Cultural Heritage in REGional Cultural Heritage in REGional NETworks NETworks REGNET REGNET Project Management and Coordination

Project Management and Coordination

  • Upload
    baka

  • View
    40

  • Download
    1

Embed Size (px)

DESCRIPTION

Project Management and Coordination. WP 7 - Management. Task 7.1 – Project Management Task 7.2 – Quality Assurance Duration: whole project lifetime. T 7.1 – Description of work. Contract management Reporting Organisation of meetings Participation in project management bodies - PowerPoint PPT Presentation

Citation preview

Page 1: Project Management and Coordination

Cultural Heritage in REGional NETworksCultural Heritage in REGional NETworks

REGNETREGNET

Project Management and Coordination

Page 2: Project Management and Coordination

27 March 2003 REGNET Final Project Review

2

WP 7 - ManagementWP 7 - Management

Task 7.1 – Project Management

Task 7.2 – Quality Assurance

Duration: whole project lifetime

Page 3: Project Management and Coordination

27 March 2003 REGNET Final Project Review

3

T 7.1 – Description of workT 7.1 – Description of work

Contract management

Reporting

Organisation of meetings

Participation in project management bodies

Participation in Cluster Committee (OH-RN)

Moderation and supervision in technical discussion process

Page 4: Project Management and Coordination

27 March 2003 REGNET Final Project Review

4

T 7.1 – Description of workT 7.1 – Description of work

Observation of technical solutions(REGNET compliance)

Observation of design phase

Project presentationD15: Final Report

D16: public web presence

D17: project fact sheet

Internal web presence

Page 5: Project Management and Coordination

27 March 2003 REGNET Final Project Review

5

T 7.1 – Management StructureT 7.1 – Management Structure

PCG – Project Control Group

PMG – Project Management Group

EPMG – Extended Project Management Group

PTG – Project Team Group

Exploitation Committee

User Group

Workpackage/Task Leader

Page 6: Project Management and Coordination

27 March 2003 REGNET Final Project Review

6

Page 7: Project Management and Coordination

27 March 2003 REGNET Final Project Review

7

Page 8: Project Management and Coordination

27 March 2003 REGNET Final Project Review

8

Page 9: Project Management and Coordination

27 March 2003 REGNET Final Project Review

9

Project MeetingsProject Meetings

3 EPMG Meetings

15 PTG Meetings – Technical/Content Group

1 Editorial Board Meeting

4 Cluster Meetings

3 REV, Pre-REV Meetings

Page 10: Project Management and Coordination

27 March 2003 REGNET Final Project Review

10Management Issues Management Issues July 2002 – March 2003July 2002 – March 2003

Reporting (TR3, TR4, TR5, PR3, PR4-draft)

3rd Cost Statement (+ cost shifts)

3rd Project Review

Consortium Agreement (21 partners signed)

Deliverables D6 to D15 (+ 3 studies)

Project Controlling

Page 11: Project Management and Coordination

27 March 2003 REGNET Final Project Review

11

TransitionTransition from development

to production to obtainbusiness value

ConstructionFeature development

GeneralizationHarvesting and reuse

LaunchStrategic program

planning

Technical Project ManagementTechnical Project Management

InceptionProject planning

ElaborationArchitecture reuse, extension,

and validation

Cyclic Projects

Project-based Project-based Architecture Architecture DeploymentDeployment

Page 12: Project Management and Coordination

27 March 2003 REGNET Final Project Review

12

UP Phases: Iterative DevelopmentUP Phases: Iterative Development

WP1 WP2 WP3 WP4

Page 13: Project Management and Coordination

27 March 2003 REGNET Final Project Review

13Technical Project Management Technical Project Management Software Development PlanSoftware Development Plan

Iteration 1Internationalization

Iteration 1

Improvement & broker

Iteration 2Improvement & Integration

09/02

03/03

04/02

01/03

WP4 – T4.2

WP3 – T3.3

D8: REGNET

V2

D10: PublicREGNET

Iteration 2extension

06/02

Feed-back

Page 14: Project Management and Coordination

27 March 2003 REGNET Final Project Review

14

Project Management Coordination of Portal and Graphical User Interface efforts

Quality Assurance: definition and support in the implementation of the REGNET Process Framework & related assets and of Quality Assurance elements and practices

Task 7.2 – Quality Assurance (I)Task 7.2 – Quality Assurance (I)

Page 15: Project Management and Coordination

27 March 2003 REGNET Final Project Review

15

Quality Assurance:Definition and implementation of the REGNET Process Framework (Task preview and planning, Task activity, Q_Gate/Review, Post Mortem) & related assetsQuality Assurance elements

Verification & Validation Internationalisation (i18n) & Localisation (l10n) Configuration & Change Management

Task 7.2 – Quality Assurance (II)Task 7.2 – Quality Assurance (II)