22
Quality assurance related to system integration of the VELO detector. Jan Buytaert, CERN On behalf of the VELO collaboration. November 4, 2011 Workshop on Quality issues in current and future silicon detectors. 1

Quality assurance related to system integration of the VELO detector

  • Upload
    sonel

  • View
    44

  • Download
    2

Embed Size (px)

DESCRIPTION

Quality assurance related to system integration of the VELO detector. Jan Buytaert , CERN On behalf of the VELO collaboration. Outline. Quick overview of the VELO detector. QA during module production, burn-in and installation. Further QA during the later stages of system integration. - PowerPoint PPT Presentation

Citation preview

Page 1: Quality assurance  related to  system integration of the VELO detector

Quality assurance related to

system integration of the VELO detector.

Jan Buytaert, CERNOn behalf of the VELO collaboration.

November 4, 2011Workshop on Quality issues in current and

future silicon detectors. 1

Page 2: Quality assurance  related to  system integration of the VELO detector

Outline

Quick overview of the VELO detector. QA during module production, burn-

in and installation. Further QA during the later stages of

system integration. Summary

November 4, 2011Workshop on Quality issues in current and

future silicon detectors. 2

Page 3: Quality assurance  related to  system integration of the VELO detector

VELO Module

November 4, 2011Workshop on Quality issues in current and

future silicon detectors. 3

double-sided symmetric build to balance stresses due to “bi-metallic” effects.

N-on-n sensors (300um). Thermal pyrolitic graphite (400um) analogue read-out asic’s : 2 x 16 Beetle chips

(~18 Watt) Cooling: 2-phase CO2 [silicon tip @ -7° C] 3 layer kapton cable for signals and power.

carbon fibrepaddle

Al cooling block

Carbon fibre (250 um)

-sensor

R-side circuit

-side circuit

R-sensor

TPG core

Cable clamps

Kapton cable

Carbon fibre base

Hybrid

Page 4: Quality assurance  related to  system integration of the VELO detector

One VELO detector half

November 4, 2011Workshop on Quality issues in current and

future silicon detectors. 4

Grounding straps

Carbon fibre constraint

frame

1 metre stainless steel base plate

21 modules2 “P

ile-u

p”

mod

ules

Page 5: Quality assurance  related to  system integration of the VELO detector

Detector vacuum box.

November 4, 2011Workshop on Quality issues in current and

future silicon detectors. 5

… insertion of one half into detector vacuum box

Thin (300 um) Alu shaped foil separates detector from primary LHC beam vacuum.

Detector box pressure < 10-4 mbar

Page 6: Quality assurance  related to  system integration of the VELO detector

Signal electronics.

November 4, 2011Workshop on Quality issues in current and

future silicon detectors. 6

Digitizing board (Tell1) :- 64 channels 10 bit ADC @ 40MHz- signal processing FPGAs [cross-talk, common mode, pedestal subtraction & clustering]

60 m cables:Analogue signal transmission

Repeater boards:- Pre-emphasis circuit for cable transmission.

- Rad-hard power regulators

Page 7: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

7November 4, 2011

Quality assurance during module production, burn-in and installation.

Page 8: Quality assurance  related to  system integration of the VELO detector

Module production, burn-in & installation

November 4, 2011Workshop on Quality issues in current and

future silicon detectors. 8

Module construction@ Liverpool

Transport to CERN

Module “Burn-in”(U.Glasgow)

Installation on base plate

Completed VELO in 10 month

Mechanics produced@NIKHEF

1 module rejected :suspicious evolution of sensor leakage current

Production yields:

- 63% of hybrids (flatness)- 87% of sensors- 0.6% average bad channels

In rugged transport box under N2 atmosphere. As hand luggage by plane.

1 module rejected :Insufficient cooling performance.

Each module was subject to :6 Visual

Inspections,6 Metrologies,7 Electrical Tests,4 Vacuum Tests3 cooling Tests2 thermal cycling

test. ... 100 man-hours per module But we had a long prototyping period before !

Page 9: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

9

QA during production. Extensive QA was done at component level

during production : sensor, pitch adapter, substrates, circuits, bonding, hybrids

November 4, 2011

Detailed reports in :LHCb VELO module production and performance NIMA 596 (2008)25-28) and NIM A 583 (2007) 18-22. Presentation RD07,firenze,2007 by A. Affolder.

