29
OMEGAMORGAN MOVING THE SELLEWOOD BRIDGE

2014 CRW - Omega Morgan Rigging Job of the Year

Embed Size (px)

DESCRIPTION

SC&RA’s Rigging Job of the Year designation is one of the most sought after awards within the crane and rigging industry. This year’s competition included 15 companies from 3 countries vying for this honor. This session showcased the three winning entries which include the removal of 10 platforms on a control tower at McCarran International Airport in Las Vegas, Nevada; the movement of the 87-year old Sellwood Bridge in Portland, Oregon, from its permanent concrete supports to temporary steel piers making way for new bridge construction across the Willamette River; and the recovery of the cruise ship Costa Concordia, which was resting on an underwater rock ledge off the coast of Isola Del Giglio in Italy. Check out these presentations! They are a testament to the commitment and ingenuity at the heart of our industry! Under $150,000 - Barnhart Crane & Rigging Between $150,000 - $750,000 - Omega Morgan Over $750,000 - Fagioli

Citation preview

Page 1: 2014 CRW - Omega Morgan Rigging Job of the Year

OMEGAMORGAN

MOVING THE

SELLEWOOD BRIDGE

Page 2: 2014 CRW - Omega Morgan Rigging Job of the Year

Rigging Job of the Year

Page 3: 2014 CRW - Omega Morgan Rigging Job of the Year

Project Overview

• The 87-year old Sellwood Bridge in Portland, Oregon

Weight: 3,400 Tons

Length: 1,100 Feet

• Busiest 2 lane bridge in Oregon, with over 30,000 vehicle crossings per day

Page 4: 2014 CRW - Omega Morgan Rigging Job of the Year

Location

Page 5: 2014 CRW - Omega Morgan Rigging Job of the Year

Location

Page 6: 2014 CRW - Omega Morgan Rigging Job of the Year

Limitations

• The Project was a firm-fixed price bid. According to Multnomah County, the government entity responsible for the bridge, Omega Morgan’s solution saved millions of dollars by reducing up to a year of construction time for the new bridge.

• The Bridge’s Main Contractor (Slayden / Sundt) hired Omega Morgan to relocate the bridge so it could remain open to traffic during the construction of a new $308 million bridge.

• The Bridge’s location provided significant additional challenges given surrounding infrastructure (both public and private.)

• The project required minimal traffic disruption.

Page 7: 2014 CRW - Omega Morgan Rigging Job of the Year

Limitations

Page 8: 2014 CRW - Omega Morgan Rigging Job of the Year

Limitations

Page 9: 2014 CRW - Omega Morgan Rigging Job of the Year

Innovation & Ingenuity

• Innovation & Ingenuity Required: • The Bridge was required to be relocated very specifically 1. East End - Shifted 33 Feet North 2. West End - Shifted 66 Feet North 3. Entire span shifted 2 Feet East

• New techniques demonstrated • Creative Application of Old Techniques • Newly Designed Equipment • Modification to Standard Equipment • Resources Used Economically

Page 10: 2014 CRW - Omega Morgan Rigging Job of the Year

Innovations & Ingenuity

Page 11: 2014 CRW - Omega Morgan Rigging Job of the Year

Innovations & Ingenuity

Page 12: 2014 CRW - Omega Morgan Rigging Job of the Year

Innovations & Ingenuity

Page 13: 2014 CRW - Omega Morgan Rigging Job of the Year

Innovations & Ingenuity

Page 14: 2014 CRW - Omega Morgan Rigging Job of the Year

Engineering & Planning

• Physical Characteristics • 1,100 Feet Long • 3,400 Tons • 87 years old

• Site Characteristics • Intruding surrounding infrastructure • Unstable ground causing existing bents to fail • Critical bridge construction timeline and required minimal traffic

disruption (less than five day shut down) • Winter job schedule; potential for rain, snow or ice

• Job Schedule • Job was completed on time and ahead of schedule (5 days closure

planned, 4 days utilized.)

• Demonstrated Professionalism • Crews worked tirelessly in cooperation with public and private partners

and earned the award for the demolition of the relocated span.

Page 15: 2014 CRW - Omega Morgan Rigging Job of the Year
Page 16: 2014 CRW - Omega Morgan Rigging Job of the Year
Page 17: 2014 CRW - Omega Morgan Rigging Job of the Year
Page 18: 2014 CRW - Omega Morgan Rigging Job of the Year
Page 19: 2014 CRW - Omega Morgan Rigging Job of the Year
Page 20: 2014 CRW - Omega Morgan Rigging Job of the Year
Page 21: 2014 CRW - Omega Morgan Rigging Job of the Year
Page 22: 2014 CRW - Omega Morgan Rigging Job of the Year
Page 23: 2014 CRW - Omega Morgan Rigging Job of the Year
Page 24: 2014 CRW - Omega Morgan Rigging Job of the Year
Page 25: 2014 CRW - Omega Morgan Rigging Job of the Year

-30

-20

-10

0

10

20

30

40

50

60

9:0

0:0

0 A

M

9:5

0:0

0 A

M

10

:40

:00

AM

Bent 18 January 19, 2013

9:00AM – 11:00AM

SG21RAW

SG18RAW

Page 26: 2014 CRW - Omega Morgan Rigging Job of the Year

-40

-20

0

20

40

60

80

100

120 2

:00:0

0 P

M

2:5

0:0

0 P

M

3:4

0:0

0 P

M

Bent 18 January 19, 2013 2:00PM – 4:00PM

SG21RAW

SG18RAW

Page 27: 2014 CRW - Omega Morgan Rigging Job of the Year

Safety • Safety program: • Safety Manager included in planning process and execution

of the job. Complete safety plan required and completed by Multnomah County and Slayden / Sundt.

• Proper use of equipment: • Slide gear set up provided for safe, timely execution of

project.

• Results: • As a result of careful planning and execution, there were

zero recordable injuries on the job.

Page 28: 2014 CRW - Omega Morgan Rigging Job of the Year
Page 29: 2014 CRW - Omega Morgan Rigging Job of the Year