been defined and represent contractual agreements.

LUSI is currently monitoring 904 Interface Milestones

Page 19: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 19

PMCS Development Process

Page 20: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 20

PMCS Development Process

Level 6 milestones have been identified as the Awards of subcontracts / procurements and supports funding reconciliations efforts.

Planning when the budget is to be spent will support performance measurement.

LUSI is currently monitoring 224 Award Milestones.

Page 21: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 21

PMCS Development Process

Page 22: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 22

PMCS Development Process

Project Resources and Rates

Define a set of Resources for effort to be performed by SLAC

with the appropriate planning rates.

Define a set of Resources for effort to be performed by BNL with

the appropriate planning rates.

Use the appropriate indirect rates, as defined by SLAC/BNL, and

apply to the direct rates as defined.

Apply a consistent escalation to activities as they get scheduled.

The Bay Area uses a 4% escalation rate for labor

Used standard 2.3% escalation for non-labor

Page 23: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 23

Integrated Schedule Development Process

Use WBS as foundation to assure 100% of scope covered

Define the detailed tasks required to accomplish the scope

Define the required resources to accomplish the tasksBased on the detailed Basis of Estimates

Define the optimal logic relationships between tasks

Incorporate all levels of DOE and Project milestones

Incorporate all Interface / handoff milestones.

PMCS Development Process

Page 24: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 24

Integrated Schedule Development Process (cont.)

Validate links to confirm timephasing and float calculations are accurate and appropriate.

Where applicable, base activity durations on recent LCLS and/or related experience.

Define and use standard calendars throughout with all the appropriate non-work days.

Plan for a standard work week (8 hours/day & 5 days/week) except where appropriate.

Develop flexible and appropriate activity coding for reporting and summarizations

PMCS Development Process

Page 25: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 25

Integrated Schedule Development Process (cont.)Because the project recognizes the importance of managing schedule contingency like it manages money contingency, blocks of time will be built into the schedule to mitigate the inevitable schedule issues.

These reserves of time will be planned as activity relationship lags between the Project controlled Level 3 milestones and the DOE controlled Level 2 milestones.

These blocks of schedule contingency were used during the development of the detail schedules and were removed to set preliminary baseline dates. The blocks will be added back into the schedule to impose control over float utilization.

PMCS Development Process

Page 26: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 26

The project has reserved time between DOE level 2 milestones and DOE level 1 milestones to allow for DOE processing:

“Project Ready” + 40 days = DOE Review + 40 days = CD-3a

“Project Ready” + 60 days = DOE Review + 40 days = CD-4a

“Project Ready” + 40 days = DOE Review + 40 days = CD-3b

“Project Ready” + 60 days = DOE Review + 40 days = CD-4b

“Project Ready” + 40 days = DOE Review + 40 days = CD-3c

“Project Ready” + 60 days = DOE Review + 40 days = CD-4a

PMCS Development Process

Page 27: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 27

For the purposes of managing Total Float, time reserves will be set aside between project level 3 milestones and DOE level 2 milestones:

“Project Ready” + 40 days = DOE Review + 40 days = CD-3a

“Project Ready” + 60 days = DOE Review + 40 days = CD-4a

“Project Ready” + 40 days = DOE Review + 40 days = CD-3b

“Project Ready” + 60 days = DOE Review + 40 days = CD-4b

“Project Ready” + 40 days = DOE Review + 40 days = CD-3c

“Project Ready” + 60 days = DOE Review + 40 days = CD-4a

PMCS Development Process

Page 28: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 28

PMCS Development Process

Each one of the 3 Instruments will have 100 days of schedule contingency controlled by the project office.

Page 29: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 29

In addition to the WBS, project phase coding for each activity will facilitate the creation of summary schedules as well as define the budget work packages.

Management / Administration

Design / Engineering

Procurement

Subcontract

Fabrication / Assembly

Testing

Installation

PMCS Development Process

Page 30: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 30

Additional activity coding will facilitate sorting, filtering and additional summarizations

Work Breakdown StructureControl Account numberWork Package numberProject PhaseMilestone LevelControl Account Manager namePerformance Measurement TechniqueEarned Value Milestone (EVM) ID numberEVM WeightDesign MaturityJudgment Factor

PMCS Development Process

Page 31: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 31

Funding Reconciliation

The project started with a “bottom-up” planning approach which

required budget authority inconsistent with the levels that were

established.

