63
Port Macquarie-Hastings Council ONE YEAR OPERATIONAL PLAN 2016 17

2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

Port Macquarie-Hastings Council

ONE YEAR OPERAtiONAl PlAN

2016

17

Page 2: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

Inside Cover Intentionally Left Blank

Page 3: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

CO

NtE

NtS

ONE YEAR OPERAtiONAl PlAN 2016–2017

Message from the General Manager .................................... 4Organisational structure ..................................................... 5Councillor profiles .............................................................. 6Funding the operational plan ............................................... 7Budget snapshot ............................................................ 8-9Budget statement ............................................................ 10Capital works program ................................................ 11-20Funding the capital works program .................................... 21Key projects map ............................................................. 22Parks and Recreation projects map ................................... 23How to read this document .......................................... 24-25

Guiding principle – Ensuring good governance........................ 26Focus area – Looking after our people................................... 33Focus area – Helping our community prosper ......................... 40Focus area – Looking after our environment .......................... 45Focus area – Planning and providing our infrastructure ........... 51

AppendixAttachment 1 – Fees and charges Attachment 2 – Revenue policyAttachment 3 – Rating maps

3

Page 4: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

I am pleased to be able to present the 2016–2017 Operational Plan, which represents the fourth Operational Plan for this current term of Council.

In October 2015, as part of the NSW Government’s local government reform program titled ‘Fit for the Future’, Port Macquarie-Hastings Council was deemed to be a ‘Fit’ council. This means that Council has

not been flagged to merge with any other council and has been deemed financially fit following the development of an action plan that demonstrates how Council will work towards meeting the various financial benchmarks set down by the government over the coming years.

Being deemed a ‘Fit’ council is testament to the work Councillors and Council staff have been undertaking over the past several years. It means that we will be able to continue to focus on delivering improved outcomes for our community by being solutions-focused and by ensuring the organisation has a culture of continuous improvement so that services are delivered in the most efficient and effective way possible.

As we continue to work towards bringing Council closer to the community, we take every opportunity possible to engage with our

A MESSAgE fROMtHE gENERAl MANAgER

community on a regular basis. We take much of our direction from these valuable opportunities to connect with the people who help make our area such a vibrant place to live, learn, work, play and invest.

This financial year will see us continue to deliver some major infrastructure such as the continued construction of Stingray Creek Bridge at North Haven; a major upgrade of Houston Mitchell Drive at Lake Cathie; the construction of an amenities block at Port Macquarie Town Beach North; completion of the expansion of the Port Macquarie Indoor Stadium; resealing of local roads in Wauchope; the replacement of Hyndmans Creek bridge on Comboyne Road plus several other bridge replacements; reconstruction of Stage 2 of Beechwood Road and the list goes on.

In addition to delivering some major projects, Council will continue to deliver other services such as water and sewer services, library services, cultural services and waste services. We will also maintain our $2 billion plus of assets on behalf of the community.

In a time of sustained, increased growth across the local government area, our focus remains on ensuring that we are delivering value for money services for the community.

Craig Swift-McNair

General Manager

4

Page 5: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

OR

gA

NiS

AtiO

NA

lSt

RU

CtU

RE

Assets Systems

transport and Stormwater

Water

Sewer

infrastructure Delivery

Engineering trade Services

giS

Community Place

Community Engagement

Communications

Customer Service

libraries

Recreation and Buildings

Economic Development

and tourism

Strategic land Use Planning

Environmental Services

Regulatory Services

Environmental Health

Developmental Assessment

Building Certification

Development Contributions

Waste Management

financial Services

governance and Executive Services

information, Communications

and technology

Organisational Performance

Commercial and Business Services

Airport

Crematorium

the glasshouse

Environmental laboratory

Property Development

infrastructure and Asset ManagementDirector, Jeffery Sharp

Community and Economic growthDirector, Tricia Bulic

Development and Environment

Director, Matt Rogers

Corporate and Organisational Services

Director, Rebecca Olsen

general ManagerCraig Swift-McNair

Council

5

Page 6: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

COUNCillORPORtfOliOS

Mayor Peter Besseling

> Communication, Governance and Community Relations

Deputy Mayor lisa intemann

> Roads and Infrastructure> Future Planning and

Environment

Councillor Adam Roberts

> Glasshouse and Cultural Development

Councillor Justin levido

> Major Projects

Councillor Rob turner

> Economic Development, Events and Tourism

> Glasshouse and Cultural Development

Councillor Sharon griffiths

> Public Spaces> Corporate Services

Councillor geoff Hawkins

> Corporate Services> Public Spaces

Councillor trevor Sargeant

> Future Planning and Environment

> Economic Development, Events and Tourism

6

Councillor Michael Cusato

> Economic Development, Events and Tourism

> Major Projects> Roads and Infrastructure

Page 7: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

BUDgEt OvERviEW

Total expenditure in 2016–2017 will be $186m. This includes:

> $98.6m on the ongoing operational costs (excluding depreciation and asset write-offs)

> $66.2m on capital works projects> $14.7m on the cost of servicing debts (including loan

repayments and interest)> $6.5m on developer-provided assets

WHERE DOES tHE MONEY COME fROM?

Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from:

> rates and annual charges ($86.6m or about 50% of the income)> user charges and fees ($29.8m) for services such as water,

waste management, building and planning, animal registration, crematorium, airport and library

> interest income ($4.7m) > grants and contributions ($47.8m or around 28% of the

income) made up of state and federal government grants and of developer contributions

> other revenue ($4.4m) such as waste management income, fines and rental of Council facilities.

SOURCES Of iNCOME fOR CONtiNUiNg OPERAtiONS

fUNDiNgtHE OPERAtiONAl PlAN

In addition to these funding sources, the budget includes new loans of ($3.43m) and cash reserves that are drawn from each year to provide additional funds for works and services as required.

Total income is $173.3m compared to total expenditure of $186m. The difference is funded by a combination of approved loans and money previously allocated to reserves for these purposes.

7

100,000,000

90,000,000

80,000,000

70,000,000

60,000,000

50,000,000

40,000,000

30,000,000

20,000,000

10,000,000

Rates & Annual Charges

User Charges & Fees

Interest Received

Grants & Contributions

Other Operating Receipts

Page 8: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

The overview at right shows what Council will spend in 2016–2017 to deliver priorities the community have identified, with the spend including operating costs and capital works investment. in a number of areas such as the airport, expenditure is offset by income generation.

Shading is colour-coded to represent the primary Focus Area where this activity is located within the Operational Plan. Spend includes interest on loans but excludes loan principal overheads, transfers to reserves and depreciation.

BUDgEtSNAPSHOt

$43.5mNew transport infrastructure plus maintenance and upgrade of sealed and unsealed roads, rural roads and bridges, roadside vegetation and drainage

ROADS & tRANSPORt

8

$5.6MMaintenance and upgrade of playgrounds, maintenance of sports fields, maintenance and upgrades of open recreation space

PARkS & RECREAtiON

$1.8M Monitoring and maintaining the network

StORMWAtER

$2.6MManagement of weeds and noxious plants, control of feral animals, bush and environmental restoration and planning for future energy use options

NAtURAl RESOURCES

Page 9: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

$2.9M

$0.8M*

$1.9M

Three swimming pools and lifeguard services across six sites plus Wauchope pool redevelopment

Maintenance and operations of the Innes Gardens Memorial Park facility and 11 outlying cemeteries

Community advocacy, sponsorship of events and new infrastructure to create vibrant and connected places

$2.3MOperations and resources for three library locations, mobile lending services and digital collection

liBRARY

$1.5MTourism marketing, visitor centre operations, industry development programs, major events support

ECONOMiC DEvElOPMENt

AqUAtiC RECREAtiON

$4.5M*

Facility management and maintenance, cultural programs, community hire subsidy and back of house operations

glASSHOUSE

$1.4M Service payment and maintenance

StREEt ligHtiNg CREMAtORiUM & CEMEtERiES

$3.2M*

Operations and facility maintenance of Port Macquarie Airport

AiRPORt

COMMUNitY PlACE

$1.9M Operations and maintenance of two ferry services

fERRY

9

$21.3mMaintenance and design and construction of system improvements including small village sewerage scheme

SEWERAgE SERviCES

$20.3mCatchment and management of captured resources, reclaimed water, construction and maintenance of system improvements

WAtER SUPPlY

$17.3mOperation of the domestic waste collection service and transfer stations, construction of new facilities, education programs to reduce waste

WAStE MANAgEMENt

*This is a business unit of Council, expenditure is offset by income generation

Page 10: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

2016–2017 BUDgEtStAtEMENt

10

Operating Activities Movements Income from continuing operations

Rates & Annual Charges 86,545,908 User Charges & Fees 29,824,384 Interest Received 4,715,873Grants & Contributions 47,794,522 Other Operating Receipts 4,381,020

Expenses from continuing operations Employee Costs (47,981,635)Materials & Contracts (38,622,703)Depreciation (42,105,601)Interest Paid (4,495,417)Other Operating Payments (11,992,976)Loss on Disposal of Assets (2,900,000)

Operating result from continuing operations 25,163,375 Restricted Asset Movements Restricted asset movements receipts

Transfer from Restricted Assets 38,514,299 Restricted asset movements payments

Transfer to Restricted Assets (30,066,172)Net Revenues Used/(Provided) in Restricted Assets 8,448,127

Property, plant and equipment movements Property, plant & equipment movements receipts

Sale of Fixed Assets - Sale of Real Estate Development Assets

Property, plant & equipment movements payments Purchase of Assets (66,223,021) Developer Provided Assets 6,500,000

Net Revenues Used/(Provided) in Investing Activity (72,723,021)

Financing activities movements Financing activities receipts

Proceeds from Borrowings & Advances 3,425,000 Financing activities payments

Repayments of Borrowings & Advances (10,159,301) Net Revenues Used/(Provided) in Financing Activity (6,734,301)Net Result (Including Depreciation) (45,845,820) Add Back: Non Cash Items (45,005,601)Cash Budget Surplus/(Shortfall) (840,219)

Rates and Annual Charges – Local taxes levied by Local Government based on the value of propertyUser Charges and Fees – A charge or fee made in relation to a specified service provided by CouncilInterest Received – Interest received from financial institutions on Council investmentsGrants – Grants received from other levels of government to assist in the provision of Council servicesContributions – Contributions received from developers etc. towards the provision of Council servicesOther Operating Receipts – Other income not included above including Glasshouse receipts and Library charges

Employee Costs – All costs related to employees including wages and salaries, workers compensation, employee leave entitlements, superannuation, fringe benefits taxation, payroll taxation and travelling but not including employee costs associated with asset constructionMaterials and Contracts – Includes all materials and contracts used on delivering operational activitiesDepreciation – This is the estimated amount that Council’s assets will deteriorate in the 2016–2017 financial yearInterest Paid – The amount that is paid to financial institutions for interest on loans made to CouncilOther Operating Payments – Includes all payments not included in the above categories including telephone costs, bank charges, electricity, insurance, street lighting and mayoral and councillor fees

Transfer from Restricted Assets – Council puts funds into a restricted asset for future use, this transfer from the restricted asset is the spending of those funds

Purchase of Assets - This item includes the purchase of assets (such as heavy machinery) along with the construction by Council of assets (such as roads and footpaths)

Transfer to Restricted Assets – This is the transfer of funds into the restricted asset for future use

Cash Budget Surplus/(Shortfall) - The balance of income vs expenditure. When this figure is nil, council has a balance budget which means that its income for the year equals its expenditure for the year

Proceeds from Borrowings and Advances – This is the amount that Council intends to borrow from financial institutions

Repayment of Borrowings and Advances – This is the repayment of principal on Council loans

iNCOME EXPENSES

Page 11: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

The tables over the following pages show all the projects and the allocated budget that make up the capital works program for the 2016–2017 financial year. These projects are listed in the body of the Operational Plan. They are aligned with the relevant Delivery Program objective and show the performance measure and the section of Council responsible for delivery. Additional works are shown in the Operational Plan that are continued from previous years.

