Upload
brett-bridges
View
215
Download
0
Tags:
Embed Size (px)
Citation preview
VELO Upgrade Critical Issues
•Two step upgrade with installation around 2013/2017•Implies a detector which can sustain 5/20/120 fb-1
•Very tight schedule
40 MHz readout implies complete replacement of all modules and considerable modifications to the signal chain• RF foil a major component of the system -> Can we keep it?• Can we keep the cooling interface?
•cooling pipes and the connection to the module integral part of mechanical design•Does the cooling plant need modification?
Institutes keen to be involved include• All current VELO institutes (CERN, Glasgow, L’pool, Nikhef, Syracuse ..)• New institutes – So far Bristol, Edinburgh, Manchester, Warwick 1
Module Irradiation
Operating up to ~120 fb-1 gives severe challenges
Accumulate 1x1014 neqcm-2 per fb-1
Electronics: 5 MRad per fb-1at tip
• Operating voltage will increase• Signal will drop – probably pixels can live with this, not strips• Can pixel chip survive?• Can innermost part be replaced e.g. silicon sensor, pixel tiles?• Thermal implications
Latest studies give new results on thickness/annealing/CCEHave to aim R&D at specific dose and sensor
2
Module Thermal Performance
Represents one of the key challenges
Currently we have a T of 20o to the silicon tip
After 20 fb-1 we run at 60 uA/cm-2 and 7o -> limit of thermal runawayInjection of heat from chips:
Strip design: potentially could be avoided but major design changePixel design: Power injection from the chip directly in fiducial volume: careful
design needed
Many ideas on the table: studies and R&D needed-7 degrees buys factor 2 leakage current-Cooling material is in acceptance-Module must fit within foil-If a lower setpoint is needed ->cooling plant upgrade- Total power probably OK 3
Module Mechanical Constraints
Current RF foil imposes mechanical constraints:
4
Module Mechanical Constraints
Current RF foil imposes mechanical constraints:
5
Module Mechanical Constraints
Current RF foil imposes mechanical constraints:Tiling has to be inventive
In addition:Fixed width to module to fit into RF boxModules must not bend into foil in z (constraint system)Issue linked to cooling solution, kapton readout
6
Module Resolution
Several resolution issues are still on the table• What is required for physics performance?• X0 and will affect IP, P resolution and efficiency• What can we expect for binary/# ADC bits• How to optimise pixel power vs cell size/ADC **** It is Critical to know what we are designing to! **
• Pixel baseline solution is for asymmetric pixels and double sided modules• Currently the strips aimed at 4 um resolution but probably do not achieve this• After irradiation resolution will go binary – a holistic solution must be considered• Innermost pixel plaquette of smaller dimension a possibility (but 2013 very tight for small pixel 40 MHz readout)
Some points to consider
7
FE Electronics and Hybridisation
Dramatic changes for FE Electronics for 40 MHz readoutHowever occupancy remains relatively low: ~3% for strips
Pixel option: Look for a chip from which we can make a derivativee.g. FPIX,MEDIPIX/TIMEPIX
40MHz Front End, and digital peripheryzero suppressed output, coarse digitizationIssues:
EMI pick up in kaptons, Baseline restorationPower, noise toleranceBump bonding, High Speed flex
Strip option: Develop chip together with silicon trackerDiscussions underway for a chip with functionality from
charge amplifier to serialiserIssues: # bits/gain/derandomiser/power/250/130 nm etc.. 8
9
FPIX2
FPIX21 R&D line: FPIX2 evolution (FNAL-Syracuse)
Sparsification and digitization giving good resolution in 1 dimensionCurrent compensation circuit implementedLow noise performance at short peaking times (~60 ns)Fast serial data output (840 Mbps)Tested with protons up to 87 MRad with no degradation in analog peromanceIssues:
• Data push speed• Timing parameters of analog front-end• Match to optimized PIXEL-VELO cell• Migration to a technology different than 0.25 um? impact on analog design, speed, power consumption, radiation hardness
Other R&D lines? Medipix/Timepix2:Synchronous readout to 40 MHz ++ possibleMove to 55 or 30 um square – connect to bump bonding R&DPossible ADC (multiple threshold)Good hopes for radiation hardnessNeed to give our input to the architecture nowTiling very important (dead areas/possible laser cutting..)