Reconciliation required the identification of opportunities and the

prioritizations of effort to adjust for funding issues at the lowest

level.

The project next used a iterative “top-down” approach to shift

entire blocks of effort to optimize the schedule flow while

accelerating the Instrument availability.

PMCS Development Process

Page 32: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 32

Once the schedule was iterated and a reasonable

schedule was achieved that met the project objectives

and stayed within the available funding, the

preliminary schedule baseline was established.

With a baseline established in the Primavera file, the

next step was to import the schedule data into Cobra

to create the budget baseline and to establish a

preliminary performance measurement baseline

(PMB).

PMCS Development Process

Page 33: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 33

Control Account and Work Package planning is based entirely on the time-phasing as defined by the schedule.

Work packages are based on the project phase and represents the cost collection intersection with the SLAC accounting system.

The work package is the lowest level at which earned value is calculated.

PMCS Development Process

Page 34: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 34

The majority of the near term effort for the project will be focused on Engineering and Design.

Procurement, Subcontract, Fabrication & Assembly, Testing and Installation work packages are coded as Planning Packages.

The detail planning for work packages coded as planning packages will be reassessed at the appropriate time.

PMCS Development Process

Page 35: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 35

LUSI uses only a subset of the Performance Measurement Technique (PMT) codes used by Cobra to calculate Earned Value are coded into the

schedule as a reference

PMCS Development Process

Page 36: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 36

PMCS Status

Page 37: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 37

Critical Decision Requirements

• Employ an Earned Value Management System that is compliant with ANSI/EIA-748-A-1998 for projects with a Total Project Cost or Environmental Management Total Project Cost greater than or equal to $20M. Projects having a Total Project Cost or Environmental Management Total Project Cost between $20M and $50M must have an Earned Value Management System that is self-certified by the contractor as ANSI/EIA-748-A-1998 compliant. Projects having a Total Project Cost or Environmental Management Total Project Cost greater than or equal to $50M require an ANSI/EIA-748-A-1998 compliant system certified by the Office of Engineering and Construction Management. For projects not required to utilize an Earned Value Management System (e.g., firm fixed-price contract projects), an alternative performance management system must be described in the Project Execution Plan.• Completed – SLAC/LCLS Project was reviewed and successfully

demonstrated compliance at a review in June 2008• Subsequent to the June review a formal letter from DOE was received

confirming the compliance of the SLAC Earned Value Management System.

Page 38: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 38

Critical Decision Requirements

Page 39: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 39

• Perform a Performance Baseline Validation External Independent Review or a Performance Baseline Validation Independent Project Review. External Independent Reviews are conducted by the Office of Engineering and Construction Management to validate the Performance Baseline for projects with a Total Project Cost or Environmental Management Total Project Cost greater than or equal to $100M. Independent Project Reviews are conducted by the Project Management Support Office to validate the Performance Baseline for projects with a Total Project Cost or Environmental Management Total Project Cost less than $100 M.• The Independent Review is to be accomplished as part of the CD-2

review

Critical Decision Requirements

Page 40: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 40

EIR Lines of InquiryEIR ELEMENT COMMENT CD2

Ready

1. Work Breakdown Structure PM-391-000-96 (Structure)

2. Project Cost & Resource Loaded Schedule

Working baselines set as of month end March 2008 for both the schedule in P3 and the project cost in Cobra