2016–2017WORkS PROgRAM

11

ENSURiNg gOOD gOvERNANCEReference number Description Multi-year project 2016-2017 Budget allocation

1.5.2.5 Renew technology infrastructure $2,107,196

1.5.2.8 Information and communications technology projects $500,000

1.5.4.2 Plant replacement program $3,883,500

1.5.6.6 Replacement of furniture at Council Offices $20,000

1.5.6.6 Purchase/cost furniture and fittings $33,200

lOOkiNg AftER OUR PEOPlEReference number Description Multi-year project 2016-2017 Budget allocation

2.1.2.6 Provide new bushfire tankers/vehicles $350,000

2.1.3.8 Purchase new laboratory technical instruments and equipment $17,900

2.6.2.12 Town and village signage installation $78,000

2.8.1.5 Expand Glasshouse artwork collection $14,800

2.9.2.1 Purchase library books $257,100

2.9.2.1 Update and replacement of library furnishings, fittings and equipment $20,000

2.9.2.1 Allocate Library Local Priority Grant $60,000

Page 12: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

2016–2017WORkS PROgRAM cont.

12

HElPiNg OUR COMMUNitY PROSPER Reference number Description Multi-year project 2016–2017 Budget allocation

3.2.2.3 Install new lawn beam at Innes Garden Memorial Park $25,000

3.2.2.3 Install new tree garden at Innes Garden Memorial Park $15,000

3.2.2.3 Install new lawn beams at Laurieton Cemetery $20,000

3.2.2.3 Install niche wall at Laurieton Cemetery $20,000

3.2.2.3 Carry out works associated with cemetery expansion at Wauchope $15,000

3.2.2.3 (e) Upgrade Port Macquarie Historic Cemetery $150,000

3.2.2.4 The Glasshouse – carry out major lift repairs $10,000

3.2.2.4 The Glasshouse – purchase plant and equipment $10,000

3.2.2.4 The Glasshouse – purchase technical equipment $56,000

3.2.4.2 Acquire land – easements etc. $30,000

3.5.1.1 Airport Business Precinct and landside improvements $500,000

lOOkiNg AftER OUR ENviRONMENt Reference number Description Multi-year project 2016–2017 Budget allocation

4.4.1.6 Construct Kew Transfer Station $2,200,000

4.4.1.9 Kingfisher Waste Depot – development application and designs $150,000

4.5.1.2 Bushland Open Space Strategy $20,000 Multi-year project

Page 13: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

2016–2017WORkS PROgRAM cont.

13

PlANNiNg AND PROviDiNg OUR iNfRAStRUCtURE Reference number Description Multi-year project 2016–2017 Budget allocation

5.1.1.1 (n) Ocean Drive duplication preconstruction Greenmeadows Drive south to Matthew Flinders Drive $186,000

5.1.1.1 (dd) Beechwood Road design stage 5 and 6 $150,000

5.1.1.3 Town Centre Master Plan – construct banner poles $90,000

5.1.1.3 Town Centre Master Plan – signage installation $75,000

5.1.1.3 (aa) Ocean Drive upgrade Mountain View Road to Fairwinds Avenue $2,373,090

5.1.1.3 (d) Ocean Drive Stingray Creek Bridge $9,946,000

5.1.1.3 (l) Town Centre Master Plan – construct Town Square $3,425,000

5.1.1.3 (w) Hyndmans Creek Bridge replacement $750,000

5.1.1.3 (x) Albert Street Bridge $400,000

5.1.1.3 (y) O’Neills Bridge Batar Creek Road $480,000

5.1.1.3 (z) Beechwood Road reconstruction Stage 2 $1,250,000

5.1.1.4 (d) Footpaths – various $351,250

5.1.1.4 (d)Ocean Drive shared path – Schools to Schools – construct shared path – Mountainview Road to Brotherglen Drive

$270,000

5.1.1.4 (d)Ocean Drive shared path design – Schools to Schools – design shared path – Pacific Drive to Glen Haven Drive

$25,000

5.1.1.4 (d)Ocean Drive shared path design – Schools to Schools – design shared path – Brotherglen Drive to Sirius Drive

$30,000

5.1.1.4 (r) Lake Road and Blackbutt Road roundabout $1,452,545

5.1.1.4 (v) Bulli Creek Bridge Comboyne Road construction $700,000

5.1.1.4 (v) Bulli Creek bridge Comboyne Road design $150,000

5.1.1.4 (w) Gordon Street upgrade $1,650,000

5.1.1.4 (x) Pappinbarra Road, Frazers Creek – road safety treatments $514,300

5.1.1.4 (y) Bago Road, north of Milligans Road, Wauchope – road safety treatments $251,200

5.1.1.4 (y) Bago Road, south of Isabel Place, Wauchope – road safety treatments $111,800

5.1.1.4 (z) Intersection of Bridge Street and Gore Street, Port Macquarie – road safety treatments $154,035

Page 14: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

2016–2017WORkS PROgRAM cont.

14

PlANNiNg AND PROviDiNg OUR iNfRAStRUCtURE cont. Reference number Description Multi-year project 2016–2017 Budget allocation

5.1.1.4 (aa) Intersection of Hill Street and Granite Street, Port Macquarie – roundabout $150,030

5.1.1.4 (bb) Ocean Drive shared path – construct shared path between Miala Street and Medical Centre $510,000

5.1.1.4 (cc)Kerb ramps and refuges – design and construct kerb ramps and refuges at multiple intersections in Port Macquarie, Laurieton and Kew

$295,000

5.1.1.4 (cc) Oxley Highway and Fernhill Road roundabout – design and construct kerb ramps and refuges $40,000

5.1.1.4 (dd) Wauchope Main Street – improve pedestrian amenity – construct Stage 1 $140,000

5.1.1.4 (ee)Ocean Drive pedestrian amenity – design improvements Kew to West Haven (Pacific Highway to Kew Drive)

$45,000

5.1.1.4 (ee)Bold St, Laurieton pedestrian amenity – develop and design improved pedestrian amenity along Bold Street from Tunis Street and Seymour Street

$20,000

5.1.1.4 (ff) Gordon Street Crossing – design for mid-block signal crossing $60,000

5.1.2.1 High traffic road resurfacing $900,407

5.1.2.1 Pavement rejuvenation $225,102

5.1.2.3 Road reseals – local government area $2,000,000

5.3.1.1 (c ) Wayne Richards Park Stage 3 – detailed design and approvals $300,000

5.3.1.2 (c) Upgrade and extend Port Macquarie Indoor Stadium $2,555,000

5.3.1.2 (l) Wauchope Swimming Pool upgrade of 50 m pool $1,787,966

5.3.1.2 (h) Town Centre Master Plan – landscape upgrades $100,000

5.3.1.4 (ad) Master Plan development, repairs and signage installation Port Macquarie Coastal Walk $218,000

5.3.2.1 Riverbank erosion management Bruce Porter Reserve $20,000

5.3.2.1 Bunny’s Corner – riverbank erosion management $10,000

5.3.2.1 Settlement Point Reserve – riverbank erosion management $30,000

5.3.2.1 Park signage replacement $18,600

5.3.2.2 Replace retaining wall Apex Park boat ramp $30,000

5.3.2.5 Park furniture replacement Dunbogan Reserve $20,000

5.3.2.5 Park furniture replacement John Downes Park $15,000

Page 15: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

2016–2017WORkS PROgRAM cont.

15

PlANNiNg AND PROviDiNg OUR iNfRAStRUCtURE cont. Reference number Description Multi-year project 2016–2017 Budget allocation

5.3.2.5 Park furniture replacement Port Macquarie Historic Cemetery $15,000

5.3.2.6 Playground replacement Foreshore Reserve $80,000

5.3.2.6 Playground replacement Innes Lake Park $60,000

5.3.2.6 Playground replacement Lake Cathie community Hall Reserve $40,000

5.3.2.6 Playground replacement softfall Long Flat Showground $15,000

5.3.2.6 Playground renewal Muston Street Reserve $65,000

5.3.2.6 (l) Park embellishment Innes Peninsula (Brierley Hill) $200,000

5.3.2.7 Sporting facility renewal Andrews Park $5,000

5.3.2.7 Children’s cycle track Blair Reserve $45,000

5.3.2.7 Sporting facility renewal Findlay Park $20,000

5.3.2.7 Floodlighting installation at Lank Bain Sports Ground $140,000

5.3.2.7 Sporting facility renewal Lank Bain Sports Ground $75,000

5.3.2.7 Sporting facility renewal Macquarie Park $20,000

5.3.2.7 Asphalt seal bike track Ruins Way Park $10,000

5.3.2.7 (i) Provision of floodlighting Oxley Oval $160,000

5.3.2.9 Pathway replacement Ashdown Reserve $10,000

5.3.2.9 Pathway replacement Bartlett’s Beach Reserve $20,000

5.3.2.9 Pathway replacement Kooloonbung Creek Nature Park $100,000

5.3.2.9 Pathway replacement Queenslake Reserve $100,000

5.3.2.9 Pathway replacement Spooneys Bay Reserve $80,000

5.3.2.9 Pathway replacement Wauchope riverwalk (adj to Rocks Ferry Rd) $80,000

5.3.2.9 Town Centre Master Plan – foreshore walkway preconstruction works $20,000

5.5.1.2 (b) Southern arm trunk main Houston Mitchell Drive $5,500,000

5.5.1.3 (b) Install new residential and business water supply services $400,000

5.5.1.4 Water supply future designs $100,000

Page 16: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

2016–2017WORkS PROgRAM cont.

16

PlANNiNg AND PROviDiNg OUR iNfRAStRUCtURE cont. Reference number Description Multi-year project 2016–2017 Budget allocation

5.5.1.4 (g) Upgrade Kendall booster water pump station $200,000

5.5.1.4 (h) Construct Bago Telemetry Tower $150,000

5.5.2.4 Renew existing live water mains $900,000

5.5.2.4 Renew water meters $350,000

5.5.2.4 Renew water assets $800,000

5.5.2.4 Water asset replacement programs $150,000

5.5.2.4 Water supply flowmeters upgrade and installation $75,000

5.5.2.4 Water supply technical equipment $15,000

5.5.3.1 Sewerage services future designs $100,000

5.5.3.1 (j) Lakewood/Kew (Area 15) sewerage upgrades $3,000,000

5.5.3.1 (k) Thrumster (Area 13) Sewerage Treatment Plant $500,000

5.5.3.3 (b) Dewater effluent pond 3 Port Macquarie Sewerage Treatment Plant $200,000

5.5.3.3 (d) Supply rising sewer reclaimed main to Thrumster $500,000

5.5.3.3 (h) Port Macquarie Sewer Pump Station 71 and new rising main $850,000

5.5.3.3 (i) Thrumster reclaimed water interim supply Oxley Highway Reservoir (0.5 ML storage) $900,000

5.5.3.3 (j) Thrumster reclaimed water trunk mains $220,000

5.5.3.3 (k) Oxley Highway reclaimed water pumping station $200,000

5.5.3.3 (l) Upgrade Port Macquarie Reclaimed Water Treatment plant $2,000,000

5.5.3.4 (c ) Mechanical Sewerage Treatment Plant asset replacement $200,000

5.5.3.4 (i) Small towns sewerage North Shore $250,000

5.5.3.4 (n) Bonny Hills Reclaimed Sewer Treatment Plant UV system $300,000

5.5.4.3 (a) Port Macquarie Sewer Treatment Plant refurbishment program – aerator lagoon $150,000

5.5.4.4 Sewer system minor extensions $250,000

5.5.4.4 Sewerage pump replacement program $150,000

5.5.4.4 Renewal of sewer reticulation pipelines $900,000

Page 17: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

2016–2017WORkS PROgRAM cont.

17

PlANNiNg AND PROviDiNg OUR iNfRAStRUCtURE cont. Reference number Description Multi-year project 2016–2017 Budget allocation

5.5.4.4 Reline sewer pipelines $200,000

5.5.4.4 Sewer electrical switchboard replacement $150,000

5.5.4.4 Sewerage treatment plant electrical replacement $100,000

5.5.4.4 Odour control installations $100,000

5.5.4.4 Port Macquarie sewerage treatment plant decanter rubber replacement $50,000

5.5.4.4 Sewer fund technical instruments $15,000

5.5.5.6 Chemical dosing system upgrade $200,000

5.5.6.1 Stormwater remediation Karalee Parade $30,000

5.5.6.1 Stormwater remediation works $30,000

5.5.6.1 (e) Various design works – additional transport and stormwater designs $200,000

The capital works budget includes an allocation of $6.5m for road, water and sewer assets associated with development. These projects are not incorporated as line items into the Operational Plan until appropriate milestones are reached. The Town Centre Master Plan is funded by a business levy.

