Submittal Requirements:
The owner has requested that we start processing submittals as soon as possible.
All submittals will be submitted by D.G. Granade, Inc. electronically via the owner’s
Web based software, PM Web. Please forward COMPLETE submittals
electronically to [email protected] and
[email protected] and [email protected] as soon as
possible. Hard copies of submittals ARE NOT required. If your submittals include
samples, please forward them to our office at 4420 Business Drive, Shingle
Springs, CA 95682.
Please review Specification Section 013300 – Submittal Procedures. Please pay
particular attention to Paragraph 3.01.E.2 which states in part “…the contractor will
be responsible for the District Representative’s review costs for each re-submittal in
excess of the first resubmittal. These costs will be back charged to the contractor
and will be deducted from progress payments.” This is to inform you that D.G.
Granade, Inc. will be passing on this cost (if incurred) to each applicable
subcontractor. Please submit a complete submittal.
PM WEB software requires that all submittals be submitted by section number, with
only one specification section being submitted per submittal. In other words, if you
have three specification sections in your contract, you will have three separate
submittals. The software will not allow multiple specification sections to be
combined into one submittal. Keep this in mind when preparing/submitting your
submittals. Also, the owner will not review partial submittals. Partial submittals
will be returned without review. If your submittal is rejected, you must
resubmit the entire submittal, not just the part that was rejected.
We plan to have all submittals turned in to the owner by no later than June 30,
2017. Initial start-up subcontractors should submit their submittals by no later than
May 26, 2017.
Please review Items 1 and 2 below. You must comply with this section or your
submittal will be returned without review. Please review your individual specification
section(s) to ensure you submit a complete submittal.
The following information shall be submitted for review in accordance with the
SUBMITTAL PROCEDURES Section (01 33 00):
1. A copy of your specification section with each paragraph check marked
to show specification compliance or marked to show deviations.
a. Mark “NA” for requirements that do not apply, and if the submittal does
not conform to a requirement, explain the exception.
b. A check mark shall denote full compliance with a paragraph as a whole.
c. If deviations from the specification are indicated, and therefore requested
by the Contractor, each deviation shall be underlined and denoted by a
number in the margin to the right of the identified paragraph referenced to
a detailed written explanation for requesting the deviation.
d. The District shall be the final authority for determining acceptability of
requested deviations.
e. The remaining portions of the paragraph not underlined will signify
compliance on the part of the Contractor with the specification.
f. Failure to include a copy of the marked-up specification section,
along with justification(s) for any requested deviations to the
specification requirements, with the submittal shall be sufficient
cause for rejection of the entire submittal with no further
consideration.
2. Equipment Data Forms per Section 01 33 16 – Design Data:
The following information is ONLY for subcontractors that have “equipment” in
their portion of work. If you do not have “equipment” in your portion of work,
please disregard the following paragraph:
Subcontractors will be required to enter Asset Attribute data electronically into the EXCEL based Equipment Data Forms (provided by owner) for all equipment and submit the data forms along with the standard equipment submittal data. Hard copies of the Equipment Data Forms are attached to Volume 3 of the specifications as Appendix C for your review. The owner will provide D.G. Granade, Inc. with electronic files in Excel format for all relevant electronic equipment data forms upon issuance of the Notice to Proceed (NTP). We will then forward them on to you. Subcontractors are responsible for selecting the correct equipment data forms for each discrete piece of equipment and to submit this form with the submittal with all data fields completed. Submittals will not receive final approval without a completed equipment data form, if applicable.
This pertains to ALL submittals: The owner is requiring a cover letter
stating the following: “The product information shown in this submittal is that
proposed to be incorporated with the Heavy Equipment Maintenance
Building, Contract 4343, Project Specification Section ________________, has
been checked and complies in all respects, except as specifically noted in
writing on the submittal and accompanying transmittal, with the requirements
of the contract documents, is a complete submittal, has been coordinated
with all other accepted Submittals, and can be properly installed in the
allocated spaces.” When submitting your submittals, please include (in your cover
letter), the above verbiage. Also include (in your cover letter), a list of the
documents being submitted.
Also, the owner requires that we submit one PDF per submittal section. Please
combine your submittal into one document (with the specification section check
marked and a Table of Contents).
Your submittal should include (in the following
order):
• Subcontractor Cover Letter that includes a list of the documents being submitted. Also, state: “The product information shown in this submittal is that proposed to be incorporated with the Heavy Equipment Maintenance Building, Contract 4343, Project Specification Section ________________, has been checked and complies in all respects, except as specifically noted in writing on the submittal and accompanying transmittal, with the requirements of the contract documents, is a complete submittal, has been coordinated with all other accepted Submittals, and can be properly installed in the allocated spaces.” Sign your cover letter.
