GEOTHERMAL POWER PLANT DEVELOPMENT IN INDONESIA Presented at: “Forum for East Asia-Latin America Cooperation” November 13 th , 2012 Tokyo, Japan DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION MINISTRY OF ENERGY AND MINERAL RESOURCES by: Jarman Directorate General of New, Renewable Energy and Energy Conservation

DIRECTORATE GENERAL OF NEW RENEWABLE …energy-indonesia.com/03dge/FEALAC JAPAN, Presentation.pdf · Direktorat Jenderal EBTKE Direktorat Jenderal Energi Baru, Terbarukan dan Konservasi

  • View
    214

  • Download
    0

Embed Size (px)

Text of DIRECTORATE GENERAL OF NEW RENEWABLE …energy-indonesia.com/03dge/FEALAC JAPAN,...

  • GEOTHERMAL POWER PLANT DEVELOPMENT IN INDONESIA

    Presented at:

    Forum for East Asia-Latin America Cooperation

    November 13th, 2012

    Tokyo, Japan

    DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION

    MINISTRY OF ENERGY AND MINERAL RESOURCES

    by:

    Jarman Directorate General of New, Renewable Energy and Energy Conservation

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    I. Background

    II. Geothermal Policy

    III. Geothermal Program

    IV. Geothermal Development

    V. Investment Opportunities

    OUTLINE

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    I. Background

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    BACKGROUND

    Geothermal is a thermal energy that naturally formed beneath the earth's surface;

    Geothermal energy is a green energy because it produces lower green house gasses (GHG) than fossil fuel. In addition, when managed properly, geothermal is also consider as a renewable energy;

    Geothermal energy is site specific, can not be stored, and also can not be transported;

    Implementation of geothermal activity in line with the mandate of the Law 1945;

    Geothermal utilization are in forms of direct and indirect use;

    Authority for geothermal management distributed to Minister, The Governor, and/or Regent/Mayor in accordance with their authority.

    Constraints and Barriers:

    Pricing Electricity price from geothermal energy still considers has not reached its economical value;

    Land-use Issues Geological Agency has been identified that more than 70% of geothermal areas are partially or completely overlapping with forestry areas (conservation forest, protected forest and production forest)

  • Direktorat Jenderal

    EBTKE Direktorat Jenderal Energi Baru, Terbarukan dan Konservasi Energi

    Kementerian Energi dan Sumber Daya Mineral

    2011

    Oil 20 %

    Gas 30 %

    Coal 33 %

    NRE 17 %

    Oil 23,7 %

    Gas 19,7 %

    Coal 30,7 %

    NRE 25,9 %

    Gov. Reg.

    NO. 5/2006

    NEP Draft

    By NEC

    Note:

    NRE = New and Renewable Energy

    NEP = National Energy Policy

    NEC = National Energy Council

    Oil 49,7 %

    Gas 20,1 %

    Coal 24,5 %

    NRE 5,7 %

    2025

    CURRENT ENERGY CONDITION

    BACKGROUND

    1. Electrification ratio in 2011 is 72,95%;

    2. Energy consumption growth is 7% per year,

    which not balance with energy suppy;

    3. The dependence on fossil energy is high,

    but the energy reserve is limited;

    4. Fossil subsidy is increasing;

    5. The utilization of renewable energy and

    implementation of energy conservation

    has not been optimized;

    6. Link with environmental issue:

    a. Climate change mitigation;

    b. Clean energy initiative:

    National commitment to reduce emission

    by 26% in 2020;

    7. Funding for energy development is limited

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    Source : Geological Survey, MEMR(2011)

    Already Developed

    Ready to Developad

    Detail Survey

    Preliminary Survey

    Note:

    RESOURCES (MWe)

    % RESERVE (MWe)

    %

    Speculative Hypothetical

    45.17%

    Possible Probable Proven

    54.83% 8.231 4.964 12.909 823 2.288

    13.195 16.020

    29.215

    GEOTHERMAL POTENTIAL

    BACKGROUND

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    II. Geothermal Policy

  • Direktorat Jenderal

    EBTKE Direktorat Jenderal Energi Baru, Terbarukan dan Konservasi Energi

    Kementerian Energi dan Sumber Daya Mineral

    Policy Directions:

    The paradigm of national energy management is shifting from Supply Side Management to demand side management Management;

    Supply Side Management on fossil focused energy sources;

    Demand Side Management focused on optimizing energy efficiency and new renewable energy sources;

    The Law No. 30/2007 on Electricity, emphasis on diversification and energy conservation.