Page 18: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

The table over the following pages show all projects that are continuing from 2015–2016. These projects are listed in the body of the Operational Plan.

PROJECtS CONtiNUiNg fROM2015–2016

18

ENSURiNg gOOD gOvERNANCEReference number Description Multi-year project

1.5.6.10 Commence construction of the new works depot in Port Macquarie

lOOkiNg AftER OUR PEOPlEReference number Description Multi-year project

2.6.2.8 (a) Town Centre Master Plan – Place Making activation at the Hay Street forecourt, Foreshore and Clarence shoreline

HElPiNg OUR COMMUNitY PROSPERReference number Description Multi-year project

3.2.2.3 (e) Upgrade Port Macquarie Historic Cemetery

3.4.1.1 Implementation of the Digital Strategy

lOOkiNg AftER OUR ENviRONMENtReference number Description Multi-year project

4.8.1.2 (b) Continue to undertake the landfill gas capture trial project at Cairncross Landfill

4.8.1.5 Commence review of Hastings River Flood Study for climate change impacts

4.8.1.7 Continue updating the Wrights and Yarranabee Creeks Flood Study

PlANNiNg AND PROviDiNg OUR iNfRAStRUCtUREReference number Description Multi-year project

5.1.1.1 (a) Comboyne Road – undertake design/preconstruction – replace bridge over Hartys Creek Id No. 109

5.1.1.1 (d) North South Link Road – undertake design/preconstruction

5.1.1.1 (h) Town Centre Master Plan – undertake design/preconstruction of walkway from Town Beach to Kooloonbung Creek

5.1.1.1 (k) Town Centre Master Plan – undertake design/preconstruction of Town Square

5.1.1.1 (o) Beechwood Road – undertake preconstruction for upgrades of segments 20, 40 and 50

Page 19: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

PROJECtS CONtiNUiNg fROM2015–2016 cont.

19

PlANNiNg AND PROviDiNg OUR iNfRAStRUCtURE cont. Reference number Description Multi-year project

5.1.1.1 (u) Works Depot relocation – undertake preconstruction/design

5.1.1.1 (y) Hasting River Drive – Aston Street crossing

5.1.1.1 (cc) Lake Road – continuation of detailed design of dual lanes

5.1.1.1 (ee) Hastings River Drive – Hughes Place to Boundary Road

5.1.1.3 (a) Hastings River Drive – undertake continued construction/delivery Gordon Street to Aston Street

5.1.1.3 (r)Houston Mitchell Drive – commence construction of Stages 2 and 3, from new Houston Mitchell Drive/ Ocean Drive roundabout west

5.1.1.4 (c) Ocean Drive – undertake continued design/construction/delivery – Matthew Flinders Drive to Greenmeadows duplication

5.1.1.4 (e) Laurieton Town Centre

5.1.1.4 (f) Wauchope Town Centre

5.1.1.4 (g) Town Centre Master Plan – develop a management plan and undertake works for the entertainment precinct

5.2.1.4 Area Wide Traffic Study

5.3.1.1 (d) Continued preconstruction and designs work for the Lake Cathie Bonny Hills Regional Sporting complex

5.3.1.2 (i) Flynn’s Beach – upgrade sea wall

5.3.1.3 (b) Googik Track – construct shared walkway/cycleway, Stage 2

5.3.1.4 (q) Westport Reserve – upgrade boat ramp Stage 2

5.3.1.4 (v) Bonny Hills Reserve – upgrade public amenities as per Master Plan

5.3.1.4 (w) Town Beach Reserve – construct public amenities

5.3.1.4 (z) Town Green – design and implement Master Plan

5.3.1.4 (ab) Henry Kendall Reserve – develop leash free dog area

5.3.2.9 (b) Kooloonbung Creek Nature Park – replace timber boardwalk

5.5.1.1 (d) O’Brien’s Dam rehabilitation works

5.5.1.1 (g) Wauchope Water Treatment Plant augmentation

5.5.1.1 (i) Kew/Kendall – feasibility study gas chlorine system

5.5.1.2 (a) North Haven to Laurieton trunk main and Stingray Creek Bridge crossing

5.5.1.3 (m) Ocean Drive Marbuck bypass – connection to Camden Haven trunk main

Page 20: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

PROJECtS CONtiNUiNg fROM2015–2016 cont.

20

PlANNiNg AND PROviDiNg OUR iNfRAStRUCtURE cont. Reference number Description Multi-year project

5.5.1.3 (o) Sancrox Reservoir (to Area 13 – 750 mm) – trunk main construction

5.5.1.4 (b) Port Dam switchgear upgrade

5.5.3.1 (c) Port Macquarie Reclaimed Water Treatment Plant upgrade for growth

5.5.3.1 (e) Small towns sewerage program – provision of centralised sewerage systems for Comboyne

5.5.3.1 (f) Small towns sewerage program – provision of centralised sewerage systems for Long Flat

5.5.3.1 (g) Small towns sewerage program – provision of centralised sewerage systems for Telegraph Point

5.5.3.1 (l) Stingray Creek Bridge New Sewer Mains

5.5.3.3 (c) Replacement of sewer telemetry and computer hardware

5.5.3.4 (a) Camden Haven upgrade and upsize of mains and pump stations

5.5.3.4 (i) Small towns sewerage North Shore

5.5.6.1 (b) Short Street drainage – undertake condition rating and investigations

5.5.6.1 (c) Lake and Jindalee Roads – investigate and design stormwater drainage

5.5.6.1 (d) East Port, Gordon/Owen Streets – investigate and design stormwater drainage

5.5.6.3 (a) Continue stormwater remediation – Batar Creek Road System, Kendall Stage 2

5.5.6.3 (b) Continue stormwater remediation – Skyline Terrace Bonny Hills

5.5.6.3 (c) Continue stormwater remediation – flood remediation Blackbutt Creek, Wauchope

5.5.6.3 (d) Open drain reprofiling – Oleander Avenue to Koala Street

5.5.6.4 (b) Continue stormwater remediation – Calwalla Crescent

5.5.7.1 (b) Wrights Creek – dredge to lower standing water levels and improve capacity

5.5.7.2 (ca) Settlement Shores canals – routine maintenance

5.5.7.2 (b) Settlement Shores – hydrographic survey and maintenance planning

5.5.7.2 (c) Broadwater Canal – structural condition assessments

Page 21: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

The Capital Works program for 2016–2017 has been developed to meet future infrastructure needs and reflect the objectives of the Community Strategic Plan. Investment in new works will total $66.2m.

The individual projects are listed in greater detail throughout the Operational Plan in the relevant focus area and are shaded.

This graph shows where the funding comes from to carry out these works. It should be noted that reserve funds are rating revenue from previous years that have been put away for future expenditure. Included in the transfers from reserves are loans that were borrowed in previous years. Unspent loan funding is transferred to reserves so that it can be used when required.

fUNDiNg tHEWORkS PROgRAM

2016–2017 CAPitAl WORkS fUNDiNg SOURCES

21

Note: Reserve funds include rating revenues from previous years that have been put away to fund future expenditure

25,000,000

20,000,000

15,000,000

10,000,000

5,000,000

0Capital grants Loans Environmental

levySection 94 &

Section 64 developer

contributions

Other capital contributions

Transfer from reserves

Special Rate Variation Funds

General rating revenue

Page 22: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

A snapshot of the location of key projects proposed in the 2016–2017 Operational Plan.

kEY PROJECtSMAP

WAUCHOPE/RURAl > Wauchope Swimming Pool upgrade of 50m pool – $1,787,966> Beechwood Road design stage 5 and 6 – $150,000> Hyndmans Creek Bridge replacement – $750,000> Albert Street Bridge – $400,000> O’Neills Bridge Batar Creek Road – $480,000> Beechwood Road reconstruction Stage 2 – $1,250,000> Bulli Creek bridge Comboyne Road design and construction – $850,000

PORt MACqUARiE> Upgrade and extend Port Macquarie Indoor Stadium – $2,555,000> Wayne Richards Park Stage 3 – Details design and approvals – $300,000> Lake Road and Blackbutt Road Roundabout – $1,452,545> Gordon Street upgrade – $1,650,000> Thrumster (Area 13) Sewerage Treatment Plant – $500,000> Port Macquarie Sewer Pump Station 71 and new rising main – $850,000

lAURiEtON/CAMDEN HAvEN> Ocean Drive Stingray Creek Bridge – $9,946,000> Southern arm trunkmain Houston Mitchell Drive – $5,500,000> Upgrade Kendall Booster Water Pump Station – $200,000> Lakewood/Kew (Area 15) sewerage upgrades – $3,000,000> Bonny Hills Reclaimed Sewer Treatment Plant UV system – $300,000

22

Page 23: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

The 2016–2017 capital works program includes a $2.1M investment in embellishments to Council parks and reserves across the region. This map provides a snapshot of the major improvements according to location.

PARkS AND RECREAtiONPROJECtS MAP

PORt MACqUARiE> Playground replacement Innes Lake Park – $60,000> Playground renewal Muston Street Reserve – $65,000> Park embellishment Innes Peninsula (Brierley Hill) – $200,000> Children’s cycle track Blair Reserve – $45,000> Provision of floodlighting Oxley Oval – $160,000> Pathway replacement Kooloonbung Creek Nature Park – $100,000

lAURiEtON/CAMDEN HAvEN > Riverbank erosion management Bruce Porter Reserve - $20,000> Playground replacement Foreshore Reserve - $80,000> Playground replacement Lake Cathie community Hall Reserve - $40,000> Pathway replacement Queenslake Reserve - $100,000> Pathway replacement Spooneys Bay Reserve - $80,000

WAUCHOPE/RURAl > Floodlighting installation at Lank Bain Sports Ground – $140,000> Sporting facility renewal Lank Bain Sports Ground – $75,000> Pathway replacement Wauchope riverwalk (adj to Rocks Ferry Rd) – $80,000

23

Page 24: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

The activities and programs described in this Operational Plan are categorised according to the five Focus Areas that were developed in the Towards 2030 Community Strategic Plan.

These Focus Areas and the types of work carried out within them are as follows:

> Ensuring Good Governance – engagement, communications, leadership and organisational management

> Looking After Our People – community development, culture, heritage, sport and recreation

> Helping our Community Prosper – economic development, business support, airport, Glasshouse

> Looking After our Environment – land management and restoration, water cycle management, waste

> Planning and Providing our Infrastructure – planning, constructing and maintaining roads; planning, constructing and maintaining recreation facilities; planning for land use; constructing and maintaining water, sewer and stormwater services.

HOW tO READtHiS DOCUMENt

liNkiNg tO tHE DElivERY PROgRAM

Each Focus Area in the document has a cover page that summarises the area’s objectives from the Towards 2030 Community Strategic Plan (What are we trying to achieve?) and the Councillors’ Delivery Program (How do we get there?).

These overviews help to put the specific activities and programs of this one year Operational Plan in the context of broader community goals, and the Delivery Program.

NUMBERiNg SYStEM

In order to assist with monitoring activity from the Operational Plan against the objectives of the Four Year Delivery Program (2013–2017), a numbering system has been developed. This means every activity across the four years has its own number.

Each action item has an individual reference number linking it back to the relevant Focus Area. Where numbers don’t appear in sequential order it means that actions had been completed in previous years during the 2013–2017 Delivery Program cycle. Delivery Program Objectives that do not have an Operational Plan number associated indicate that action has occurred prior to 2016–2017.

24

Page 25: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

5.1.1 Plan, investigate, design and construct road and transport assets which address pedestrian, cyclist and vehicular needs

Lead responsibility

Community partners Performance measures

5.1.1.1 Undertake design/preconstruction activities on road and transport assets including:

Infrastructure Delivery

5.1.1.1 (k) Town Centre Master Plan - undertake design/preconstruction of Town Square

Infrastructure Delivery

Project delivered according to approved project plan

5.1.1.1 (n) Ocean Drive - undertake preconstruction for duplication Greenmeadows Drive south to Matthew Flinders Drive

Infrastructure Delivery

Project delivered according to approved project plan

5.1.1.1(dd) Beechwood Road - design stage 5 & 6 of Beechwood Road reconstruction (Riverbreeze to Waugh Street)

Transport and Stormwater Network

Program delivered according to approved project plan

5.1.1.3(x) Albert Street bridge - replace single lane timber bridge with concrete culvert Infrastructure Delivery

This diagram explains how to read the activity tables throughout the document.