TIMEPIX9
Interconnects and Transmission
Special issue for VELO: Getting the signals out of the vacuumDedicated R&D on feedthroughs neededhigh speed copper cablesUse of GBT (interface/speed) to be discussed
CERN standard
down link for TTC and ECS incorporated
10 links of 320 MBits / GBT: we would prefer fewer
Current thinking favours electrical/optical transition outside tank
power and space on hybridNeed a decent input on data sizes and uniformity in time and space
Each “equivalent ASIC” will generate ~5 Gbit/sGives about 1400 links for whole detector. Data volumefor pixels similar.
10
Software studies
Upgrade dedicated software studies urgently neededLook at pattern recognition/ghost rate issuesEvaluate strip and pixel options (vary # modules)Quantify our “back of the envelope” guesstimates(data volumes, ip resolution, layouts…)
A very exciting option which is often mentioned but not yet evaluated
pixels + magnetic field What would this buy us in pattern recognition/resolution?
11
Due Diligence
Big enthusiasm within the group to make the sensor choice pixel based• Practical reasons
• The 40 MHz strip module is very complex and challenging• Synergy with world wide pixel effort • Interest from institutes
• Radiation hardness etc.Essential to start an R&D line in this direction
We also need to convince ourselves, and future reviewers that There is no significant advantage to strip option (keep in mind issues of resolution, material, coverage...) And we must be sure there is no showstopper for pixels
12
R&D plan
Document focussing on demonstrator pixel module already in existence (Syracuse, Liverpool)A more detailed R&D plan is being worked out.
In addition we need independent and parallel R&D lines. Module thermal performance Decide on silicon operating temperature
Design FEA process, validate with prototypesDecide on cooling pipe connection
Development of vacuum feedthroughs, high speed cables and linksSetup readout slicecheck integrity of signals/vacuum performance
R/O architecture and electrical/optical transitionSetup of testbenches and eventually testbeam facilitiesFE chip development lines and bump bondingSoftware infrastructure: layout, performance evaulation+optimisationRadiation hardness of sensors and electronicsHybridisation issues: fast flex, thinning 13
Time line
2013/2017 timeline is extremely tightTo integrate all parts of the projectTo do the necessary turnaround on the testing + QAPlus the detector debugging before physics readiness
We are aware that there is the possibility of a one step upgrade, and this would allow a few more options onto the table
It also has a big implication for the VELO, which is that we have to survive until 2017 (20-25 fb-1)
14
Evaluation of Current detector performance
It may turn out that the current detector plus its replacement has to survive more than the design 5 fb-1
Note that our depletion voltage is currently limited to 500V.
The thermal runaway in the current running condition must be evaluated
VELO replacement is n-in-p which could give an advantage. Also small cooling interface improvements not excluded.
Could we live until 2017 with VELO + VELO replacement?Or is more drastic action needed? Can we reevaluate the annealing policy in light of recent R&D?
15
Blue Sky
Aim is not to build the bestpossible detector. But to builda detector which does the job.
However it is natural that institutespursue some research lines whichfit into their profile and it is not excludedthat these could be integrated:
smaller pixel dimension,diamond, 3dTSV, thinning,RF foil/wires/LN2 cooling...
They can’t stop mefrom dreaming
16
Summary
17
Critical to know what we are designing to:VELO Upgrade Group working on a Requirements document on timescale of 2 months
R&D plan not yet fully available but work is going on and we anticipate a draft within 3 weeks
Timeline is crucial. We will evaluate with respect to the 2013 scenario but also keep in mind the possible changes.