    Opportunities:

    Environmental issues and sustainable development;

    A paradigmatic shifting in the management of the national energy;

    Indonesia has huge of renewable energy potential;

    High potential for energy savings.

    GEOTHERMAL POLICY

  • Direktorat Jenderal

    EBTKE Direktorat Jenderal Energi Baru, Terbarukan dan Konservasi Energi

    Kementerian Energi dan Sumber Daya Mineral

    9

    GEOTHERMAL POLICY

    1. Revision of Law 27/2003 on Geothermal:

    GoI is revising the law 27/2003 on Geothermal, law 5/1990 on Conservation of Natural Resources, and law 41/1999 on Forestry.

    2. MoU Between MEMR Minister of Forestry

    MEMR and Minister of Forestry have signed MoU regarding the acceleration of geothermal utilization permit within production forest, protected forest, and conservation forest .

    3. Feed-in Tariff:

    Feed-in Tariff is a Government policy to set the price of electricity from geothermal power plant which is final and can not be negotiated by PT. PLN

    4. Funding incentives : Government guarantee on the feasibility of PT. PLN; Geothermal Fund" for geothermal exploration; Green Banking Program.

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    III.Geothermal Program

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    Development 2010 2011 2012 2013 2014 2015

    Geothermal Development

    1. Added Capacity (MW) 37 115 3 375 1.797

    2. Installed Capacity (MW) 1.189 1.226 1.341 1.344 1.719 3.516

    GEOTHERMAL PROGRAM POWER PLANT DEVELOPMENT 2010 2015

    Note:

    - Capacity Factor of Geothermal Power Plant = 90%

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    No Geothermal Working Area (GWA) Location Potential Capacity

    (MW)

    1 Gn. Talang West Sumatera 36

    2 Songa Wayaua North Maluku 140

    3 Danau Ranau Lampung & South

    Sumatera 210

    4 Mataloko East Nusa Tenggara 63

    5 Gn. Endut Banten 80

    6 Way Ratai Lampung 105

    7 Candi Umbul Telomoyo Central Java 72

    8 Simbolon Samosir North Sumatera 155

    9 Bora Pulu Central Sulawesi 123

    10 Gn. Lawu Central Java 195

    GEOTHERMAL WORKING AREA FOR TENDER

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    PRELIMINARY SURVEY ASSIGNMENTS AREA 2012

    No Geothermal Working Area (GWA) District/ City Province

    1 Gn. Hamiding West Halmahera, North Halmahera North Maluku

    2 Pentadio Gorontalo, Bone Bolango, Gorontalo

    City' Gorontalo

    3 Graho Nyabu Merangin, Kerinci, Muko-Muko Jambi and Bengkulu

    4 Gn. Wilis Ponorogo, Madiun, Nganjuk, Kediri,

    Tulungagung, Trenggalek East Java

    5 Gn. Geureudong Central Aceh, Bener Meriah, North

    Aceh Nanggroe Aceh Darussalam

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    IV.Geothermal Development