UNDERStANDiNgtHE tABlES

This symbol indicates that the action is continued from the previous year

This symbol indicates the action is new and has not appeared in previous plans

This column is the action Council will undertake in 2016-2017

This column lists the Council section responsible for the action

This column shows how the action will be measured and reported against

Shading indicates capital works projects/initiatives

This row contains the Four Year Delivery Program (DP) - objectives that guide what activities are carried out in the one year plan

25

Page 26: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

gU

iDiN

g

PR

iNC

iPlE

ENSURiNg gOOD gOvERNANCE

WHO Will ASSiSt US?NSW Government

Local businesses

NSW Government

(Land & Property Information)

State Government

Northern Joint Regional Planning Panel

Department of Planning

Other state government agencies

Community interest

groups

HOW DO WE gEt tHERE?

1.1 Engage the community in decision making by using varied communication channels that are relevant to residents

1.2 Create professional development opportunities and networks to support future community leaders

1.3 Create strong partnerships between all levels of government and their agencies so that they are effective advocates for the community

1.4 Demonstrate conscientious and receptive civic leadership

1.5 Implement innovative, fact-based business practices

WHO Will ASSiSt US?

> NSW Government

> Local businesses

> NSW Government (Land & Property

Information)

> State Government

> Northern Joint Regional Planning Panel

> Department of Planning

> Other State Government agencies

> Community interest groups

WHAt ARE WE tRYiNg tO ACHiEvE?

A collaborative community that works together and recognises opportunities for community participation in decision making that is defined as ethically, socially and environmentally responsible.

26

Page 27: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

1

1.1.1

Lead responsibility Performance measures

1.1.1.1 Community Engagement and Planning

1. Audit media message uptake2. Distribute quarterly newsletter3. Meet statutory advertising requirements4. Increase engagement in social media5. Maintain up to date corporate website

1.1.2

Lead responsibility Performance measures

1.1.2.1 Community Engagement and Planning

1. Number of engagement activities undertaken during the year and numbers participating2. Increased participation on PMHCListening 3. Conduct four lunchtime conversations across the Local Government Area (LGA) 4. Advise Community Reference Group members of engagement opportunities

1.2.1

Lead responsibility Performance measures

1.2.1.1 Governance and Executive Services

Minimum of five equitable development opportunities offered

1.3.1

Lead responsibility Performance measures

1.3.1.1 General Manager's Office Participate in ongoing discussions and make submissions at local and state level

1.3.1.2 General Manager's Office Meetings scheduled

1.3.1.3 General Manager's Office Meetings scheduled

Convene meetings with local business chambers

Use a variety of tools to engage with the community in a manner that is transparent, effective, relevant and inclusive

Support community involvement in decision making through education around Council matters and services

Provide effective leadership that supports the community

Convene meetings with state and federal members

Participate in active alliances with other agencies to make effective decisions that address the needs of our community

Implement the Councillor Professional Development Program

Progress local government reform through consideration of Joint Organisations and responding to Office of Local Government engagement

Use a variety of media, direct publication and digital mediums to keep the community informed

Use a combination of online, face to face and printed engagement methods to facilitate community involvement in decision making

27

Page 28: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

2

1.4.1

Lead responsibility Performance measures

1.4.1.1 Community Engagement and Planning

1. Annual report adopted by Council and submitted to Office of Local Government (OLG) no later than 30 November2. Publish community report card and distribute to community groups in December

1.4.1.2 Community Engagement and Planning

Four Year Delivery Program progress report provided to Council on a six monthly basis

1.4.1.3 Governance and Executive Services

Annual review undertaken and presented to Council no later than 30 June

1.4.1.4 Governance and Executive Services

GIPA annual report submitted to Information and Privacy Commission no later than 31 October

1.4.1.5 Governance and Executive Services

Report prepared annually and presented to Council no later than 31 December

1.4.1.7 Community Engagement and Planning

An annual operational plan is adopted no later than 30 June

1.4.2

Lead responsibility Performance measures

1.4.2.1 Financial Services 1. Three quarterly budget review statements and an annual report submitted to Council 2. Financial statements prepared by 30 September3. Audited financial statements lodged with OLG by 30 October

1.4.2.2 Financial Services 1. Investment return to exceed OLG benchmark 2. Investment report tabled at Council meeting on a monthly basis

Provide a progress report on the implementation of the 2013-2017 Four Year Delivery Program

Undertake development of the one year operational plan

Manage Council’s investment portfolio to optimise investment returns within the constraints of the policy, the Local Government Act and Regulations

Engage with the community on impacts and changes of operations

Manage Council’s financial assets; provide accurate, timely and reliable financial information for management purposes and provide plain English communityreporting

Produce and submit the annual Code of Conduct complaints report in accordance with OLG requirements

Monitor and accurately report on Council’s financial position in accordance with Local Government Act requirements

Produce and submit the annual report in accordance with Local Government Act requirements

Review the Legislative Compliance Register

Produce and submit the annual Government Information Public Access (GIPA) Report in accordance with the GIPA Act requirements

28

Page 29: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

3

1.4.2

Lead responsibility Performance measures

1.4.2.4 Financial Services 1. Develop draft annual budget no later than 30 April2. Develop draft fees and charges by 30 April3. Review the Long Term Financial Plan in line with budget adoption by 30 June4. Final budget to be adopted by Council by 30 June

1.4.2.6 Financial Services Present 10 monthly financial reports to Council (excl. July & January)

1.4.2.8 Assets and Systems Revaluation completed by 30 June

1.4.3

Lead responsibility Performance measures

1.4.3.1 Governance and Executive Services

Annually update Disclosure Register by 30 September

1.4.3.2 Governance and Executive Services

1. Policy reviewed and adopted by 30 November2. Submit to OLG by 1 December

1.4.3.3 Governance and Executive Services

1. Report biannually in July and February on any PIDs 2. PID annual report submitted to NSW Ombudsman by 31 October

1.4.3.4 Water and Sewer 1. Performance reporting data collated and forwarded to NSW Office of Water annually2. Annual performance of PMHC water and sewer business in comparison to state medians reported to Council3. Recommendations from triple bottom line summary report detailed by NSW Office of Water are considered for action

Manage Council’s financial assets; provide accurate, timely and reliable financial information for management purposes and provide plain English communityreporting (cont.)

Report on Public Interest Disclosures (PID)

Undertake revaluation of Council's water and sewer assets

Coordinate lodgement of annual Disclosure of Interest Returns

Prepare monthly financial reports for Council

Submit annual performance reporting for the water and sewer business to NSW Office of Water for benchmarking comparisons

Develop annual Operational Plan budget and review the Long Term Financial Plan

Review the Payment of expenses and provision of facilities for Councillors Policy

Build trust and improve Council's public reputation through transparency and accountability

29

Page 30: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

4

1.4.4

Lead responsibility Performance measures

1.4.4.1 Governance and Executive Services

Two off-site Council meetings held during the year (March Wauchope, October Laurieton)

1.4.4.3 Governance and Executive Services

Minimum of four rural visits per annum

1.5.1

Lead responsibility Performance measures

1.5.1.1 Community Engagement and Planning

1. Greater than 75% of customer initial interaction is dealt with at first point of contact2. 75% of calls answered within service level standards (currently 20 seconds)3. Call abandonment rate is 3% or lower

1.5.1.3 Community Engagement and Planning

1. All new staff inducted on Customer Service Charter2. Deliver internal education program

1.5.1.5 Community Engagement and Planning

Report annually to Council by 30 September

1.5.1.6 Economic Development Submit quarterly reports to the Office of the NSW Small Business Commissioner

1.5.1.7 General Manager's Office Applications for grants made as available

1.5.1.8 Economic Development 1. Implement actions from Economic Development Strategy2. Report to Council on Economic Development Steering Group (EDSG) activity in December and June3. Undertake biannual business confidence survey and report to EDSG

Promote the visibility and profile of councillors through improved access by the community

Deliver the Engaging and Communicating with our community program

Deliver the Take the Council to the Community program

Deliver high quality customer interactions through the Customer Service Centres and Call Centre within service level standards

Educate staff on the Customer Experience Charter

Meet the charter requirements of the Small Business Friendly Council Program

Further develop an innovative, business friendly and solutions - focused culture within Council

Review and evaluate referrals, compliments and complaints on an annual basis

Address community needs with a transparent, responsive, efficient and effective organisation that is customer focused, and aspires to deliver best practiceservice

Actively seek grant funding opportunities to maximise delivery of Council priorities

30

Page 31: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

5

1.5.2

Lead responsibility Performance measures

1.5.2.4 Assets and Systems Less than five complaints received relating to GIS data accuracy as captured in the Customer Record Management (CRM) system

1.5.2.5 ICT Undertake technology infrastructure renewal projects according to project plan

1.5.2.8 ICT Projects delivered as per approved project plans

1.5.3

Lead responsibility Performance measures

1.5.3.1 Development Assessment

Number of applications and processing times, together with a commentary ondevelopment trends reported to Council quarterly

1.5.3.4 Business Improvement Office

1. Progress report biannually to Council2. Implement actions as per Council resolution of June 2016

1.5.3.6 General Manager's Office Two forums held with the community

1.5.4

Lead responsibility Performance measures

1.5.4.1 Commercial and Business Services

Completion of audit action items as per agreed timelines with quarterly reporting to the Audit Committee.

Renew technology infrastructure to provide secure and responsive Information Communication Technology (ICT) systems

Provide and maintain efficient and effective information management systems that are accessible, user friendly and meets community and organisationrequirements

Provide Geographic Information Systems (GIS) to the organisation and to the community in a timely and effective manner

Work across the organisation to facilitate business improvement initiatives

Use procurement, tendering and purchasing approaches that provide best value to the community

Continue to implement and monitor the procurement strategy action items

Progress Service Level Project and incorporate feedback through active engagement on Service Levels

Ensure ratepayer value for money through continuous improvement in quality, effectiveness and efficiency of delivery of Council services

Ensure development assessment, building certification and subdivision certification activities are completed efficiently and in accordance with legislation

Undertake delivery of ICT projects

31

Page 32: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

6

1.5.4

Lead responsibility Performance measures

1.5.4.2 Transport and Stormwater Network

Plant replacement program delivered according to approved schedule

1.5.5

Lead responsibility Performance measures

1.5.5.1 Governance and Executive Services

Review the risk register on a quarterly basis and report to the Audit Committee

1.5.5.2 Governance and Executive Services

Review and implement the Risk Management Action Plan on a quarterly basis and report to Executive

1.5.5.3 Governance and Executive Services

Annual review completed and insurance renewals in place

1.5.6

Lead responsibility Performance measures

1.5.6.4 Organisational Development

Performance and improvements against the Equal Employment Management Plan targets are reported in the Annual Report

1.5.6.6 Replacement program carried out according to approved schedule

1.5.6.10 Assets and Systems, Transport and Stormwater Networks

Project delivered according to approved project plan Commence construction of the new works depot in Port Macquarie (multi-year project)

Carry out office furniture replacement program

Create a workplace that reflects Human Resources current best practice

Review the Corporate Risk Register

Ensure there is appropriate management of risk for Council and the community

Implement workplace strategies and processes as outlined in the Equal Employment Management Plan

Ensure plant purchases are in line with the plant replacement program

Implement the Risk Management Action Plan, as part of the statewide continuous improvement program

Conduct an annual review of insurance coverage

Use procurement, tendering and purchasing approaches that provide best value to the community (cont.)

32

Page 33: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

33

fOC

US

AR

EAlOOkiNg AftER OUR PEOPlE

HOW DO WE gEt tHERE?

2.1 Create an environment and culture that allows the Port Macquarie-Hastings community to feel safe

2.2 Provide young people with a range of leisure activities and opportunities for personal development

2.3 Provide medical and social services for all members of the community

2.4 Develop partnerships within the community to build on existing strengths and improve areas of social disadvantage

2.5 Create events and activities that promote interaction and education

2.6 Provide social and community infrastructure and services

2.7 Empower the community to be active and involved in community life

2.8 Promote cultural and artistic expression2.9 Promote a healthy lifestyle through education,

support networks and facilities

WHO Will ASSiSt US?