3. Cost & Schedule Assumptions Covered in this presentation

4. Critical Path Critical paths for CD-4a, CD-4b and CD-4c available

5. Risk Management Mgmt presentation

6. Funding Profile Mgmt presentation

7. Project Controls/EVMS Overview and status covered in this presentation

8. Basis of Design Engineering presentation

9. Design Review Engineering presentation

10. System Functions & Reqs Engineering presentation

11. Sustainability Not applicable

12. Hazards Analysis PM-391-001-01

13. Value Management/Engineering LUSI Value Management Plan (Doc No. PM-391-000-02)

14. Start-up Test Plan SP-391-001-15, -16, -17 (XPP, CXI, XCS)

15. Project Execution Plan Draft ready for signature pending CD-2 review changes

16. Acquisition Strategy

17. Integrated Project Team This presentation & the PEP

Page 41: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 41

PMCS Status

Page 42: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 42

PMCS Status

Using Primavera (P3) as the Scheduling tool

Currently the statistics for the LUSI Project group with supporting project files are:

LUSI Project Group - 4131 activities & 6159 relationships

Project Management (SLAC) - 191 activities

XPP Instrument (SLAC) - 531 activities

CXI Instrument (SLAC) - 899 activities

XCS Instrument (SLAC) - 539 activities

Diagnostics and Common Optics (SLAC) - 599 activities

Controls and Data Acquisition (SLAC) - 1297 activities

XPP and XCS Detector Systems (BNL) - 75 activities

Page 43: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 43

LUSI Project Summary Schedule

=Level 1 & 2 DOE

=Level 3 Project Ready

XCS

FY12FY07

XPP

CXI

FY08 FY09 FY10 FY11

Ready for CD-4bApr 2011

Ready for CD-4cMar 2012

Ready for CD-4aJul 2010

Ready for CD-3cFeb 2010

Ready for CD-3bOct 2009

Ready for CD-3aFeb 2009

CD-2 ReviewAug 2008

CD-1 ApprovalSep 2007

Design Procure / Fab / Assy / Install (Components not part of CD-4a)

Procure / Fab / Assy / Install (Comp. not part of CD-4b)

Procure / Fab / Assy / InstallDesign

Design

Page 44: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 44

Schedule Critical Path(s)

Because each Instrument represents a separate major

deliverable, critical paths have been identified and are

being monitored to the Approve Start of Operations

milestones:

CD-4a for the XPP Instrument

CD-4b for the CXI Instrument

CD-4c for the XCS Instrument

As a general rule, critical paths/envelopes are

regularly monitored for all three instruments and the

two supporting systems.

LUSI Critical Paths/Envelopes

Page 45: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 45

XPP Schedule Critical Path

Driving Milestones

LL Approval,CD-3 & CD-4

Diffractometer Design Effort

Diffractometer Awards &

Vendor effort

Page 46: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 46

XPP Schedule Critical Path

Diffractometer deliveries to the

Installation effort

Page 47: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 47

CXI Schedule Critical Path

Driving Milestones

LL Approval,CD-3 & CD-4

KB Mirrors Reqmts/Design

Effort

KB Mirrors AWARD &

Vendor Design

Post Vendor Effort and Installation

Page 48: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 48

CXI Schedule Critical Path

Page 49: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 49

XCS Schedule Critical Path

Driving Milestones

LL Approval, CD-3, CD-4 & Funding M/S

Delayed Design Start due to

Funding

XCS Path moves to DCO

Procurements

XCS Instrument Installation effort

Page 50: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 50

XCS Schedule Critical Path

Procurement of DCO components delayed to FY11 due to funding

Design & initial procurement was completed for the XPP Instrument

Page 51: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 51

XCS Schedule Critical Path

Page 52: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 52

DCO Schedule Critical Envelope

DCO has one design effort and multiple procurements to support the Instrument reqmts. The project will

monitor strings of activities with the least float

Page 53: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 53

DCO Schedule Critical Envelope

Page 54: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 54

CDA Schedule Critical Envelope

CDA has multiple deliveries to the instruments and is

heavily driven by their needs. The project will

monitor strings of activities with the least float

Page 55: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 55

CDA Schedule Critical Envelope

Page 56: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 56

PMCS Status

Page 57: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 57

PMCS Status

Page 58: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 58

PMCS Status

Measurable Effort

Level of Effort

Page 59: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 59

PMCS Status

Labor

Non-Labor

Page 60: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 60

PMCS Status

Page 61: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 61

PMCS Hammer

Page 62: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 62

Statusing and Reporting

SLAC/LCLSPMCS

Procedures

ScheduleReports

ScheduleBaseline

SLACAccounting

System

AnalysisTool

“Hammer”

CostReports

Page 63: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 63

Statusing and Reporting

LUSI Project data is now stored on the LCLS website.

https://slacspace.slac.stanford.edu/sites/LCLS%20Document%20Storage/default.aspx

Toward the bottom there’s a PMCS section.

