Page 1 of 34 PM PROJECT MANAGEMENT AND QUALITY CONTROL PM A Project Management PM B Subconsultant Coordination PM C Develop and Update the Schedule (Preliminary Engineering and Procurement) PM D Monthly Progress Reports and Invoices PM E Coordination Meetings E.1 Project Kick-off Meeting E.2 Project Management Meetings E.3 Cost Estimating Validation Process E.4 RFQ - Page Turns E.5 RFP - Page Turns E.6 Constructability Reviews PM F Project Setup F.1 Basemap and InRoad files F.2 Document Control and Management PM G Quality Assurance/Quality Control Reviews PM H Public Involvement H.1 Open Houses H.2 Limited Access Hearing PM I Develop the Schedule (Design-Build Phase) PM J Design-Build Estimate J.1 Bid-Based Parametric Construction Cost Estimate J.2 Design-Builder Design and Quality Management Plan Costs J.3 Other Costs PROC PROJECT PROCUREMENT (Request for Qualifications & Request for Proposals - ITP, CH 1, appendices, and forms) PROC A Request for Qualifications PROC B Request for Proposals - Instructions to Proposers PROC C Request for Proposals - CHAPTER 1 General Provisions PROC D Request for Proposals - Appendices PROC E Request for Proposals - Forms 2 PRELIMINARY ENGINEERING & PROJECT PROCUREMENT (Request for Proposals - CH 2) 2.1 General Information 2.1.A NA 2.1.B RFP - Technical Requirements 2.2 Mandatory Standards 2.2.A NA 2.2.B RFP - Technical Requirements 2.3 Vacant DRAFT SR 432 Longview Grade Crossing - Draft Scope of Work

PM PROJECT MANAGEMENT AND QUALITY CONTROL · Page 1 of 34 PM PROJECT MANAGEMENT AND QUALITY CONTROL PM A Project Management PM B Subconsultant Coordination PM C Develop and Update

  • Upload
    lekhue

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

Page 1 of 34

PM PROJECT MANAGEMENT AND QUALITY CONTROL

PM A Project Management

PM B Subconsultant Coordination

PM C Develop and Update the Schedule (Preliminary Engineering and Procurement)

PM D Monthly Progress Reports and Invoices

PM E Coordination Meetings

E.1 Project Kick-off Meeting

E.2 Project Management Meetings

E.3 Cost Estimating Validation Process

E.4 RFQ - Page Turns

E.5 RFP - Page Turns

E.6 Constructability Reviews

PM F Project Setup

F.1 Basemap and InRoad files

F.2 Document Control and Management

PM G Quality Assurance/Quality Control Reviews

PM H Public Involvement

H.1 Open Houses

H.2 Limited Access Hearing

PM I Develop the Schedule (Design-Build Phase)

PM J Design-Build Estimate

J.1 Bid-Based Parametric Construction Cost Estimate

J.2 Design-Builder Design and Quality Management Plan Costs

J.3 Other Costs

PROC PROJECT PROCUREMENT

(Request for Qualifications & Request for Proposals - ITP, CH 1, appendices, and forms)

PROC A Request for Qualifications

PROC B Request for Proposals - Instructions to Proposers

PROC C Request for Proposals - CHAPTER 1 General Provisions

PROC D Request for Proposals - Appendices

PROC E Request for Proposals - Forms

2 PRELIMINARY ENGINEERING & PROJECT PROCUREMENT

(Request for Proposals - CH 2)