> NSW Surf Lifesaving Association> Rural Fire Service> BFMC> Landcare> NSW Fire and Rescue> Local Aboriginal Land Council> Crown Lands> National Parks> Department of Planning> NSW Fire Brigade> Office of Local Government> Environmental Protection Authority (EPA)> NSW Public Health Unit> Dept of Health> NSW Food Authority> NSW Police> State Debt Recovery Office> Youth Network> Schools> Community Groups> Government Agencies> Bearlay Interagency> State Government> Other LGAs> Local Businesses> TCMP community> 355 Committees Property Services

WHAt ARE WE tRYiNg tO ACHiEvE?

Our social infrastructure and community programs create a healthy, inclusive and vibrant community.

Page 34: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

8

2.1.1

Lead responsibility Performance measures

2.1.1.4 Recreation and Buildings 1. Deliver approved lifeguard services2. Deliver lifeguard education programs to schools and community groups (target 2500 students)

2.1.2

Lead responsibility Performance measures

2.1.2.2 Recreation and Buildings Risk management plan actions for current financial year implemented

2.1.2.3 Recreation and Buildings 1. Monitor and assess one site per month to identify risk rating2.Develop priority listing by 30 November3.Deliver works in accordance with relevant standards

2.1.2.4 Recreation and Buildings Two programs delivered by 30 June

2.1.2.6 Emergency Management Equipment supplied in accordance with RFS allocation

2.1.3

Lead responsibility Performance measures

2.1.3.1 Regulatory Services 1. Greater than 80% of complaints responded to within set customer service standards2. A minimum of 40 fire safety, 250 pool, 1000 on-site sewage and 195 public health inspections completed

Provide leadership in implementing safety initiatives

Implement Council actions included within the local government area (LGA) Bushfire Risk Management Plan (BFRMP) in relation to Council-owned and managed land

Deliver annual maintenance programs for bushfire risk mitigation works on Council land in accordance with the BFRMP — adopted by NSW Rural Fire Service

Deliver bushfire preparedness and planning programs to the community

Manage and deliver Council lifeguard services

Monitor and take action as appropriate to ensure compliance with development approvals and building, environmental, public health and on-site sewage standards

Advocate for, support and coordinate emergency management services

Implement inspection, compliance and education practices that ensure acceptable levels of public and environmental health; meet building and fire safety standards

Provide new bushfire tankers/vehicles in accordance with Rural Fire Service (RFS) annual allocation

34

Page 35: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

9

2.1.3.5 Regulatory Services 1. Greater than 80% of complaints regarding compliance with regulation and legislation responded to within set customer service standard2. Number of offences detected during proactive patrols3. Report legislated companion animal data through the annual report

2.1.3.6 Water and Sewer 1. Daily testing and monitoring program achieved2. Nil reportable incidents in accordance with NSW Health agreed protocols3. Water quality is within the health limits set by Australian Drinking Water Guidelines 2011 100% of the time

2.1.3.8 ` 1. All sampling, analysis and reporting of operational and regulatory requests completed in accordance with approved budgets2. All sampling, analysis and reporting of operational and regulatory requests completed in accordance with the required service standards3. National Association of Testing Authorities (NATA) corporate accreditation maintained4. Laboratory equipment purchased as required within budget

2.1.3.10 Regulatory Services Distribute education materials and participate in community companion animal events

2.2.1

2.2.1.1 Community Place 1. Youth Week held annually2. Youth Advisory Council activities coordinated3. Undertake two skill development programs for young people

Provide ranger and local law enforcement services to ensure compliance with legislation, regulations and Council policies relating to parking, regular beach patrols, illegal signage, sale of goods on roads, building site sediment control and companion animal management

Provide a safe water supply in accordance with Australian Drinking Water Quality Guidelines

Undertake all sampling, analysis and reporting of operational and regulatory requirements as requested and provide services to outside organisations on an approved cost for service basis. Purchase new technical instruments and equipment as required.

Provide opportunities for young people to learn and develop through 'youth-focused' initiatives

Build capacity in the community to support young people

Deliver statewide companion animal education programs

35

Page 36: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

10

2.3.1

Lead responsibility Performance measures

2.3.1.2 Community Place Advocacy undertaken and social impact and social justice issues documented

2.4.1

Lead responsibility Performance measures

2.4.1.3 Community Place 1. Disability Action Plan strategies implemented on time and on budget 2. Annual report of achievements against the Disability Discrimination Act for the previous financial year presented to Council3. Seniors Week program developed and implemented

2.4.1.7 Community Place 1. Strategies completed on time and on budget 2. NAIDOC week supported3. Sorry Day activities conducted4. Reconciliation Week activities and program implemented

2.4.1.8 Community Place 1. Two rounds of grants completed2. Conduct annual review of grant compliance

2.5.1

Lead responsibility Performance measures

2.5.1.9 Community Place, General Manager's Office

1. Annual Australia Day events coordinated, held and evaluated 2. Handa Sister City (three day) cultural exchange coordinated and held3. Countdown to Christmas event held4. Moonlight Movies events held5. Citizenship ceremonies held

Advocate, support and/or implement wellness and healthy lifestyles in accordance with the 2013-2017 social strategy

Provide sponsorship and expertise to community groups that coordinate social and community events

Implement the actions from the Aboriginal Awareness and Understanding Strategy

Work with community groups to build capacity on social justice issues

Coordinate the grants program to assist the community to deliver projects that contribute to a sense of place

Advocate on the social impacts and social justice initiatives identified through the Place Making initiative for the local communities in the LGA

Coordinate and facilitate the Access Committee and in conjunction undertake programs, activities and events utilising a Place Making approach that focus on better outcomes for the aged and disabled in the LGA.

Coordinate civic events that bring the community together

36

Page 37: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

11

2.5.2

Lead responsibility Performance measures

2.6.1

Lead responsibility Performance measures

2.6.1.1 Community Place Four Place Making initiatives achieved with the community

2.6.2

Lead responsibility Performance measures

2.6.2.8 Community Place 1. Framework and action plan adopted 2. Conduct 20 Place Making initiatives across the LGA

2.6.2.8 (a) Community Place Project delivered according to approved project plan

2.6.2.9 Community Place, Recreation and Buildings

Attend annual general meeting and additional meetings of committees when held (S355 — Local Government Act)

2.6.2.12 Community Place Project delivered according to approved project plan

Facilitate, support and/or advocate for cultural and heritage education within the community

Work with rural communities to identify, evaluate and address community needs

Create access to community facilities that allow a range of social, health and wellbeing activities

Operational Plan action/s conducted prior to 2016 — 2017

Town Centre Master Plan — Place Making activation at the Hay Street Forecourt, Foreshore and Clarence shoreline

Participate in the rural community networks

Town and village signage installation

Develop and implement a Place Making framework to create vibrant, resilient places that are valued by the community

Encourage use of community facilities through Place Making initiatives

37

Page 38: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

12

2.7.1

Lead responsibility Performance measures

2.7.1.9 Community Place 1. Develop volunteer database by 30 June2. Number of volunteer programs developed

2.8.1

Lead responsibility Performance measures

2.8.1.5 Commercial and Business Services

1. Present quarterly reports to Council 2. Number of performing arts events presented by 30 June3. Number of visual arts events presented by 30 June

2.8.1.6 Community Place 1. Implement the Cultural Plan 2. Engage with key stakeholders and community to deliver cultural activities

2.9.1

Lead responsibility Performance measures

2.9.1.2 Community Place 1. Provide an annual report on activities of the Mayor's Sporting Fund2. Manage distribution of funds on behalf of the Mayor's Sporting Fund Committee3. Mayor's Sporting Fundraiser activities held

2.9.1.3 Recreation and Buildings 1. Conduct policy reviews 2. Quarterly stakeholder communication3. Develop a quarterly audit process for Council's sporting facilities

Encourage and build capacity for community groups to be active, successful, sustainable and to support growth of volunteer base

Provide a range of sporting and recreational opportunities

Continue implementation of Recreation Action Plan — 2015 — 2025

Support, facilitate and advocate for arts and cultural programs that engage the community and deliver a range of high quality performing, visual arts andcultural development services

Promote and coordinate volunteer involvement in Council programs and activities

Continue to implement and monitor the Glasshouse Strategic Plan 2014 — 2017

Work with community groups involved in arts and culture to deliver a wide range of inclusive cultural experiences across the LGA

Manage the Mayor's Sporting Fund to promote and support athletes and sporting people

38

Page 39: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

13

2.9.2

Lead responsibility Performance measures

2.9.2.1 Community Place 1. Update resources including books and equipment2. Provide access to online services including databases and downloadable materials3. Submit State Library reporting4. Provide access and technical support for the Imaginarium — Recording and editing studio

Plan and deliver innovative library services that cater for new technology and growth areas

Provide a range of library programs and lending services across the local government area including books, equipment, technology, online databases and funding opportunities

39

Page 40: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

fOC

US

AR

EAHElPiNg OUR COMMUNitY PROSPER

HOW DO WE gEt tHERE?

3.1 Create opportunities for lifelong learning and skill enhancement with the availability of a broad range of education and training facilities

3.2 Promote and support an increase in business capacity in order to generate ongoing economic growth

3.3 Expand tourism business opportunities and benefits through collaborative planning and promotion

3.4 Maximise innovation and economic competitiveness by providing high quality communication technology throughout the Port Macquarie-Hastings region

3.5 Target and encourage business enterprise by providing favourable business conditions including infrastructure and transport options

WHO Will ASSiSt US?

> Economic Development Steering Group

> Education and training industry

stakeholders

> State Government

> Federal Governments

> Landowners

> Business and industry groups

> Community groups

> Greater Port Macquarie Tourism

Association Board

> Destination NSW

> North Coast Destination Network

WHAt ARE WE tRYiNg tO ACHiEvE?

The Port Macquarie-Hastings region is able to thrive through access to a range of educational, employment and business opportunities.

40

Page 41: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

14

3.1.1

Lead responsibility Performance measures

3.1.1.2 Economic Development Participation in the Hastings Education and Skills Forum and industry working groups

3.2.1

3.2.1.12 Economic Development Recommend advocacy options to EDSG

3.2.1.13 Economic Development Actions delivered and reported to Economic Development Steering Group

3.2.2

Lead responsibility Performance measures

3.2.2.1 Commercial and Business Services

Operating revenue increased by 3% per annum per business unit

3.2.2.3 Commercial and Business Services

Projects delivered according to approved project plan

3.2.2.3 (e) Recreation and Buildings Project delivered according to approved project plan

3.2.2.4 Commercial and Business Services

Program delivered as required

3.2.2.5 Commercial and Business Services

Project delivered according to approved project plan

3.2.2.6 Commercial and Business Services

Services carried out in accordance with legislative and customer requirements

Work collaboratively to advocate for priority industries including agriculture, forestry and fisheries, creative industries, electricity industry, and small and home-based businesses

Develop, manage and maintain Council business units to optimise commercial return and community benefit

Upgrade Port Macquarie Historic Cemetery

Implement equipment improvements and repairs for the laboratory

Increase operating revenue on Council business units the Airport, the Crematorium, the Glasshouse and the Environmental Laboratory

Manage burial and cremation services at Innes Garden Memorial Park, Wauchope, Laurieton and other outlying cemeteries

Advocate for growth in higher education and positive links with local industry

Investigate and plan for expansion of the higher education industry and actively explore and facilitate optimal local partnerships, together with Universitiesand other educational institutions

Identify, support and advocate for effective programs that assist the growth of appropriate business and industry

Undertake Glasshouse back of house maintenance including lift repairs, plant and equipment

Carry out improvement and expansion works at Innes Garden Memorial Park, Wauchope and Laurieton cemeteries

Implement industry action plans for manufacturing, construction, and transport and warehousing industries

41

Page 42: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

15

3.2.3

Lead responsibility Performance measures

3.2.3.1 Strategic Land Use Planning

Report to Council following exhibition of draft LEP and DCP provisions by 31 December

3.2.4

Lead responsibility Performance measures

3.2.4.1 Commercial and Business Services

All commercial and community leases current as of 30 June

3.2.4.2 Commercial and Business Services

Projects delivered according to approved project plan

3.2.5

Lead responsibility Performance measures

3.2.5.1 Commercial and Business Services

Business plan actions delivered by 30 June

3.2.6

Lead responsibility Performance measures

3.2.6.1 Strategic Land Use Planning

Report to Council by December 2016

Manage statutory property functions including land acquisitions

Continue to implement and monitor the property portfolio business plan

Appropriately develop, manage and maintain Council’s property including property sales, acquisitions, road closures, land development and management ofcommunity and commercial leases

Optimise the commercial focus on Council’s property portfolio to deliver improved returns to Council and the community

Prepare LEP amendments to facilitate development in the Major Innes Road/Charles Sturt University Precinct and DCP amendments for the Innes Peninsula, including the Port Macquarie Hospital Precinct

Optimise the use of appropriately zoned land

Manage Council's community and commercial leases for the most appropriate return to Council and the community

Prepare Local Environmental Plan (LEP) and Development Control Plan (DCP) amendments in relation to a business park near Port Macquarie Airport

Facilitate growth in retail and commercial business through the provision of appropriately zoned land that meets the needs of sustainable business

42

Page 43: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

16

3.3.1

Lead responsibility Performance measures

3.3.1.1 Economic Development 1. Implement the Major Events Strategic Action Plan for 2016 — 2017 2. 5% increase in the visitor nights associated with major events annually3. Distribute event development sponsorship funding according to adopted guidelines

3.3.2

Lead responsibility Performance measures

3.3.2.1 Economic Development 1. Maintain No 1 ranking for North Coast NSW2. Increase total overnight visitor expenditure (four year annual update) by 7.1% per annum, in accordance with Destination NSW target to double overnight visitor economy

3.3.2

Lead responsibility Performance measures

3.3.2.2 Economic Development Develop, update and distribute marketing collateral for specific target markets

3.4.1

Lead responsibility Performance measures

3.4.1.1 Economic Development Implement 2016 — 2017 actions from the Digital Strategy

Implement and support innovative and effective strategies and partnerships to position Greater Port Macquarie as a distinct and competitive destinationthat guides market development, investment and infrastructure in public and private sectors (cont.)