Page 64: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 64

Statusing and Reporting

PMCS data will be stored and available in the folders as described. The PMCS Hammer is an interactive tool team members will use to view, analyze data and write

VARs

Page 65: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 65

Statusing and Reporting

The PMCS Hammer is a utility that was customized for SLAC/LCLS that integrates Primavera, Cobra and Accounting data for any team member to use. The LCLS

Hammer and LUSI Hammer pages are access controlled and access is granted as appropriate.

Page 66: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 66

Statusing and Reporting

The Drilldown CPR and DCE will probably be the most often used utilities, but other information is available.

Page 67: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 67

Statusing and Reporting

The CPR Drilldown identifies areas that have broken a threshold that requires a VAR.

Page 68: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 68

Statusing and Reporting

By double-clicking on the highlight variance, the VAR form will be enabled.

Page 69: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 69

In Conclusion

The project set preliminary schedule and budget baselines as of March 2008.

The project team is ready for CD-2. We are ready to formally establish a performance measurement baseline and to proceed with the project.

Thank you for your participation

Page 70: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 70

PMCS Backup

Page 71: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 71

PMCS Status

Page 72: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 72

PMCS Status

Labor

Non-Labor

Page 73: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 73

PMCS Status

Page 74: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 74

PMCS Status

Labor-SLAC

Non-Labor-SLAC

Labor-BNL

Non-Labor-BNL

Page 75: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 75

PMCS Status

Page 76: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 76

PMCS Status

Labor

Non-Labor

Page 77: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 77

PMCS Status

Page 78: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 78

PMCS Status

Labor-SLAC

Non-Labor-SLAC

Labor-BNL

Non-Labor-BNL

Page 79: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 79

PMCS Status

Page 80: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 80

PMCS Status

Labor

Non-Labor

Page 81: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 81

PMCS Status

Page 82: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 82

PMCS Status

Labor

Non-Labor