Page 10: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

10

QA ‘soft’ tools @ production

Provided up-to-date production status of all modules. Very useful given tight production schedule and complex production

flow ... Gave easy access to test results of every module, e.g. :

http://hep.ph.liv.ac.uk/velodb/velo1/moduledata.php?label=75&modID=28

Has some built-in functionality, e.g. validation of test results and release to next production step.

In-house developed.

Production database :

PA Testing

Silicon Testing

Cable Testing

Thickness Measurem

ents

Metrology (B

efore Population)

Additional M

et/Ship

Electrical Tests after Population

Clean and Inspect

Metrology

Glue r-Side Pitch A

daptors

Glue r-Side C

hips

Fill Glue Pitch A

daptors

Glue Phi-Side Pitch A

daptors

Glue Phi-Side C

hips

Bond Back End r-Side C

hips

Bond B

ack End Phi-Side Chips

Electrical Test on All C

hips

Replace Faulty r-Side Chips

Replace Faulty Phi-Side Chips

Front End Bond r-Side C

hips

Front End Bond Phi-Side C

hips

Electrical Test

Glue sensors

Metrology on full hybrid

Bias B

ond Measure

Bond r-Side

Bond Phi-Side

Laser Test

Attach to Pedestal

Metrology on the Full M

odule

Attach Cables

Full Metrology w

ith Cables

Vacuum Test + Therm

ographs

Final Module M

etrology

Ship

Stage 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31Anthony Affolder 1 1 1 1 1 0 1 1 0 0 0Themis Bowcock 1John Carroll 0 1 0 1 0 0 0Gianluigi Casse 0 0 0 0 0 0 0 0 0 0 0Ashley GreenallTorkjell Huse 1 1 1 1 1 1 1David Hutchroft 1 1 1 1 0David Jones 1 1 1 1 1Mike Lockwood 1 1 1 1Dave Muskett 1 1 1 1 1 1Girish Patel 0 0 1Kurt Rinnert 1Tony Smith 0 1 0 0 0 0 1Geoff Southern 0 1 1 1 1 1 1 1 1 1Peter Sutcliffe 1 1 1Phil Turner 1 1 1 1 1 1 1 1 1Mark Whitley 1 1 1 1 0 1 1Mike Wormald 0 0 0 0 0 0 1 1 0 0 1 1 0 0 0 1 1 0

Total Qualified 3 2 2 2 1 1 2 2 1 2 2 1 2 2 2 2 4 3 3 3 3 4 3 2 3 3 3 2 3 3 3 3 2 3 2

Responsible Person

Phil T

Phil T

Tony S

Tony S

Phil T

Tony S

Geoff S

Mike W

Phil T

Mike W

Mike W

Mike W

Mike W

Mike W

Mike W

Mike W

Tony S

Mike W

Mike W

Mike W

Mike W

Tony S

John C

Torkjell H

Gianluigi C

Mike W

Mike W

Gianluigi C

John C

John C

Tony S

John C

Gianluigi C

John C

List of production and test tasks (34)

List

of p

eopl

e (1

7)

Competency matrix

Allowed efficient planning of a complex productionand ensure competence redundancy.

= primary executor= backup executor= training executor

Competency matrix :

November 4, 2011

Page 11: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

11

QA during module burn-in.

November 4, 2011

Detailed visual inspection under microscope (3hours)

Thermal cycling4 x [-22C/+28C](3h)

Long (24h) power up under vacuum

Monitoring of leakage current and strip noise. Thermal imaging IR camera.

Connector damage caused by cable extraction tool

HV return bond wires crushed by production jig

Mainactivities

Major visual findings

Documented in “LHCb VELO module characterisation and long term quality assurance tests” NIM A 611(2009) 41-51.

Pitch adapter problems

1 module was rejected due to suspicious leakage current evolution.

Burn in system

Page 12: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

12

Further system QA The aim is to assure that all components perform

to expectation when integrated in the system ... Major full system test in SPS beam test. Study of high voltage breakdown in vacuum.

Some failures have appeared at system level Instability of electronic amplifiers Connector reliability problem Unexpected behaviour of the front-end asic. Problem of mechanical clearance of sensor to RF foil

November 4, 2011

Page 13: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

13

Putting all pieces together. 2 test beams in SPS with the

aim of integrating : Multiple modules and final

mechanics. Signal chain : repeater

electronics/long cables/TELL1. Final LHCb DAQ HW and event

building SW. Final LHCb Timing and Fast control

(“ODIN”) Final low and high voltage systems.

(found bug on interlock input of CAEN LV !)