Maximise, support, facilitate and advocate for major events and conferences to ensure ongoing positive economic and tourism growth

Maximise the economic impact of major events

Implement and support innovative and effective strategies and partnerships to position Greater Port Macquarie as a distinct and competitive destinationthat guides market development, investment and infrastructure in public and private sectors

Advocate and lobby government for implementation of the National Broadband Network as soon as possible

Implement the Greater Port Macquarie Destination Management Plan to grow our visitor economy

Advocate for regional growth by promoting the local government area (LGA) as a great place to live, learn, work, play and invest

Maximise use of current technologies and future opportunities for local businesses and industry by implementing the Digital Strategy

43

Page 44: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

17

3.5.1

Lead responsibility Performance measures

3.5.1.1 Commercial and Business Services

1. Master plan actions delivered by 30 June2. Projects delivered according to approved project plan

3.5.1.2 Commercial and Business Services

1. Increase in RPT airline aircraft movements compared to previous year2. Increase in passenger numbers compared to previous year

3.5.2

Lead responsibility Performance measures

3.5.3

Lead responsibility Performance measures

3.5.4

Lead responsibility Performance measures

3.5.5

Lead responsibility Performance measures

Operational Plan action/s conducted prior to 2016 — 2017

Operational Plan action/s conducted prior to 2016 — 2017

Operational Plan action/s conducted prior to 2016 — 2017

Operational Plan action/s conducted prior to 2016 — 2017

Investigate options for the future management and ownership of the Port Macquarie Airport

Advocate for a range of high quality, safe and competitive transport services

Develop partnerships with local and regional business networks to assist in maintaining existing businesses and industry in the region

Develop, manage and maintain Port Macquarie Airport as a key component of the regional transport network and continue to grow the airport’scontribution to the regional economy

Continue to implement and monitor the Port Macquarie Airport Master Plan including development of the Airport Business Hub and airside and landside airport improvements

Support, facilitate and advocate for regular public transport (RPT) airline services at Port Macquarie Airport

Support and encourage continuous improvement and implementation of programs designed to support the development of all businesses and industry inpartnership with the chambers of commerce and other business networks

44

Page 45: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

fOC

US

AR

EAlOOkiNg AftER OUR ENviRONMENt

HOW DO WE gEt tHERE?

4.1 Protect and restore natural areas4.2 Ensure service infrastructure maximises efficiency and

limits environmental impact4.3 Implement total water cycle management practices4.4 Continue to improve waste collection and recycling

practices4.5 Provide community access and opportunities to enjoy

our natural environment4.6 Create a culture that supports and invests in

renewable energy4.7 Increase awareness of and plan for the preservation

of local flora and fauna4.8 Plan and take action to minimise impact of natural

events and climate change4.9 Manage development outcomes to minimise the

impact on the natural environment

WHO Will ASSiSt US?

> State Government

> Koala Preservation Society Landowners

> NSW Government Independent

> Chair Community interest groups

> General public

WHAt ARE WE tRYiNg tO ACHiEvE?

We understand and manage the impact that the community has on the natural environment. We protect the environment now and into the future.

45

Page 46: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

18

4.1.1

Lead responsibility Performance measures

4.1.1.1 Environmental Services Annual invasive species (weeds) targets met including:1. 240ha land treated for invasive weeds2. 600km weed dispersal routes treated3. 20% of all plant nurseries in the local government area (LGA) inspected for invasive weeds4. 300 properties inspected for invasive weeds

4.1.1.2 Environmental Services Feral animal control undertaken in accordance with approved control plans on five sites during the year

4.1.1.3 Environmental Services A minimum of 70 km (lineal) control undertaken

4.1.1.4 Environmental Services 600 ha area of bush regeneration undertaken

4.2.1

Lead responsibility Performance measures

4.3.1

Lead responsibility Performance measures

4.3.1.1 Water and Sewer 100% compliance with EPA licence effluent quality conditions

4.3.2

Lead responsibility Performance measures

4.3.2.1 Water and Sewer 1. Nil reportable incidents in accordance with Reclaimed Water Quality Plan requirements2. 100% compliance with verification monitoring programs and reclaimed water quality targets

Incorporate efficiency and environmental impact mitigation into project planning processes

Operate the sewerage system to maximum efficiency to ensure that effluent released into the environment meets Environment Protection Authority (EPA) licence conditions

Increase availability and community awareness of reclaimed water and reused effluent

Operational Plan action/s conducted prior to 2016 — 2017

Undertake the weed management program according to the Mid North Coast Invasive Plant Species Strategy 2012, working in partnership with community groups such as Landcare

Control feral animals on Council-controlled land

Implement various riparian restoration works

In collaboration with community groups, such as Landcare, implement the Bushland Regeneration Program

Implement and advocate a range of proactive programs for the environmental management of lands within the local government area

Provide reclaimed water that is fit for purpose and ensures public health and safety

Meet effluent quality requirements of environmental protection licences

46

Page 47: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

19

4.3.3

Lead responsibility Performance measures

4.3.4

Lead responsibility Performance measures

4.4.1

Lead responsibility Performance measures

4.4.1.3 Environmental Services Education program delivered by 30 June

4.4.1.5

4.4.1.6 Infrastructure Delivery, Environmental Services

Project delivered according to approved project plan

4.4.1.9 Environmental Services Project delivered according to approved project plan

4.4.2

Lead responsibility Performance measures

Incorporate integrated water management and water-sensitive urban design principles into new development areas

Adopt water conservation practices that maintain potable water consumption below state benchmark levels

Operational Plan action/s conducted prior to 2016 — 2017

Reduce waste to landfill, utilising appropriate education, facilities and strategies

Operational Plan action/s conducted prior to 2016-2017

Deliver a resident, commercial and industrial education program to encourage source separation of waste

Construct and manage waste management facilities including:

Participate in regional cooperation for effective waste management and resource recovery at the strategic and operational level

Construct Kew Transfer Station (multi-year project)

Kingfisher Waste Depot — development application and designs

Operational Plan action/s conducted prior to 2016-2017

47

Page 48: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

20

4.5.1

Lead responsibility Performance measures

4.5.1.3 Implement the Bushland Open Space Strategy Recreation and Buildings Project delivered according to approved project plan

4.6.1

Lead responsibility Performance measures

4.7.1

Lead responsibility Performance measures

4.7.1.1 Strategic Land Use Planning

Report koala planning outcomes to Council by 31 March

4.7.1.2 Environmental Services Draft strategy adopted by 30 June

4.7.1.3 Recreation and Buildings 1. Investigations undertaken in relation to all reported illegal tree works2. Educational material and delivery program developed and implemented 3. Advice provided in accordance with service standards and industry best practice

4.8.1

Lead responsibility Performance measures

4.8.1.2 (b) Environmental Services Project delivered according to approved project plan

4.8.1.5 Commence review of Hastings River Flood Study for climate change impacts Environmental Services Review commenced by 30 June

4.8.1.7 Environmental Services Project delivered according to approved project plan Continue updating the Wrights and Yarranabee Creeks Flood Study to include urban drainage systems and link to flood mitigation plan

Continue to undertake the landfill gas capture trial project at Cairncross Landfill

Operational Plan action/s conducted prior to 2016 — 2017

Provide and promote new and upgraded paths, facilities and access to parks and bushland/natural resources

Investigate and implement cost effective renewable energy generation for Council assets and promote outcomes to the community

Promote the conservation of key habitats

Carry out relevant studies to determine the likely extent of natural events and the impact of climate change; develop relevant mitigation strategies

Prepare a plan to promote the conservation of key koala habitat for the coastal areas of the Port Macquarie-Hastings local government area

Prepare a draft biodiversity strategy to determine environmental priorities for conservation and restoration

Inform and educate residents, industry and community groups about Council’s tree management requirements within the Port Macquarie-Hastings 2013 development control plan

48

Page 49: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

21

4.9.1

Lead responsibility Performance measures

4.9.1.1 Environmental Services Draft contributions plan for open space adopted by 30 June

4.9.2

Lead responsibility Performance measures

4.9.2.2 Development Assessment

No successful legal appeals relating to process errorsEnsure the Development Assessment Panel operates in accordance with their charter and all applications are accurately determined

Review the Development Contributions Plans

Strategically and financially plan for the infrastructure that will cater for population growth

Undertake transparent and efficient development assessment in accordance with relevant legislation

49

Page 50: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

50

fOC

US

AR

EAPlANNiNg AND PROviDiNg OUR iNfRAStRUCtURE

WHO Will ASSiSt US?

> State Government

> Koala Preservation Society Landowners

> NSW Government Independent

> Chair Community interest groups

> General public

HOW DO WE gEt tHERE?

5.1 Create and maintain an integrated transport system that eases access between population centres and services

5.2 Ensure transport options are safe, functional and meet access needs across the Local Government Area

5.3 Develop and enhance quality open space and recreational facilities

5.4 Plan settlements to accommodate a range of compatible land uses and projected population growth

5.5 Create and maintain public infrastructure that delivers sustainable water, sewer and stormwater services

WHO Will ASSiSt US?

> State Government

> Federal Government

> Landowners

> Business and Industry groups

> Community groups

> External contractors

WHAt ARE WE tRYiNg tO ACHiEvE?

Our population is

supported through

public infrastructure,

land use and

development

strategies that

create a connected,

sustainable

and accessible

community.