Page 83: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 83

Milestones with PO ContingencyActivity ID Activity description MS Level

Early Finish

Late FinishTotal float

PM000000 CD-0 MISSION NEED APPROVAL L1 08/10/05A 08/10/05A

PM001000 CD-1 COST RANGE APPROVAL L1 09/27/07A 09/27/07A

PM002000 CD-2 PERFORMANCE BASELINE APPROVED L1 10/13/2008 3/2/2009 88

PM002100 COMPLETE CD-2 REQUIREMENTS - XPP / CXI / XCS L2 8/18/2008 1/5/2009 88

PM002150 PROJECT READY FOR CD-2 APPROVAL L3 7/28/2008 12/1/2008 88

PM002200 LONG LEAD PROCUREMENT APPROVED-Early Science L1 12/10/2008 4/27/2009 88

PM002210 LONG LEAD AWARD - XPP DIFFRACTOMETER L3 7/1/2009 7/21/2009 14

PM002220 LONG LEAD AWARD - CXI KB MIRROR SYSTEMS L3 7/6/2009 12/8/2009 109

PM003000 CD-3a CONSTRUCTION START APPROVED - XPP L1 5/28/2009 7/2/2009 25

PM003010 COMPLETE CD-3a REQUIREMENTS - XPP L2 4/2/2009 5/7/2009 25

PM003020 PROJECT READY FOR CD-3a APPROVAL - XPP L3 2/5/2009 3/12/2009 25

PM003030 CD-3b CONSTRUCTION START APPROVED - CXI L1 3/8/2010 4/1/2010 18

PM003040 COMPLETE CD-3b REQUIREMENTS - CXI L2 1/11/2010 2/4/2010 18

PM003050 PROJECT READY FOR CD-3b APPROVAL - CXI L3 10/29/2009 11/24/2009 18

PM003060 CD-3c CONSTRUCTION START APPROVED - XCS L1 6/9/2010 10/5/2010 84

PM003070 COMPLETE CD-3c REQUIREMENTS - XPP / CXI / XCS L2 4/14/2010 8/10/2010 84

PM003080 PROJECT READY FOR CD-3c APPROVAL - XCS L3 2/17/2010 6/15/2010 84

PM004000 CD-4a START OF OPERATIONS APPROVED XPP L1 12/17/10* 12/17/10* 0

PM004010 APPROVED: Instrument Readiness Review - CD-4a L2 9/30/2010 10/20/2010 14

PM004020 PROJECT READY FOR CD-4a APPROVAL L3 7/8/2010 7/28/2010 14

PM004100 CD-4b START OF OPERATIONS APPROVED-CXI L1 09/30/11* 09/30/11* 0

PM004110 APPROVED: Instrument Readiness Review - CD-4b L2 7/12/2011 8/5/2011 18

PM004120 PROJECT READY FOR CD-4b APPROVAL L3 4/19/2011 5/13/2011 18

PM004200 CD-4c START OF OPERATIONS APPROVED-XPP/CXI/XCS L1 08/31/12* 08/31/12* 0

PM004210 APPROVED: Instrument Readiness Review - CD-4c L2 6/8/2012 7/6/2012 20

PM004220 PROJECT READY FOR CD-4c APPROVAL L3 3/16/2012 4/13/2012 20

Page 84: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 84

Milestones without PO ContingencyActivity ID Activity description MS Level

Early Finish

Late FinishTotal float

PM000000 CD-0 MISSION NEED APPROVAL L1 08/10/05A 08/10/05A

PM001000 CD-1 COST RANGE APPROVAL L1 09/27/07A 09/27/07A

PM002000 CD-2 PERFORMANCE BASELINE APPROVED L1 10/13/2008 7/17/2009 187

PM002100 COMPLETE CD-2 REQUIREMENTS - XPP / CXI / XCS L2 8/18/2008 5/22/2009 187

PM002150 PROJECT READY FOR CD-2 APPROVAL L3 7/28/2008 5/1/2009 187

PM002200 LONG LEAD PROCUREMENT APPROVED-Early Science L1 12/10/2008 9/11/2009 187