• Table of Contents (if your submittal is a large document). If your submittal only contains one or two items, a Table of Contents is not required.
• Equipment Data Form (if your work includes equipment). The equipment data forms are available in Excel format on our website.
• Specification Section with Check Marks. See instructions above on how to check mark a section.
• Your product data, shop drawings, etc.
Finally, attached is a SAMPLE COPY of an approved
submittal for another project. Please use this as a
reference when preparing your submittals.
May 23, 2016 Submittal #26 22 17 To: Peter Durkee RE: Miscellaneous Site Buildings, Contract 4216 8521 Laguna Station Road Elk Grove, CA 95758 Subject: Submittal 26 22 17 Dear Mr. Durkee: List of documents being submitted:
Equipment Data form
Table of Contents
Specification Section 26 22 17
Product Data
Shop Drawings The product information shown in this submittal is that proposed to be incorporated with the Echo Water Miscellaneous Site Buildings, Contract Number 4216, Project Specification Section 26 22 17, has been checked and complies in all respects, except as specifically noted in writing on the submittal and accompanying transmittal, with the requirements of the contract documents, is a complete submittal, has been coordinated with all other accepted Submittals, and can be properly installed in the allocated spaces. Certified by Douglas G. Granade on May 23, 2016. Respectfully,
Douglas G. Granade Douglas G. Granade, President
4420 Business Drive, Shingle Springs, CA 95682 Phone (530) 677-7484 Fax (530) 677-7550 CA LIC#581408
Serving El Dorado County and Surrounding Areas Since 1989 www.dggranade.com
Since 1928 CA State License No. 115427 Member of National Electrical Contractors Association Since 1946
1902 Channel Drive • West Sacramento, California 95691 • Tel (916) 567-1100 • Fax (916) 567-1292 www.collinselectric.com
May 19, 2016 Submittal: 262217 Attention: Doug Granade Reference: Echo Water Site Preparation Project Subject: Submittal 262217 Transformers Dear : Doug CECI has provided product information for Transformers, per specification section 262217. Sincerely,
Denny Kennedy Denny Kennedy Project Manager The product information shown in this Submittal is that proposed to be incorporated with the EchoWater Site Preparation Project, Contract Number 4206, Project Specification Section 26 22 17, has been checked and complies in all respects, except as specifically noted in writing on the Submittal and accompanying transmittal, with the requirements of the Contract Documents, is a Complete Submittal, has been coordinated with all other accepted Submittals, and can be properly installed in the allocated spaces.
Table of Contents Miscellaneous Site Buildings, Contract #4216
8521 Laguna Station Road Elk Grove, CA 95758
Subcontractor: Collins Electrical Company, Inc.
Tab No.
Tag Manufacturer Model No. Description/Section
1
Transformer TFR98E2
Siemens
3F3Y045K4FCD16 – Series H
26 22 17 2.01-2.09
2
Transformer TFR98E14
Siemens
1D1Y050FCTP1 – Series H
26 22 17 2.01-2.09
3
Transformer Anchorage
PROJECT: Misc Site BldgCONTRACT #: 4216ENTERED BY: Collins ElectricAL Company Inc.DATE: 5/13/2016ASSET NAME: PowerASSET CLASS: Transformer
GENERAL ASSET METADATAEQ. TAG #s EQ. TAG #s EQ. TAG #s EQ. TAG #s EQ. TAG #s
Transformer TransformerTFR98E2 TFR98E14
VENDOR: Central Valley Central Valley MANUFACTURER: Siemens SiemensMODEL #: 3F3Y045K4FCD16 - Series H 1D1Y050FCTP1 - Series HSUBMITTAL #: 003-03-05 003-03-05PURCHASE PRICE: LOT PRICE LOT PRICEASSET DESCRIPTION(s): 75kVA Transformer 50kVA Dry Type Transformer
SPECIFIC ASSET METADATA
OTHER DATA
SECTION 26 22 17
LOW-VOLTAGE DRY-TYPE TRANSFORMERS
PART 1 -- GENERAL
1.01 GENERAL REQUIREMENTS
A. SCOPE:
1. This section specifies dry-type transformers rated 600 volts and less used for power distribution, lighting and control purposes.
1.02 REFERENCES
A. REFERENCE STANDARDS: The publications referred to hereinafter form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only. The latest edition of referenced publications in effect at the time of the bid shall govern. In case of conflict between the requirements of this section and the listed references, the requirements of this section shall prevail.