Page 51: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

22

5.1.1

Lead responsibility Performance measures

5.1.1.1

5.1.1.1 (a) Infrastructure Delivery Project delivered according to approved project plan

5.1.1.1 (c) Transport and Stormwater Network

Program delivered according to approved ongoing schedule

5.1.1.1 (d) Transport and Stormwater Network

Project delivered according to approved project plan

5.1.1.1. (h) Infrastructure Delivery Project delivered according to approved project plan

5.1.1.1 (k) Infastructure Delivery Project delivered according to approved project plan

5.1.1.1 (n) Infrastructure Delivery Project delivered according to approved project plan

5.1.1.1 (o) Infrastructure Delivery Project delivered according to approved project plan

5.1.1.1 (u) Assets and Systems Project delivered according to approved project plan

5.1.1.1 (y) Transport and Stormwater Network

Project delivered according to approved project plan

5.1.1.1(cc) Infrastructure Delivery Project delivered according to approved project plan

5.1.1.1(dd) Transport and Stormwater Network

Program delivered according to approved project plan

5.1.1.1 (ee) Transport and Stormwater Network

Program delivered according to approved project plan

Lake Road — continuation of detailed design of dual lanes

Works depot relocation — undertake preconstruction/design

Hasting River Drive — Aston Street crossing

Town Centre Master Plan — undertake design/preconstruction of walkway from Town Beach to Kooloonbung Creek

Town Centre Master Plan — undertake design/preconstruction of Town Square

Ocean Drive — undertake preconstruction for duplication of Greenmeadows Drive south to Matthew Flinders Drive

Beechwood Road — undertake preconstruction for upgrades of segments 20, 40 and 50

Beechwood Road — design Stages 5 and 6 of Beechwood Road reconstruction (Riverbreeze to Waugh Street)

Hastings River Drive — Hughes Place to Boundary Road

Undertake design/preconstruction activities on road and transport assets including:

Comboyne Road — undertake design/preconstruction — replace bridge over Hartys Creek Id No. 109

Miscellaneous design works

Plan, investigate, design and construct road and transport assets that address pedestrian, cyclist and vehicular needs

North South Link Road — undertake design/preconstruction

51

Page 52: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

23

5.1.1.3

5.1.1.3 (a) Infrastructure Delivery Project delivered according to approved project plan

5.1.1.3 (d) Infrastructure Delivery Project delivered according to approved project plan

5.1.1.3 (l) Infrastructure Delivery Project delivered according to approved project plan

5.1.1.3 (r) Infrastructure Delivery Project delivered according to approved project plan

5.1.1.3 (w) Infrastructure Delivery Project delivered according to approved project plan

5.1.1.3 (x) Infrastructure Delivery Program delivered according to approved project plan

5.1.1.3 (y) Infrastructure Delivery Program delivered according to approved project plan

5.1.1.3 (z) Infrastructure Delivery Program delivered according to approved project plan

5.1.1.3(aa) Infrastructure Delivery Program delivered according to approved project plan

5.1.1.4

5.1.1.4 (c) Infrastructure Delivery, Transport and Stormwater Network

Project delivered according to approved project plan

5.1.1.4 (d) Transport and Stormwater Network

Project delivered according to approved project plan

5.1.1.4 (e) Community Place Project delivered according to approved project plan

5.1.1.4 (f) Community Place Project delivered according to approved project plan

5.1.1.4 (g) Community Place Project delivered according to approved project plan

Hastings River Drive — undertake continued construction/delivery Gordon Street to Aston Street

Laurieton Town Centre works

Ocean Drive — undertake continued design/construction/delivery — Matthew Flinders Drive to Greenmeadows duplication

Wauchope Town Centre works

Town Centre Master Plan — develop a management plan and undertake works for the entertainment precinct

Construct multiple footpath/cycleway projects throughout the local government area (LGA)

Undertake construction/delivery of roads and transport assets including:

Undertake design/construction/delivery of road and transport assets including:

Albert Street bridge — replace single lane timber bridge with concrete culvert

O'Neills Bridge Batar Creek Road — replace timber bridge with concrete culvert

Houston Mitchell Drive — commence construction of Stages 2 and 3, from new Houston Mitchell Drive/Ocean Drive roundabout west

Beechwood Road — deliver Stage 2 reconstruction from Riverbreeze Drive to Rosewood Road (south of intersection)

Ocean Drive — upgrade from Mountain View Road to Fairwinds Avenue including intersection of Sirius Drive

Comboyne Road — replace Hyndmans Creek Bridge

Ocean Drive — undertake continued construction/delivery — replace Stingray Creek Bridge

Town Centre Master Plan — construct Town Square

52

Page 53: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

24

5.1.1.4 (r) Infrastructure Delivery Project delivered according to approved project plan

5.1.1.4 (v) Transport and Stormwater Network, Infrastructure Delivery

Program delivered according to approved project plan

5.1.1.4 (w) Infrastructure Delivery Program delivered according to approved project plan

5.1.1.4 (x) Transport and Stormwater Network

Program delivered according to approved project plan

5.1.1.4 (y) Transport and Stormwater Network

Program delivered according to approved project plan

5.1.1.4 (z) Transport and Stormwater Network

Program delivered according to approved project plan

5.1.1.4(aa) Transport and Stormwater Network

Program delivered according to approved project plan

5.1.1.4(bb) Transport and Stormwater Network

Program delivered according to approved project plan

5.1.1.4(cc) Transport and Stormwater Network

Program delivered according to approved project plan

5.1.1.4(dd) Transport and Stormwater Network

Program delivered according to approved project plan

5.1.1.4(ee) Transport and Stormwater Network

Program delivered according to approved project plan

5.1.1.4(ff) Transport and Stormwater Network

Program delivered according to approved project planDesign mid-block signal pedestrian crossing on Gordon Street, Port Macquarie

Construction of road safety treatments along Pappinbarra Road from Pipeclay Road to Koree Island Road

Construction of road safety treatments at the intersection of Bridge Street and Gore Street, Port Macquarie

Construction of a roundabout at the intersection of Hill Street and Granite Street, Port Macquarie

Construction of a shared path between Miala Street and Lake Cathie Medical Centre Ocean Drive

Construction of kerb ramps and refuges at multiple intersections in Port Macquarie, Laurieton and Kew

Construction of improved pedestrian amenity, Wauchope Main Street, Stage 1

Construction of road safety treatments at two locations on Bago Road, 650m north of Milligan’s Road and 250m south of Isabel Place

Lake Road — intersection with Blackbutt roundabout multi-year project

Bulli Creek Bridge, Comboyne Road — undertake design and replacement of single lane timber bridge with a two lane concrete bridge

Gordon Street — upgrade Gordon Street to Horton Street to Lake Road to a dual carriageway

Design pedestrian amenity improvements — Kew to Laurieton along Ocean Drive and Bold Street

53

Page 54: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

25

5.1.2

Lead responsibility Performance measures

5.1.2.1 Transport and Stormwater Network

1. Program delivered according to approved schedule2. Develop annual road maintenance report by 30 June

5.1.2.2 Transport and Stormwater Network

1. Program delivered according to approved schedule 2. Develop annual road maintenance report by 30 June

5.1.2.3 Transport and Stormwater Network

1. Program delivered according to approved schedule 2. Develop annual road maintenance report by 30 June

5.1.2.6 Transport and Stormwater Network

1. Program delivered according to approved schedule 2. Develop annual road maintenance report by 30 June

5.2.1

Lead responsibility Performance measures

5.2.1.1 Transport and Stormwater Network

Two major educational programs undertaken by 30 June

5.2.1.4 Transport and Stormwater Network

Project delivered according to approved project plan

5.3.1

Lead responsibility Performance measures

5.3.1.1 Recreation and Buildings Projects delivered according to approved project plans

5.3.1.1 (c) Infrastructure Delivery, Recreation and Buildings

Project delivered according to approved project plan

Implement the 2014 — 2017 Road Safety Action Plan and undertake road safety education and awareness programs identified in the plan

Carry out annual unsealed road maintenance program including resheeting, grading, drainage and vegetation and rural roadside vegetation clearing

Undertake bridges and culverts maintenance and repair program including inspections, monitoring and bridge repair works

Plan and implement traffic and road safety programs and activities addressing pedestrian, cyclist and vehicular needs

Area-wide traffic study (multi-year project)

Carry out annual sealed road network maintenance program including resurfacing, heavy patching, vegetation management, roadside furnishing and drainage

Wayne Richards Park — Stage 3B detailed design and approvals

Undertake design/preconstruction activities of open space, town centres and recreational assets including:

Plan, investigate, design and construct open spaces and recreational facilities

Undertake road resurfacing and rehabilitation works in accordance with the rolling priority program and roads maintenance hierarchy

Develop and implement the annual maintenance and preventative Works Programs for Roads and Transport assets

54

Page 55: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

26

5.3.1.1 (d) Infrastructure Delivery, Recreation and Buildings

Project delivered according to approved project plan

5.3.1.2 Recreation and Buildings, Infrastructure Delivery

Projects delivered according to approved project plans

5.3.1.2 (c) Infrastructure Delivery Project delivered according to approved project plan

5.3.1.2 (h) Infrastructure Delivery Project delivered according to approved project plan

5.3.1.2 (i) Infrastructure Delivery Project delivered according to approved project plan

5.3.1.2 (l) Infrastructure Delivery Project delivered according to approved project plan

5.3.1.3

5.3.1.3 (b) Infrastructure Delivery Project delivered according to approved project plan

5.3.1.4 Recreation and Buildings, Infrastructure Delivery

Projects delivered according to approved project plans

5.3.1.4 (q) Infrastructure Delivery Project completed according to approved project plan

5.3.1.4 (v) Recreation and Buildings Project delivered according to approved project plan

5.3.1.4 (w) Infrastructure Delivery Project delivered according to approved project plan

5.3.1.4 (z) Recreation and Buildings Project delivered according to approved project plan

5.3.1.4 (ab) Recreation and Buildings Project delivered according to approved project plan

5.3.1.4 (ad) Recreation and Buildings Project delivered according to approved project plan

Henry Kendall Reserve — develop leash free dog area

Bonny Hills Reserve — upgrade public amenities as per Master Plan

Port Macquarie Coastal Walk — Master Plan development, repairs and signage installation

Town Green — design and implement Master Plan

Wauchope Swimming Pool — upgrade of 50 m pool (multi-year project)

Continued preconstruction and designs work for the Lake Cathie Bonny Hills Regional Sporting complex

Westport Reserve — upgrade boat ramp Stage 2

Undertake construction and upgrade activities of existing open spaces, town centres and recreational facilities including:

Undertake construction/delivery of open spaces, town centres and recreational assets including:

Googik Track - construct shared walkway/cycleway, Stage 2

Undertake design/construction/delivery of open spaces, town centres and recreational assets including:

Town Beach Reserve — construct public amenities

Flynn's Beach — upgrade sea wall

Port Macquarie Indoor Stadium — upgrade and expansion (multi-year project)

Town Centre Master Plan — undertake landscaping upgrades

55

Page 56: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

27

5.3.2

Lead responsibility Performance measures

5.3.2.1 Recreation and Buildings Program including beach cleaning and playground inspections delivered according to approved maintenance schedules

5.3.2.2 Transport and Stormwater Network

Program delivered according to approved maintenance schedules

5.3.2.3 Recreation and Buildings Deliver projects according to facilities works program

5.3.2

Lead responsibility Performance measures

5.3.2.4 Recreation and Buildings 1. Undertake annual off-season facility maintenance in accordance with approved program2. Oversee the management of Council's public aquatic facilities in accordance with lease obligation checklist

5.3.2.5 Recreation and Buildings 1. Inspections carried out July — September2. Works delivered April — June

5.3.2.6 Recreation and Buildings Replacement delivered according to approved schedule

5.3.2.6 (l) Recreation and Buildings Project delivered according to approved project plan

5.3.2.7 Recreation and Buildings Renewal delivered as per schedule and reported according to seasonal sports

5.3.2.7 (i) Recreation and Buildings Project delivered according to approved project plan

5.3.2.9 Recreation and Buildings Replacement program delivered according to approved project plan

5.3.2.9 (b) Recreation and Buildings Project delivered according to approved project plan

Oxley Oval — provision of floodlighting

Undertake scheduled and reactive maintenance programs of all Council-owned and leased buildings including office furniture replacement

Provide, maintain and manage public aquatic facilities

Kooloonbung Creek Nature Park — replace timber boardwalk

Develop and implement programs for the annual maintenance and operations for open spaces and recreational facilities

Carry out playground equipment replacement program

Deliver recreational walkway replacement program across the LGA

Deliver sporting facility renewal and new asset program across the LGA

Implement maintenance programs for boat ramps, wharves and jetties

Deliver park furniture renewals across the Local Government Area LGA, including donated seats program

Innes Peninsula (Brierley Hill)

Develop and implement programs for the annual maintenance and operations for open spaces and recreational facilities (cont.)