PM002210 LONG LEAD AWARD - XPP DIFFRACTOMETER L3 6/23/2009 10/6/2009 75

PM002220 LONG LEAD AWARD - CXI KB MIRROR SYSTEMS L3 7/6/2009 3/16/2010 169

PM003000 CD-3a CONSTRUCTION START APPROVED - XPP L1 4/2/2009 9/24/2009 125

PM003010 COMPLETE CD-3a REQUIREMENTS - XPP L2 2/5/2009 7/30/2009 125

PM003020 PROJECT READY FOR CD-3a APPROVAL - XPP L3 2/5/2009 7/30/2009 125

PM003030 CD-3b CONSTRUCTION START APPROVED - CXI L1 1/11/2010 6/24/2010 118

PM003040 COMPLETE CD-3b REQUIREMENTS - CXI L2 10/29/2009 4/29/2010 118

PM003050 PROJECT READY FOR CD-3b APPROVAL - CXI L3 10/29/2009 4/29/2010 118

PM003060 CD-3c CONSTRUCTION START APPROVED - XCS L1 4/14/2010 1/13/2011 184

PM003070 COMPLETE CD-3c REQUIREMENTS - XPP / CXI / XCS L2 2/17/2010 11/2/2010 184

PM003080 PROJECT READY FOR CD-3c APPROVAL - XCS L3 2/17/2010 11/2/2010 184

PM004000 CD-4a START OF OPERATIONS APPROVED XPP L1 12/17/10* 12/17/10* 0

PM004010 APPROVED: Instrument Readiness Review - CD-4a L2 7/7/2010 10/20/2010 75

PM004020 PROJECT READY FOR CD-4a APPROVAL L3 7/7/2010 10/20/2010 75

PM004100 CD-4b START OF OPERATIONS APPROVED-CXI L1 09/30/11* 09/30/11* 0

PM004110 APPROVED: Instrument Readiness Review - CD-4b L2 3/25/2011 8/5/2011 95

PM004120 PROJECT READY FOR CD-4b APPROVAL L3 3/25/2011 8/5/2011 95

PM004200 CD-4c START OF OPERATIONS APPROVED-XPP/CXI/XCS L1 08/31/12* 08/31/12* 0

PM004210 APPROVED: Instrument Readiness Review - CD-4c L2 3/16/2012 7/6/2012 80

PM004220 PROJECT READY FOR CD-4c APPROVAL L3 3/16/2012 7/6/2012 80

Page 85: LCLS Ultrafast Science Instruments (LUSI)

Felix B. [email protected]

LUSI DOE Review August 20, 2008PMCS Overview p. 85

Milestones with no Funding LimitsActivity ID Activity description MS Level

Early Finish

Late FinishTotal float

PM000000 CD-0 MISSION NEED APPROVAL L1 08/10/05A 08/10/05A

PM001000 CD-1 COST RANGE APPROVAL L1 09/27/07A 09/27/07A

PM002000 CD-2 PERFORMANCE BASELINE APPROVED L1 10/13/2008 7/17/2009 187

PM002100 COMPLETE CD-2 REQUIREMENTS - XPP / CXI / XCS L2 8/18/2008 5/22/2009 187

PM002150 PROJECT READY FOR CD-2 APPROVAL L3 7/28/2008 5/1/2009 187

PM002200 LONG LEAD PROCUREMENT APPROVED-Early Science L1 12/10/2008 9/11/2009 187

PM002210 LONG LEAD AWARD - XPP DIFFRACTOMETER L3 6/23/2009 10/6/2009 75

PM002220 LONG LEAD AWARD - CXI KB MIRROR SYSTEMS L3 4/2/2009 3/16/2010 236

PM003000 CD-3a CONSTRUCTION START APPROVED - XPP L1 4/2/2009 9/24/2009 125

PM003010 COMPLETE CD-3a REQUIREMENTS - XPP L2 2/5/2009 7/30/2009 125

PM003020 PROJECT READY FOR CD-3a APPROVAL - XPP L3 2/5/2009 7/30/2009 125

PM003030 CD-3b CONSTRUCTION START APPROVED - CXI L1 1/11/2010 6/24/2010 118

PM003040 COMPLETE CD-3b REQUIREMENTS - CXI L2 10/29/2009 4/29/2010 118

PM003050 PROJECT READY FOR CD-3b APPROVAL - CXI L3 10/29/2009 4/29/2010 118

PM003060 CD-3c CONSTRUCTION START APPROVED - XCS L1 1/11/2010 1/13/2011 251

PM003070 COMPLETE CD-3c REQUIREMENTS - XPP / CXI / XCS L2 10/29/2009 11/2/2010 251

PM003080 PROJECT READY FOR CD-3c APPROVAL - XCS L3 10/29/2009 11/2/2010 251

PM004000 CD-4a START OF OPERATIONS APPROVED XPP L1 12/17/10* 12/17/10* 0

PM004010 APPROVED: Instrument Readiness Review - CD-4a L2 7/7/2010 10/20/2010 75

PM004020 PROJECT READY FOR CD-4a APPROVAL L3 7/7/2010 10/20/2010 75

PM004100 CD-4b START OF OPERATIONS APPROVED-CXI L1 09/30/11* 09/30/11* 0

PM004110 APPROVED: Instrument Readiness Review - CD-4b L2 2/23/2011 8/5/2011 117

PM004120 PROJECT READY FOR CD-4b APPROVAL L3 2/23/2011 8/5/2011 117

PM004200 CD-4c START OF OPERATIONS APPROVED-XPP/CXI/XCS L1 08/31/12* 08/31/12* 0

PM004210 APPROVED: Instrument Readiness Review - CD-4c L2 10/6/2011 7/6/2012 182

PM004220 PROJECT READY FOR CD-4c APPROVAL L3 10/6/2011 7/6/2012 182