Reference Title ANSI/IEEE C57.12.01
General Requirements for Dry-Type Distribution and Power Transformers
NEMA ST20 Dry-Type Transformers for General Application NEMA ICS-6 Enclosures for Industrial Controls and Systems
B. DEFINITIONS (NOT USED)
1.03 SUBMITTALS
A. The following information shall be submitted for review in accordance with the SUBMITTAL PROCEDURES Section (01 33 00):
1. A copy of this section, with addenda updates, with each paragraph check marked to show specification compliance or marked to show deviations.
2. Manufacturer's product data including catalog number, sound level data, and unit weight.
3. Dimensional outline drawing.
4. Nameplate engraving list.
10/28/2015 Miscellaneous Site Buildings Project 26 22 17 - 1
5. Mounting bolt design calculations in accordance with the COMMON WORK RESULTS FOR ELECTRICAL Section (26 05 00).
1.04 OPERATION AND MAINTENANCE INSTRUCTIONS
A. Submit operation and maintenance (O&M) instructions in accordance with the OPERATION AND MAINTENANCE DATA Section (01 78 23) by submitting a copy of the OPERATION AND MAINTENANCE DATA Section (01 78 23) with each paragraph check marked to show compliance. O&M instructions shall be submitted after all submittals specified above have been returned mark “No Exceptions Taken” or “Make Corrections Noted.” O&M instructions shall reflect the approved materials and equipment.
PART 2 -- PRODUCTS
2.01 GENERAL
A. GENERAL PURPOSE TRANSFORMERS:
1. Transformers rated 15KVA and greater shall be 3 phase with a "K" factor of 4. Three Phase transformers less than 15KVA shall not be acceptable. Transformers shall conform to ANSI/IEEE C57.12.01 and ANSI/UL506. The voltage, frequency, number of phases and KVA rating shall be as shown on the drawings. Transformers shall be limited to a 115 degree C temperature rise. Double-sized neutral terminal shall be provided to handle excessive neutral currents. Transformers shall be Acme Electric #TPNS-533xx-1S series, Eaton Type KT-4 series, or equal.
2.02 INSULATION
A. Transformers 15 KVA and above shall have a Class 220 insulation system in accordance with NEMA ST20.
2.03 COILS
A. Transformer coils shall be copper. Transformer coils 15 KVA and above shall be impregnated with varnish.
2.04 WINDING CONFIGURATION
A. Transformers shall have electrically isolated primary and secondary windings. Primary and secondary winding configurations shall be Delta-wye. Provisions shall be made to permit separate grounding of the neutral conductor and the enclosure.
10/28/2015 Miscellaneous Site Buildings Project 26 22 17 - 2
2.05 TRANSFORMER TAPS
A. Transformers 15 KVA and above shall be provided with two 2-1/2 percent full capacity taps above normal voltage and four 2-1/2 percent full capacity taps below rated voltage on the primary winding.
2.06 TERMINAL COMPARTMENTS
A. Terminal compartments shall be sized to permit termination of cables as shown on the drawings and cable schedule. Terminal connections shall be made in the bottom third of the enclosure. The terminals shall be copper and sized for the cable specified.
2.07 ENCLOSURES
A. Indoor transformers rated greater than 15 KVA shall be provided with drip-proof, ventilated, NEMAICS-6, Type 2 enclosures. Outdoor transformers shall have weatherproof, NEMA ICS-6, Type 3R enclosures.
2.08 NAMEPLATES
A. Nameplates shall meet the requirements of the ELECTRICAL CONTROLS AND RELAYS Section (26 09 16).
2.09 FACTORY TESTING
A. The following standard factory tests shall be performed on all transformers: ratio of all taps, polarity, phase relation, applied potential, induced potential, no-load, and excitation current tests.
PART 3 -- EXECUTION
3.01 GENERAL (NOT USED)
3.02 INSTALLATION
A. LOCATION:
1. Transformers shall be installed a minimum of 6-inches away from the walls and ceiling.
B. CONDUIT ENTRY:
1. Conduit connections shall be made with flexible conduits.
2. Conduits shall enter the transformer in the lower third area of the enclosure to prevent warm air from traveling up the conduit.
