Intern Operations Project2012

Derek Waldron

Interiors/ Special ProjectsFoulger-Pratt Contracting, LLC.9600 Blackwell Road, Suite 200Rockville, MD 20850

Page 2: Intern operations project

Greystone Servicing Corp.

• Project Overview• Schedule Updates• Submittal Process• Request For Information• Cost Summary• Jobsite Reports

Page 3: Intern operations project

Greystone Servicing Corp.Project Overview

• Located at Rockville Metro Plaza I• 111 Rockville Pike, Suite 1150

Rockville, Maryland 20850

• Estimated SF 9345• Preconstruction estimated value of $328,400• Project Manager - Patrick Renzi• Superintendent – Gordon MacDonald• Building Engineer – Marty Patterson

Page 4: Intern operations project

Greystone Servicing Corp.

Project Overview

Page 5: Intern operations project

Greystone Servicing Corp.Project Overview- Subcontractors

• Cavalier Fire Protection, Inc. - $4,650• Control Tec - $54,000• Economy Glass of Calvert, Inc. - $28,000• Inspiration Plumbing Company - $9,800• McClary Tile, Inc. - $5,230• MDC Construction - $44,000• Precision Wall Tech, Inc. - $9,300• Specified Woodworking - $12,228• Tyson Floors - $33,699• W & W Electric Co., Inc. - $81,500• Cameron Concrete Scanning, LLC:

Page 6: Intern operations project

Greystone Servicing Corp.Submittals

Preferred Submittal Process

Subcontractors

F.P.C.

Architect

F.P.C.

Page 7: Intern operations project

Greystone Servicing Corp.Schedule

Greystone’s Submittal Process

Greytsone Servicing

Subcontractors

F.P.C.

Architect

F.P.C.

Page 8: Intern operations project

Greystone Servicing Corp.Schedule

Page 9: Intern operations project

Greystone Servicing Corp.Schedule

Page 10: Intern operations project

Greystone Servicing Corp.Schedule

Week 1-2 Week 3-4 Week 5-6 Week 7-8 Week 9-10

Mobilize Mechanical Hang Drywall Install Lighting Fixtures Drop Ceiling Tiles *

Site Make Safe Frame Partitions Install Doors & Frames Plumbing (Ceiling) Paint (2nd Coat)

Salvage & Demo Electrical/ Inspections Install Lighting Fixtures Prime & Paint (1st Coat) Install Glass Partitions

Layout Partitions Install Ceiling Grid * Plumbing (Ceiling) Install Millwork Install Carpet & Trim

Plumbing (Walls) Rework Sprinkler Heads

Hang Drywall

Page 11: Intern operations project

Greystone Servicing Corp.Schedule

Long lead items include:• Carpet• Glass• Light Fixtures

Page 12: Intern operations project

Greystone Servicing Corp.Progress Photos

Page 13: Intern operations project

Greystone Servicing Corp.Request for Information

• Done via email but using same process as submittals

• Problems faced:– Too many people involved– Client’s uncertainty held up some work from being

accomplished– Continuous change

Page 14: Intern operations project

Cost Summary

Page 15: Intern operations project

Cost Summary

Page 16: Intern operations project

Cost Summary

Page 17: Intern operations project

Cost Summary

Page 18: Intern operations project

Cost Summary

Page 19: Intern operations project

Greystone Servicing Corp.Daily Report

Page 20: Intern operations project

Intern Operations Project2012

Thank You!!