  • 2012

    Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    15

    ACEH 2 WKP

    Jaboi: 70 MW

    Seulawah Agam: 130 MW

    NORTH SUMATERA 5 WKP

    Sibayak Sinabung: 130 MW

    Sibual Buali: 750 MW

    Sipaholon Ria-ria: 75 MW

    Sorik Marapi: 200 MW

    Simbolon Samosir : 155 MW

    JAMBI 1 WKP

    Sungai Penuh: 70 MW

    SOUTH SUMATERA 3 WKP

    Lumut Balai: 250 MW

    Rantau Dedap: 106 MW

    Danau Ranau: 210 MW

    BANTEN 2 WKP

    Kaldera Danau Banten: 115 MW

    G. Endut: 80 MW

    WEST SUMATERA 4 WKP

    Bukit Kili: 83 MW

    Gn Talang: 35 MW

    Liki Pinangawan: 400 MW

    Bonjol: 200 MW

    BENGKULU 2 WKP

    Tmbg Sawah-Hululais: 873 MW

    Kepahiang: 180 MW

    LAMPUNG 4 WKP

    Gn.Rajabasa: 91 MW

    Suoh Sekincau: 230 MW

    Waypanas Ulubelu: 556 MW

    Danau Ranau: 210 MW

    Way Ratai :105 MW

    WEST JAVA 10 WKP

    Ciater - Tgkban Perahu: 60 MW

    CibeureumParabakti: 485 MW

    Cibuni: 140 MW

    Cisolok Cisukarame: 45 MW

    Gn. Tampomas: 50 MW

    Gn. Tgkuban Perahu: 100 MW

    Kamojang-Darajat: 1465 MW

    Karaha Cakrabuana: 725 MW

    Pangalengan: 1106 MW

    G. Ciremai: 150 MW

    CENTRAL JAVA 5 WKP

    Baturaden: 175 MW

    Dataran Tinggi Dieng: 780 MW

    Guci: 79 MW

    Gn. Ungaran: 100 MW

    Umbul Telomoyo : 120 MW

    EAST JAVA 3 WKP

    Blawan Ijen: 270 MW

    Gn. Iyang Argopuro: 295 MW

    Telaga Ngebel: 120 MW

    Gn. Lawu: 195 MW

    BALI 1 WKP

    Tabanan: 276 MW

    WEST NUSA

    TENGGARA 2 WKP

    Hu'u Daha: 65 MW

    Sembalun: 100 MW

    EAST NUSA TENGGARA 5 WKP

    Atadei: 40 MW

    Sokoria: 30 MW

    Ulumbu: 199 MW

    Mataloko: 63 MW

    Oka Ile Ange: 40 MW

    MALUKU 1 WKP

    Tulehu: 100 MW

    NORTH MALUKU 2 WKP

    Jailolo: 75 MW

    Songa Wayaua: 140 MW

    NORTH SULAWESI 2 WKP

    Kotamobagu: 410 MW

    Lahendong-Tompaso: 358 MW

    GORONTALO 1 WKP

    Suwawa: 110 MW

    CENTRAL SULAWESI 2 WKP

    Marana: 35 MW

    Bora Pulu : 152 MW

    Total : 58 GWA

    Distribution of GWA

    GEOTHERMAL DEVELOPMENT

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    Presidential Regulation No. 04/2010 on Assignment to PT. PLN to Accelerate Power Plant Development Using Renewable Energy, Coal and Gas

    MEMR Regulation No. 01/2012 as revised in Ministerial Regulation No. 15/2010 on Projects List of Power Plant Accelerated Development using Renewable Energy, Coal and Gas as well as Related Transmission

    Target for Geothermal Power Plant Development on Crash Program 10.000 MW Phase II

    Existing field (on Production Phase) : 465 MW

    Existing field (not on Production Phase) : 1535 MW

    New Geothermal Working Area : 2925 MW

    Total of Geothermal Development 4925 MW

    GEOTHERMAL DEVELOPMENT TARGET

    (2010 - 2014)

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    V. Investment Opportunities

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    The development of 4,925 MW electricity from Geothermal in Second Phase Crash Program 10,000 MW up to the year 2014 requires more than US$ 14,000 millions for the investment.

    The development plan of 12,000 MW Geothermal Power Plant up to the year 2025, international supports are needed.

    Foreign ownership in Geothermal Business is allowed up to 95 %;

    Access to Potential Geothermal Resources for Investors: - Preliminary Survey Assignment - Participate in the geothermal business through GWAs tendering mechanism

    Other business opportunities in geothermal sector: Geothermal direct use;

    Low temperature geothermal potential;

    Small scale power plant;

    CER under CDM Scheme;

    Services company to support the core business of geothermal.