2.1 General Information

2.1.A NA

2.1.B RFP - Technical Requirements

2.2 Mandatory Standards

2.2.A NA

2.2.B RFP - Technical Requirements

2.3 Vacant

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 2 of 34

2.4 Vacant

2.5 Survey

2.5.A Preliminary Engineering and Conceptual Plans *

2.5.B RFP - Technical Requirements

2.6 Geotechnical

2.6.A Preliminary Engineering and Conceptual Plans *

2.6.B RFP - Technical Requirements

2.7 Pavement

2.7.A Preliminary Engineering and Conceptual Plans *

2.7.B RFP - Technical Requirements

2.8 Environmental

2.8.A Preliminary Engineering and Conceptual Plans *

2.8.B RFP - Technical Requirements

2.9 Communications

2.9.A NA

2.9.B RFP - Technical Requirements

2.10 Utilities and Relocation Agreements

2.10.A Preliminary Engineering and Conceptual Plans

2.10.B RFP - Technical Requirements

2.11 Roadway

2.11.A Preliminary Engineering and Conceptual Plans

2.11.B RFP - Technical Requirements

2.12 Project Documentation

2.12.A Preliminary Engineering and Conceptual Plans

2.12.B RFP - Technical Requirements

2.13 Bridge and Structures

2.13.A Preliminary Engineering and Conceptual Plans *

2.13.B RFP - Technical Requirements

2.14 Hydraulics

2.14.A Preliminary Engineering and Conceptual Plans

2.14.B RFP - Technical Requirements

2.15 Roadside Restoration

2.15.A Preliminary Engineering and Conceptual Plans *

2.15.B RFP - Technical Requirements

2.16 Illumination

2.16.A Preliminary Engineering and Conceptual Plans

2.16.B RFP - Technical Requirements

2.17 Signal Design

2.16.A Preliminary Engineering and Conceptual Plans

2.16.B RFP - Technical Requirements

2.18 Intelligent Transportation Systems (ITS)

2.18.A Preliminary Engineering and Conceptual Plans

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 3 of 34

2.18.B RFP - Technical Requirements

2.19 Signing

2.19.A Preliminary Engineering and Conceptual Plans

2.19.B RFP - Technical Requirements

2.2 Pavement Marking

2.20.A Preliminary Engineering and Conceptual Plans

2.20.B RFP - Technical Requirements

2.21 Traffic Operations

2.21.A NA

2.21.B RFP - Technical Requirements

2.22 Maintenance of Traffic (MOT)

2.22.A Preliminary Engineering and Conceptual Plans

2.22.B RFP - Technical Requirements

2.23 Railroad

2.23.A Preliminary Engineering and Conceptual Plans

2.23B RFP – Technical Requirements

2.24 Right-of-Way

2.24.A Preliminary Engineering and Conceptual Plans *

2.24.B RFP - Technical Requirements

2.25 Control of Materials

2.25.A NA

2.25.B RFP - Technical Requirements

2.26 Vacant

2.27 Vacant

2.28 Quality Management Plan (QMP)

2.28.A NA

2.28.B RFP - Technical Requirements

2.29 Maintenance During Construction

2.29.A NA

2.29.B RFP - Technical Requirements

* A portion of this SOW will be performed by WSDOT

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 4 of 34

WSDOT Southwest Region

SR432/ Longview Grade Crossing

Design, RFQ, RFP Support

Scope of Work

Project Description

The SR432 / Longview Grade Crossing Project, also known as the Industrial Way/Oregon Way

Intersection Project, (hereinafter referred to as the Project) is a Connecting Washington project

funded by the Washington State Legislature. The purpose of the project is to develop an affordable

long-term roadway solution to improve travel reliability for all vehicles, accommodate current and

future freight truck and passenger vehicle movement, and maintain or improve emergency response

at this critical intersection.

Located in the Longview Industrial Area, the Industrial Way/Oregon Way intersection is a critical

connection of State Route (SR) 432 and SR 433, two Highways of Statewide Significance and part

of the National Highway System, that support significant passenger and freight truck movement.

The intersection generally accommodates the existing number of vehicles using the roadway;

however, the intersection experiences heavy congestion during the PM peak hours with backups

that are longer than the available storage distance for most turn movements. Traffic volumes are

expected to increase 40-50 percent by 2040. Traffic demand at all left turn and some right turn

movements is expected to exceed the capacity of these lanes (LOS F), causing long backups that

exceed their available storage distance, which in turn impacts through traffic movement. The

overall intersection congestion will result in failing conditions (LOS F) where drivers experience

significant backups, waiting two or more signal cycles to pass through the intersection, and an

intersection that is unable to accommodate the number of vehicles traveling to and from the Lewis

and Clark Bridge.

The Washington State Department of Transportation (WSDOT) has a project that will grade

separate the major movements of the Industrial Way/ Oregon Way intersection. The Project will be

delivered using the Design-Build method.

A preferred alternative to improve the existing intersection is being evaluated. This alternative will

be the basis of the Conceptual Plan that will be forwarded through the Preliminary Engineering and

Procurement Phases:

Partial Grade Separated option – this option would be constructed with some movements

elevated and other movements retained on the surface. The new elevated intersection would

accommodate all northbound and southbound turning and through movements, as well as

all eastbound and westbound turning movements. All eastbound and westbound through

movements on SR 432 would occur at the new surface intersection that would be

constructed where the existing intersection is located. Under this option, the Reynold’s

Lead will not be realigned.

Although there is a preferred alternative to improve the existing intersection that will be used as the

basis for the Conceptual Plan, the Technical Requirements shall be developed to allow the

Proposers the flexibility to be creative and innovative in their approach to improve the intersection.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 5 of 34

WSDOT is seeking a CONSULTANT to perform Preliminary Engineering (up to 30% design) in

order to prepare the Basic Configuration, Conceptual Plan, design documentation, estimate and

schedule in support of WSDOT Design-Build procurement documents for the Project.

The CONSULTANT Scope of Work shall also include the development of the Design-Build

procurement documents (the Request for Qualifications (RFQ) and the Request for Proposals

(RFP) including the Instructions to Proposers (ITP), Chapter 1- General Provisions, Chapter 2 –

Technical Requirements, and the Appendices) for the Project.