Under vacuum and CO2 cooling . PVSS based configuration software. elog ...

‘Last check’ before installation on LHC.

Large effort, but it proved there was no showstopper towards the final system !

November 4, 2011

Page 14: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

14

QA on software ... This test also produced the

first real data to feed into software :

Alignment Pattern recognition & tracking Vertex finding

It exposed many bugs and was key to tune all the software

November 4, 2011

Small Pb targets.Reconstructed.

Page 15: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

15

Study of HV breakdown in vacuum The expected dependence on

pressure is described by Paschen’s curve :

It was measured on a complete module.

The study was done in air. Measured minimum

breakdown voltage = 370V. The breakdown was likely not on the sensor (looking at strip noise map.)

Fully described in LHCb note 2007-104, 2007.

November 4, 2011

B.p.d

(C+ln(p.d))V breakdown =

B = 365 V/cm/Torr for airP = pressure (Torr)D = distance (cm)C = 1.18 for air

Theoretical curves for parallel plate with separation distance of 0.1mm(green), 1mm(blue), 10mm red.

measuredAllowedOperational region

Page 16: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

16

Electrical Oscillations… The amplifiers on the

repeater boards exhibited unstable behaviour under certain conditions when inserted in their crates.

It was caused by a feedback through a parasitic path (metallic frame and standoff feet).

It was solved by modifying the mechanics (isolated

standoffs) the grounding scheme (additional

interconnections).

November 4, 2011

standoffs isolated

additional interconnection points at repeaters

Page 17: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

17

The usual culprits : connectors

Use of a connector without locking mechanism for the interconnection between the ‘short’ and ‘long’ kapton cables.

The retention force is large, but sometime not sufficient to resist the force from cable torsion.

It has caused partial disconnection in a pile-up detector module (cables with higher torsion). The Velo detector is not affected.

Careful last visual inspection ...

November 4, 2011

Start of lift-off

Page 18: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

18

strips

AD

C R

eado

ut

128 strips

= 1beetle

A Beetle weakness. Very large charge deposits in

multiple channels cause large pedestal shift in all 128 channels of the ASIC

This was accidentally observed in test beam data. (Rare event).

The beetle was specified and tested for large charge deposits in single channel only.

At LHC, these events are 0.1% of the data and can be corrected for by signal processing in FPGA.

This was not detected despite ‘good’ specification and QA...

3 consecutive events (green, red, blue). Red event contains large charge deposit.

Large negative pedestal shift

Very Large charge deposit

November 4, 2011

Page 19: Quality assurance  related to  system integration of the VELO detector

November 4, 2011Workshop on Quality issues in current and

future silicon detectors. 19

Achieving Sensor-foil clearance ...

By design in general, 1mm clearance

Achieved clearance depends on mechanical precision and stability of

the modules, the base plate andthe vacuum box foil.

Everything was tried to stay within the required tolerances ....

Alu foil of vacuum box

Page 20: Quality assurance  related to  system integration of the VELO detector

3D precision surveys

November 4, 2011Workshop on Quality issues in current and

future silicon detectors. 20

Modules: very accurate construction in

x and y (< 60um), less in z, flatness ~200um affected by kapton cable

attachment Expansion with cooling

Module base: combination of slots and

dowel pins define position of modules in y and z

flatness of base defines x of modules

Deformation when installed

RF foil: x and z vary over foil

length depth of slots (x)

critical parameter can flex during venting

0.8 mm

0.1 mm

0.45 mm

Total = 1.35 mm !!0.35mm too much...

Obtained maximal excursions in z

Page 21: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

21

2. Constraint systemFinally decided to add a constraint system to hold hybrids at proper z-location along beam. Penalty of 0.6%<X/X0> on material budget...

In situ verification with a special designed measuring device with dimensions that are 0.5 mm larger than those for a module.A micro-switch beeps if the foil is touched.

Imaged with secondary interaction vertices

November 4, 2011

Precision grooves

Page 22: Quality assurance  related to  system integration of the VELO detector

Workshop on Quality issues in current and future silicon detectors.

22

Summary We had a very intense period (12 month) of

production and installation ... following a long and careful prototyping phase.

Because of the modest production volume, we could afford extreme care and our QA succeeded in eliminating some few non conforming modules.

There will ‘unavoidably’ be some features that escape through the maze of QA and show up during later integration. Luckily these were minor or correctable in our case.

The VELO detector operates fully to the ‘expected quality’ regarding performance, stability and reliability... which is the whole purpose of QA !

November 4, 2011