    INVESTMENT OPPORTUNITIES

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    Go Green Indonesia ! green energy, future energy

    Jalan Jenderal Gatot Subroto, Kav. 49 Jakarta 12950; Telp: 021-52904235; 5250575; Faks: 021-25529106; 25529212

    Email: [email protected] ; [email protected]

    MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA

    DIRECTORATE GENERAL OF NEW, RENEWABLE ENERGY, AND ENERGY CONSERVATION

    Thank You

    www.ebtke.esdm.go.id

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    No. Geothermal Working

    Area/ Location License Holder Developer Power Plant

    Installed

    Capacity

    (MW)

    1 Sibayak Sinabung,

    NORTH SUMATERA

    PT. Pertamina Geothermal

    Energy (PGE)

    PT. Pertamina Geothermal

    Energy (PGE) Sibayak 12

    2 Cibeureum Parabakti,

    WEST JAVA

    PT. Pertamina Geothermal

    Energy (PGE)

    KOB - Chevron Geothermal

    Salak, Ltd (CGS) Salak 377

    3 Pangalengan,

    WEST JAVA

    PT. Pertamina Geothermal

    Energy (PGE)

    KOB - Star Energy

    Geothermal Wayang

    Windu, Ltd (SEGWWL)

    Wayang

    Windu 227

    4 Kamojang Darajat,

    WEST JAVA

    PT. Pertamina Geothermal

    Energy (PGE)

    PT. Pertamina Geothermal

    Energy (PGE) Kamojang 200

    5 Kamojang Darajat,

    WEST JAVA

    PT. Pertamina Geothermal

    Energy (PGE)

    KOB - Chevron Geothermal

    Indonesia, Ltd (CGI) Darajat 270

    6 Dataran Tinggi Dieng,

    CENTRAL JAVA

    PT. Pertamina Geothermal

    Energy (PGE) PT. Geo Dipa Energi (GDE) Dieng 60

    7 Lahendong Tompaso,

    NORTH SULAWESI

    PT. Pertamina Geothermal

    Energy (PGE)

    PT. Pertamina Geothermal

    Energy (PGE) Lahendong 80

    8 Ulubelu,

    LAMPUNG

    PT. Pertamina Geothermal

    Energy (PGE)

    PT. Pertamina Geothermal

    Energy (PGE) Ulubelu 55

    1.281 20

    INSTALLED GEOTHERMAL POWER PLANT CAPACITY 2012

  • 2012

    Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    MEMR

    Prov.

    Govmt.

    Corporation

    PLN

    WKP

    Determination Pre-Survey WKP

    Tendering

    IUP

    Issuance

    Electricity

    Price

    Rep

    ort o

    f

    Ten

    derin

    g

    Pro

    cess

    Geo

    therm

    al

    Po

    tential

    Potential

    Map Survey

    APBN

    Survey

    APBD

    Prov.

    Other

    Parties

    Assignment

    Evaluation WKP Report WKP-N

    WKP-P

    WKP-K

    (S3-N)

    (S3-P)

    (S3-K)

    IUP-N

    IUP-P

    IUP-K

    (S4-N)

    (S4-P)

    (S4-K)

    Tender Winner

    GEOTHERMAL VALUE CHAIN

    (S-1) (S-2) (S-3) (S-4) (S-5)

    PPA

    (S-6)

    Assignment

    Exp

    loratio

    n

    (S-7)

    Exp

    lora

    tio

    n

    (Current Regulations)

    (S-0)

    BUSINESS STADIUM (S-X)

    Survey

    APBD

    Kab./

    Kota

    Local

    Govmt.

    (Regent/

    City)

    DJEBTKE KESDM 2012

    Units

    Potential/

    Stadium Explo

    itation

    FS Production/

    Utilization

    (S-8) (S-9) (S-10)

    FS

    Exp

    loit

    atio

    n

    Pro

    du

    ctio

    n/

    Uti

    lizat

    ion

    Tender Winner

    Tender Winner

    Report

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    Road Map of Geothermal Development 2006 2025

    Current Condition

    2006

    852 MW

    (Produksi)

    2008 2012 2016 2020

    2000 MW 3442 MW 4600 MW 6000 MW 9500 MW

    (Target)

    1148 MW

    Existing WKP

    1442 MW

    Existing WKP

    1158 MW

    Existing WKP

    + New WKP

    1400 MW

    New WKP

    3500 MW

    New WKP

    2025

    1.281 MW

    (based on Presidential Decree No. 5/2006 on National Energy Policy)

