SC&RA’s Rigging Job of the Year designation is one of the most sought after awards within the crane and rigging industry. This year’s competition included 15 companies from 3 countries vying for this honor. This session showcased the three winning entries which include the removal of 10 platforms on a control tower at McCarran International Airport in Las Vegas, Nevada; the movement of the 87-year old Sellwood Bridge in Portland, Oregon, from its permanent concrete supports to temporary steel piers making way for new bridge construction across the Willamette River; and the recovery of the cruise ship Costa Concordia, which was resting on an underwater rock ledge off the coast of Isola Del Giglio in Italy. Check out these presentations! They are a testament to the commitment and ingenuity at the heart of our industry! Under $150,000 - Barnhart Crane & Rigging Between $150,000 - $750,000 - Omega Morgan Over $750,000 - Fagioli
Citation preview
Las Vegas McCarran Air Traffic Control Tower
Platform Removal Archer Western Construction
April 26, 2014
Job Summary
• Lump Sum Price • No safety incidents
– JHA’s, PPE, Fall Protection Plan
• Discovered new innovative uses of existing tools – Moment resistant connection – Control pump integrated into the counterweight – Pump controls modified to operate with remote control
• Detailed planning addressed all aspects of the job – Engineered a plan around all the obstructions – Lead to flawless execution of the work
• Job finished on schedule with a delighted customer
Thank you!
Minds Over Matter