10/28/2015 Miscellaneous Site Buildings Project 26 22 17 - 3
Job Name:
Quote #:
Sac Bldgs 1Sac Bldgs 1 with DOE 2016 Xfrsspursx00c_09231501_01_00_O00
Quote Name:
Bid Date: 12/02/2015
Siemens Industry, Inc. (Company) agrees to sell to Purchaser and Purchaser agrees to purchase from theCompany the goods described below. Written quotations are valid for 30 calendar days from price approval dateunless otherwise stated in the quotation. Quotations are subject to change by Siemens Industry, Inc. at any timeupon written notice to Purchaser. Quoted Lead times refer to the manufacturing cycles, in working days, at time ofquotations and are subject to change.
Line #: Qty Description
To: CENTRAL VALLEY ELECTRIC SUPPLY From:4891 24TH ST
Attention:Tel. No.:
USA USASACRAMENTO, CA 95822
Quote Notes:
1200 1 TFR98E2--3F3Y075K4FCD16 - Series HStandard Dry Type, 3 Phase, 75 KVA, 480 Primary Voltage, 208Y/120 SecondaryVoltage, (K4) 50% Non-Linear Load, 6 - 2.5% (2 FCAN 4 FCBN) Taps, 115C,Ventilated, Copper Windings (C), 115C Rise (F), Drip Shield Kit: Provided WithTransformer, Seismic Rated: FLOOR MOUNTED ONLY.Catalog No.: A6X30105200
1300 1 TFR98E14--1D1Y050FCTP1 - Series HStandard Dry Type, 1 Phase, 50 KVA, 480x240 Primary Voltage, 120/240 SecondaryVoltage, 6 - 2.5% (2 FCAN 4 FCBN) Taps, 115C, Ventilated, Copper Windings (C),115C Rise (F).Catalog No.: A6X1080185
Price Policy:
Payment:
Shipping:
Delivery:
Other:
Freight:
Standard quote is valid for 30 days from price approval date.
Per Siemens distributor's terms.
Shipment of goods will be made after receipt of all the following at Company's production facility:(a) Purchase Order / Electronic PO, (b) Technical Information, and if required (c) DrawingApproval.
FOB Shipping Point, unless stated otherwise.
This proposal is subject to credit approval and US government regulation. It is also based on theCompany's interpretation of the plans and specifications and is subject to correction for errors insuch plans or specifications. This document and any other documents specifically referred to asbeing a part hereof constitute the entire agreement on the subject matter and it shall not bemodified except in writing signed by both parties.THIS PROPOSAL IS BASED UPON SIEMENS STANDARD TERMS AND CONDITIONS OFSALE ATTACHED HERETO AND INCLUDED HEREIN. Company hereby objects to any additionalor different terms set forth in Purchaser's request for proposal, specifications, purchase order, orany other document of Purchaser. Acceptance of additional or different terms must be specificallyassented to in writing by Company.NUCLEAR - Buyer represents and warrants that the goods covered by this contract shall not beused in or in connection with a nuclear facility or application. If Buyer is unable to make suchrepresentation and warranty, then Buyer agrees to indemnify and hold harmless Siemens and towaive and require its insurers to waive all right of recovery against Siemens for any damage, loss,destruction, injury or death resulting from a "nuclear incident", as that term is defined in the AtomicEnergy Act of 1954, as amended, whether or not due to Siemens' negligence.
Freight allowed on orders over $1000.00 provided Seller selects the Route Option: BESTRT - BestRoute.
Global Notes:
Proposal
4/18/2016spursx00c_09231501_01_00_O00 1
Since 1928 CA State License No. 115427 Member of National Electrical Contractors Association Since 1946
1902 Channel Drive • West Sacramento, California 95691 • Tel (916) 567-1100 • Fax (916) 567-1292 www.collinselectric.com
Echo Water Site Prep Project 8521 Laguna Station Road
Elk Grove, CA 95758
TAB 1
Spec Section 26 22 17 Tag: Transformer
Seimens TFR98E2
Project Name:Quote #:
Sac Bldgs 1 with DOE 2016 Xfrsspursx00c_09231501_01_00_O00
Engineer:Contractor:Distributor: CENTRAL VALLEY ELECTRIC SUPPLYDate: 04/18/2016
Drawings are for: Approval Record
Tel. No.:Fax No.:
Submitted By:
CONTENTS: 3F3Y075K4FCD16 - Series H
Since 1928 CA State License No. 115427 Member of National Electrical Contractors Association Since 1946
1902 Channel Drive • West Sacramento, California 95691 • Tel (916) 567-1100 • Fax (916) 567-1292 www.collinselectric.com
Echo Water Site Prep Project 8521 Laguna Station Road
Elk Grove, CA 95758
TAB 2
Spec Section 26 22 17 Tag: Transformer
Seimens TFR98E14