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    GEOTHERMAL POWER PLANT PROJECTS INCLUDED IN CRASH PROGRAM PHASE II (Based on MEMR Regulaton No. 01/2012)

    NO.GEOTHERMAL POWER

    PLANT PROJECTSTATUS PROVINCE

    ESTIMATION

    OF CAPACITY

    (MW)

    1 Sungai Penuh Existing WKP Jambi 2x55

    2 Hululais Existing WKP Bengkulu 2x55

    3 Kotamobagu 1 and 2 Existing WKP North Sulawesi 2x20

    4 Kotamobagu 3 and 4 Existing WKP North Sulawesi 2x20

    5 Sembalun Open Area West Nusa Tenggara 2x10

    6 Tulehu Existing WKP Maluku 2x10

    7 Tangkuban Perahu I New WKP West Java 2x55

    8 Kamojang 5 and 6 Existing WKP West Java 1 x30 1 x60

    9 Ijen New WKP East Java 2x55

    10 Iyang Argopuro Existing WKP East Java 1 x55

    11 Ngebel New WKP East Java 3x55

    12 Gunung Endut New WKP Banten 1 x55

    13 Rawa Dano New WKP Banten 1 x 110

    14 Cibuni Existing WKP West Java 1 x 10

    15 Cisolok-Cisukarame New WKP West Java 1 x50

    16 Karaha Bodas Existing WKP West Java 1 x30 2x55

    17 Patuha Existing WKP West Java 3x60

    18 Tampomas New WKP West Java 1 x45

    19 Tangkuban Perahu II Existing WKP West Java 2x30

    20 Wayang Windu Unit 3 and 4 Existing WKP West Java 2x 110

    21 Gunung Ciremai New WKP West Java 2 x 55

    22 Baturaden New WKP Central Java 2x 110

    23 Dieng Existing WKP Central Java 1 x55 1 x60

    24 Guci New WKP Central Java 1 x55

    25 Ungaran New WKP Central Java 1 x55

    26 Seulawah Agam New WKP Aceh 1X55

    NO.GEOTHERMAL POWER

    PLANT PROJECTSTATUS PROVINCE

    ESTIMATION

    OF CAPACITY

    (MW)

    27 Jaboi New WKP Aceh 2x5

    28 Sarulla 1 Existing WKP North Sumatera 3x 110

    29 Sarulla 2 Existing WKP North Sumatera 2x55

    30 Umbul Telumoyo New WKP Central Java 1 x55

    31 Simbolon Samosir Open Area North Sumatera 2x55

    32 Sipoholon Ria-Ria New WKP North Sumatera 1 x55

    33 Sorik Marapi New WKP North Sumatera 240 (Total)

    34 Muaralaboh New WKP West Sumatera 2x 110

    35 Bonjol New WKP West Sumatera 3x55

    36 Lumut Balai Existing WKP South Sumatera 4x55

    37 Rantau Dadap New WKP South Sumatera 2x110

    38 Rajabasa New WKP Lampung 2x110

    39 Ulubelu 3 and 4 Existing WKP Lampung 2x55

    40 Suoh Sekincau New WKP Lampung 4x55

    41 Wai Ratai Open Area Lampung 1 x55

    42 Danau Ranau New WKP Lampung 2x55

    43 Lahendong 5 dan 6 Existing WKP North Sulawesi 2x20

    44 Bora Open Area Central Sulawesi 1 x5

    45 Marana/Masaingi New WKP Central Sulawesi 2x10

    46 Hu'u New WKP West Nusa Tenggara 2x10

    47 Atadei New WKP East Nusa Tenggara 2 x2,5

    48 Sokoria New WKP East Nusa Tenggara 3x5

    49 Mataloko New WKP East Nusa Tenggara 1 x5

    50 Jailolo New WKP North Maluku 2x5

    51 Songa Wayaua New WKP North Maluku 1 x5

    TOTAL PLANNED INSTALLED CAPACITY 4925

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    President Decree No 45/1991, No 49/1991, and No 23/1992