Undertake maintenance program for parks, reserves, sporting fields and beaches

56

Page 57: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

28

5.4.1Lead responsibility Performance measures

5.4.1.1 Strategic Land Use Planning

Report to Council following exhibition of draft strategy by 31 March

5.4.1.4 Strategic Land Use Planning

Draft LEP amendments endorsed after exhibition by Council by 30 June

5.4.2

Lead responsibility Performance measures

5.4.2.1 Strategic Land Use Planning

Report to Council by 30 June

5.4.3

Lead responsibility Performance measures

5.4.3.1 Strategic Land Use Planning

Six monthly progress reports and/or briefings to Council

5.4.3.2 Strategic Land Use Planning

Six monthly progress reports and/or briefings to Council

5.4.3.4 Strategic Land Use Planning

Report to Council following exhibition

5.5.1

Lead responsibility Performance measures

5.5.1.1

5.5.1.1 (d) Water and Sewer Project delivered according to approved project plan

5.5.1.1 (g) Water and Sewer Project delivered according to approved project plan

Undertake ongoing review to the Port Macquarie-Hastings LEP 2011

Plan settlements to accommodate a range of compatible land uses that meet projected population growth for new and existing developments

Preparation of Local Environmental Plan (LEP) and Development Control Plan (DCP) amendments for the South Lindfield urban release area

Preparation, exhibition and review of the draft Port Macquarie-Hastings Urban Growth Management Strategy 2016

O'Brien's Dam rehabilitation works

Wauchope Water Treatment Plant augmentation — augmentation additional treatment capacity

Review planning instruments and strategies to ensure currency and facilitate sustainable development outcomes whilst acknowledging the impact on community affordability

Undertake ongoing review of the Port Macquarie-Hastings DCP 2013

Review the planning framework for decisions regarding land use and development

Review neighbourhood planning for Thrumster (Area 13) including the Thrumster Koala Plan of Management; amend the LEP and DCP accordingly

Undertake preconstruction/design activities for water supply assets including:

Plan, investigate, design and construct water supply assets

Finalise a Structure Plan for the proposed future urban release area to the west of Wauchope

57

Page 58: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

29

5.5.1.1 (i) Water and Sewer Project delivered according to approved project plan

5.5.1.2

5.5.1.2 (a) Water and Sewer Project delivered according to approved project plan

5.5.1.2 (b) Water and Sewer Project delivered according to approved project plan

5.5.1.3

5.5.1.3 (b) Water and Sewer Project delivered according to approved project plan

5.5.1.3 (m) Water and Sewer Project delivered according to approved project plan

5.5.1.3 (o) Water and Sewer Project delivered according to approved project plan

5.5.1

Lead responsibility Performance measures

5.5.1.4 Water and Sewer Project delivered according to approved project plan

5.5.1.4 (b) Water and Sewer Project delivered according to approved project plan

5.5.1.4 (g) Water and Sewer Project delivered according to approved project plan

5.5.1.4 (h) Water and Sewer Project delivered according to approved project plan

5.5.2

Lead responsibility Performance measures

5.5.2.1 Water and Sewer 1. Plant breakdowns are attended to within 24 hours2. Plants are monitored continuously by electronic means

Bago Telemetry Tower — construct 40 m telemetry tower at Bago reservoir site

North Haven to Laurieton trunk main and Stingray Creek Bridge crossing

Kew/Kendall — feasiblility study gas chlorine system (multi-year project)

Port Dam switchgear upgrade

Undertake construction of water supply assets including:

Kendall Booster Water Pump Station — upgrade pump to allow for increased population growth

Installation of new water supply services to residential and business premises — to cater for new development

Undertake design/construction/delivery of water supply assets including water supply future designs

Sancrox Reservoir (to Area 13 — 750 mm) — trunk main construction — multi-year project

Plan, investigate, design and construct water supply assets (cont.)

Undertake construction/delivery of water supply assets including:

Southern Arm trunk main — rolling program to construct southern arm trunk main along Houston Mitchell Drive

Operate and maintain water treatment plants in accordance with adopted maintenance programs and scheme requirements

Develop and implement the annual maintenance and preventative works program for water assets

Ocean Drive Marbuck bypass — connection to Camden Haven trunk main — multi-year project

58

Page 59: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

30

5.5.2.2 Water and Sewer 1. Plant breakdowns are attended to within 24 hours2. Plants are monitored continuously by electronic means

5.5.2.4 Water and Sewer Program delivered according to approved schedule

5.5.3

Lead responsibility Performance measures

5.5.3.1

5.5.3.1 (c) Water and Sewer Project delivered according to approved project plan

5.5.3.1 (e) Infrastructure Delivery, Water and Sewer

Project delivered according to approved project plan

5.5.3.1 (f) Infrastructure Delivery, Water and Sewer

Project delivered according to approved project plan

5.5.3.1 (g) Infrastructure Delivery, Water and Sewer

Project delivered according to approved project plan

5.5.3.1 (j) Water and Sewer Project delivered according to approved project plan

5.5.3.1 (k) Water and Sewer Project delivered according to approved project plan

5.5.3.1 (l) Infrastructure Delivery, Water and Sewer

Project delivered according to approved project plan

Plan, investigate, design and construct sewerage assets

Area 15 (Lakewood/Kew) — sewerage upgrade to provide for future development

Undertake preconstruction/design activities for sewerage assets including Sewerage services future designs

Operate and maintain sewerage treatment plants in accordance with environmental licences, adopted maintenance programs and scheme requirements

Conduct water asset replacement and renewal programs for live water mains, water meters, minor works, pumps, switchboards, flow meters, technical equipment and water quality

Small towns sewerage program — provision of centralised sewerage systems for Comboyne

Port Macquarie Reclaimed Water Treatment Plant upgrade for growth

Small towns sewerage program — provision of centralised sewerage systems for Long Flat

Small towns sewerage program — provision of centralised sewerage systems for Telegraph Point

Thrumster (Area 13) Sewerage Treatment Plant — environmental impact and concept study

Stingray Creek Bridge New Sewer Mains

59

Page 60: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

31

5.5.3

Lead responsibility Performance measures

5.5.3.3

5.5.3.3 (b) Water and Sewer Project delivered according to approved project plan

5.5.3.3 (c) Water and Sewer Project delivered according to approved project plan

5.5.3.3 (d) Water and Sewer Project delivered according to approved project plan

5.5.3.3 (h) Water and Sewer Program delivered according to approved project plan

5.5.3.3 (i) Water and Sewer Program delivered according to approved project plan

5.5.3.3 (j) Water and Sewer Project delivered according to approved project plan

5.5.3.3 (k) Water and Sewer Project delivered according to approved project plan

5.5.3.3 (l) Water and Sewer Project delivered according to approved project plan

5.5.3.4

5.5.3.4 (a) Water and Sewer Project delivered according to approved project plan

5.5.3.4 (c) Water and Sewer Project delivered according to approved project plan

5.5.3.4 (i) Infrastructure Delivery Project delivered according to approved project plan

5.5.3.4 (n) Water and Sewer Program delivered according to approved project plan

Camden Haven upgrade and upsize of mains and pump stations

Thrumster reclaimed water interim supply rising main to Thrumster Reservoir

Thrumster — construct various reclaimed water trunkmains

Oxley Highway — construct reclaimed water interim supply pumping station

Replacement of sewer telemetry and computer hardware (sewer SCADA application) (multi-year project)

Mechanical sewerage treatment plant asset replacement — rolling program of mechanical asset replacement

Undertake design/construction/delivery of sewerage assets including:

Small towns sewerage program — provision of centralised sewerage systems for North Shore

Bonny Hills Sewer Treatment Plant — design and construct ultra-violet system including pumping modifications

Thrumster Reclaimed Water interim supply Oxley Hwy Reservoir (0.5 ML storage)

Port Macquarie Reclaimed Water Treatment Plant — undertake upgrade activities

Port Macquarie Sewer Pump Station 71 and new rising main

Undertake construction/delivery of sewerage assets including:

Plan, investigate, design and construct sewerage assets (cont.)

Port Macquarie Sewerage Treatment Plant — dewater effluent pond 3 to comply with Environmental Protection Agency (EPA) commitments

60

Page 61: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

32

5.5.4

Lead responsibility Performance measures

5.5.4.3 (a) Water and Sewer Project delivered according to approved project plan

5.5.4.4 Water and Sewer Program delivered according to approved schedule

5.5.5

Lead responsibility Performance measures

5.5.5.3 Water and Sewer 1. Main breaks are attended to immediately, residents are notified of potential interruptions and the Customer Service Centre is notified if required2. 100% of complaints/requests reported as Customer Request Management System and dealt with in accordance with the adopted service standard3. Pumping stations and reservoir levels monitored electronically 100% of the time4. For interruptions to service delivery, residents and the Customer Service Centre are notified during next available working hours

5.5.5.4 Water and Sewer 1. Monitoring of seepage from dam structure and pore pressures within dam wall recorded as per ANCOLD recommendations. All readings compiled in graphical form2. Inspections undertaken on dam structures in accordance with ANCOLD recommendations3. Dam safety emergency plan updated annually, annual high accuracy surveys undertaken on dam walls to determine movement

Maintain and operate storage dams in accordance with Australian National Committee On Large Dams (ANCOLD) guidelines

Operate the water supply network to ensure public health and safety

Port Macquarie sewer treatment plant refurbishment program — aerator lagoon

Deliver water and sewerage supply services to ensure public health and safety and environmental protection

Develop and implement the annual maintenance and preventative works program for sewerage assets

Conduct sewer assets replacement and maintenance program for odour control installations, minor extensions, pumps, pipelines, instruments, switchboards and electrical sewerage treatment plant assets

61

Page 62: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

33

5.5.5.5 Water and Sewer 1. Nil reportable incidents relating to the operation of the sewerage network2. 100% of complaints/requests reported as CRMs and dealt with in accordance with the adopted service standard3. Pumping stations monitored electronically 100% of the time4. Trade waste inspections — 100% of defects identified are acted upon

5.5.5.6 Water and Sewer Project delivered according to approved project

5.5.6

Lead responsibility Performance measures

5.5.6.1 Transport and Stormwater Network, Infrastructure Delivery

5.5.6.1 (b) Transport and Stormwater Network

Project delivered according to approved project plan

5.5.6.1 (c) Transport and Stormwater Network

Project delivered according to approved project plan

5.5.6.1 (d) Transport and Stormwater Network

Project delivered according to approved project plan

5.5.6.1 (e) Transport and Stormwater Network

Projects delivered according to approved project planVarious transport and stormwater design works

Plan, investigate, design and construct stormwater assets

Short Street drainage — undertake condition rating and investigations

Undertake preconstruction/design activities for stormwater remediation and new assets

Chemical dosing system upgrade

East Port, Gordon/Owen Streets — investigate and design stormwater drainage

Lake and Jindalee Roads — investigate and design stormwater drainage

Operate the sewerage network to ensure service delivery meets public health and safety requirements

62

Page 63: 2016 - Port Macquarie-Hastings Council · Council’s projected income for 2016–2017 is expected to be $173.3m, which will come from: > rates and annual charges ($86.6m or about

34

5.5.6.3

5.5.6.3 (a) Infrastructure Delivery Project delivered according to approved project plan

5.5.6.3 (b) Infrastructure Delivery Project delivered according to approved project plan

5.5.6.3 (c) Infrastructure Delivery Project delivered according to approved project plan

5.5.6.3 (d) Transport and Stormwater Network

Project delivered according to approved project plan

5.5.6.4

5.5.6.4 (b) Infrastructure Delivery Project delivered according to approved project plan

5.5.7

Lead responsibility Performance measures

5.5.7.1 Transport and Stormwater Network

Program delivered according to approved maintenance schedules

5.5.7.1 (b) Transport and Stormwater Network

Project delivered according to approved project plan

5.5.7.2

5.5.7.2 (a) Transport and Stormwater Network

Project delivered according to approved project plan

5.5.7.2 (b) Transport and Stormwater Network

Project delivered according to approved project plan

5.5.7.2 c) Transport and Stormwater Network

Project delivered according to approved project plan

Conduct canal maintenance activitities including:

Undertake construction/delivery of stormwater assets including:

Open Drain reprofiling — Oleander Avenue to Koala Street

Undertake design/construction/delivery of stormwater assets including:

Broadwater Canal — structural condition assessments

Continue stormwater remediation — Skyline Terrace, Bonny Hills

Continue stormwater remediation — flood remediation Blackbutt Creek, Wauchope

Settlement Shores canals — routine maintenance

Settlement Shores — hydrographic survey and maintenance planning

Continue stormwater remediation — Calwalla Crescent

Wrights Creek — dredge to lower standing water levels and improve capacity

Develop and implement the annual maintenance and preventative works program for stormwater assets

Carry out stormwater maintenance and repairs program including inspections, cleaning, clearing and minor drainage remediation/improvements

Continue stormwater remediation — Batar Creek Road System, Kendall Stage 2

63