    Business structure based on JOC and ESC 34% of Net Operating Income (NOI), that had included all kinds of taxes and retribution, except personal tax. Project Management : Under Pertamina (JOC) and PLN (ESC) Project Type:

    Total (Integrated) Project Partial Project

    Law No. 27/2003

    Business structure in the form of Permit: Geothermal Mining Permit Enterprise Permit for Electricity

    Obligation to pay for taxes and royalty Project Management : Under Permit Holder Project Type: Total (Integrated) Project GWA holder will be granted as generally plan

    operation

    Implementation of Geothermal Policies

    Existing GWA New GWA

    24

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    1. Law No. 27/2003 on Geothermal

    2. Government Regulation (GR) No. 59/2007 on Geothermal Business Activities, as amanded in GR No. 70/2010

    3. GR No. 62/2008 jo. GR No. 1/2007 on Income Tax Facilities for Investment in Certain Business Areas and / or in Specific Regions

    4. GR No. 9/2012 on Types And Tariffs On Non-tax State Revenue Applicable to The Ministry Of Energy And Mineral Resources

    5. Presidential Regulation No. 04/2010 on Assignment to PT. PLN (Persero) to Accelerate The Development of Power Plant from Renewable Energy, Coal and Gas

    6. Ministry Regulation (MR) of Minister Energy And Mineral Resources

    1) MR No. 11/2008 on the Procedure for Determination Geothermal Working Area

    2) MR No. 02/2009 on Guidelines for Geothermal Preliminary Survey Assignment (as amendment of MR. 05/2007)

    3) MR No. 11/2009 on Guidelines for Implementation of Geothermal Business , jo. MR No. 18/2012

    GEOTHERMAL REGULATION

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    4) MR No. 01/2012 on Revision of MR No. 15/2010 on The List of Power Plant Acceleration Projects Using Renewable Energy, Coal, and Gas and Related Transmission

    5) MR No. 22/2012 on Assignment to PT PLN (Persero) to Purchase Electricity from Geothermal Power Plant and Geothermal Power Purchase Benchmark Price by PT PLN (Persero)

    7. Ministry Regulation of Minister of Finance

    1) No. 139/PMK.011/2011 on Procedures for Granting Business-Feasibility Guarantee to PT PLN (Persero) for The Development or Renewable Energy, Coal and Gas-Fueled Power Plants Through Cooperation With The Independent Power Producers

    2) No. 03/PMK.011/2012 on Procedures for the Management and Accountability Geothermal Facility Fund

    ..Continue

  • Direktorat Jenderal

    EBTKE Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    No Area

    Price (cent US$/kWh)

    High Voltage

    Medium Voltage

    1 Sumatera 10 11,5

    2 Java, Madura and Bali 11 12,5

    3 South Sulawesi, West Sulawesi, and

    Southeast Sulawesi

    12 13,5

    4 North Sulawesi, Central Sulawesi, and

    Gorontalo

    13 14,5

    5 West Nusa Tenggara, and East Nusa

    Tenggara

    15 16,5

    6 Maluku and Papua 17 18,5

    GEOTHERMAL FEED-IN TARIFF

  • 2012

    Ministry of Energy and Mineral Resources

    Directorate General of New Renewable Energy and Energy Conservation

    The Feed-in Tariffs mechanism will be applied to :

    a. geothermal license holders (IUP holder) after the issuance of Minister Regulation No. 22/2012;

    b. mining right holders, license holder or concession holder that existed before the enactment of Law No. 27 Year 2003 on Geothermal who already have Power Purchase Agreement (PPA), which will increase power plant capacity on the existing agreement (PPA);

    c. mining right holders, license holder or concession holder that existed before the enactment of Law No. 27 Year 2003 on Geothermal who will extend their expired PPA;

    d. mining right holders, license holder or concession holder that existed before the enactment of Law No. 27 Year 2003 on Geothermal who already have PPA, for both who have produced or not yet produced electricity or steam, as long as all parties involved agree upon the amendment on sales price of electricity or steam; or

    e. IUP holder who will undertake PPA, as long as agreed by the parties involved and allowed by PPA to be agreed by the parties.

    Feed in Tariff Mechanism