RFP documents are to be completed to meet an “Issue RFP” date no later than March 31, 2020 for

an anticipated Notice to Proceed to the Design-Builder to start design in July 2020.

Except as noted below, the CONSULTANT shall be responsible for all aspects of Preliminary

Engineering and Procurement Document Development, which include, but are not limited to:

• Project Management and Quality Control

• Public Involvement Support

• Project Schedule (Preliminary Engineering, Procurement, & Design-Build Phases)

• Construction Staging and Constructability Reviews

• Construction Estimate

• Request for Qualifications

• Request for Proposals – Instructions to Proposers, General Provisions, Forms

• Request for Proposals – Preliminary Engineering (up to 30% Design and Conceptual

Plans), Technical Requirements & Appendices

Survey*

Geotechnical *

Pavement *

Environmental *

Communications

Utility Conflicts

Roadway

Project Documentation

Bridge and Structures *

Hydraulics and Drainage

Roadside Restoration *

Illumination

Intelligent Transportation Systems (ITS)

Signing

Pavement Marking

Traffic Operations

Maintenance of Traffic

Right-of-Way *

Control of Materials

Quality Management Plan

Maintenance During Construction

and all other analyses and/or design activities necessary to complete the contract documents.

* a portion of this work will be performed by WSDOT staff. See appropriate chapter in Section

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 6 of 34

2 of this Scope of Work for details.

Assumptions

• The Project will be delivered with the Design-Build method.

• The Project will employ a Practical Design approach, as outlined in the WSDOT Design

Manual, for this Project.

• WSDOT will perform a portion or all of the following services (See appropriate chapter in

Section 2 of this Scope of Work for details):

Survey

Geotechnical Design

Pavement Design

Environmental Permitting

Bridge Design

Right-of-Way Plans

The WSDOT Kelso Area Engineering Office will be active members of the Project team

assisting with Project decisions and direction, providing reviews, attending meetings, and

acting as the conduit between the Project team and WSDOT support groups.

The WSDOT Design-Build Office will perform Procurement activities (such as SOQ and

RFP evaluations and shortlisting/selection of Best Value Proposer, preparing for

construction administration, etc.)

• Complete design to a level (up to 30%) and on a schedule that will allow environmental

documents and permits to be complete, and right-of-way impacts and property acquisitions

to be determined prior to issuing the RFP.

• For all deliverables associated with design reports, analysis, or documentation, the

CONSULTANT shall provide draft deliverables (60% and 90%), respond to a single

consolidated set of comments from WSDOT, and finalize the deliverable.

• WSDOT anticipates that the Project can be constructed entirely within right of way that

WSDOT will acquire along SR 432, SR 433, East Port Way, West Port Way and Oregon

Way .

• Access to the businesses along SR 432, SR 433, East Port Way, West Port way and Oregon

Way shall be maintained, and railroad traffic will not be impeded during construction.

• The CONSULTANT will facilitate the Cost-Risk Assessment.

• The CONSULTANT will facilitate the access hearing.

• WSDOT will provide the CONSULTANT with the Environmental Impact Statement for

this project.

Design Standards and References

The design shall be prepared in accordance with the standard practices of WSDOT. The design

documentation, reports, and design file items shall be prepared in accordance with WSDOT

standards and practices, which includes, but may not limited to, the following reference material

for the Project:

• WSDOT Design Manual M22-01

• WSDOT Highway Surveying Manual M22-97

• WSDOT Bridge Design Manual LRFD M23-50

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 7 of 34

• WSDOT Highway Runoff Manual M31-16

• WSDOT Hydraulics Manual M23-03

• WSDOT Plans Preparation Manual M22-31

• WSDOT Right of Way Manual M26-01

• WSDOT Utilities Manual M22-87

• WSDOT Roadside Manual M25-30

• WSDOT Traffic Manual M51-05

• WSDOT Standard Plans M21-01

• WSDOT Standard Specifications M41-10

• WSDOT Electronic Engineering Data Standards M3028

• WSDOT Environmental Manual M31-11

• WSDOT DRAFT Design-Build Manual

These manuals are a baseline for estimating work efforts. If future revisions to these manuals

necessitate changes to work already completed, WSDOT and the CONSULTANT shall evaluate

changes in scope, and shall initiate a scope change, if appropriate. Work Elements

PM - PROJECT MANAGEMENT AND QUALITY CONTROL

PM A - Project Management

The CONSULTANT Project Manager shall be responsible for internal project management

and communications with WSDOT. The WSDOT Project Engineer will act as the WSDOT

Project Manager for this Project.

The CONSULTANT project manager shall be co-located in the WSDOT Kelso Area

Engineering Office (located at 2400 Talley Way, Kelso, WA) with the Project team one (1)

day a week, at a minimum. Co-location frequency can be subject to revision with the

concurrence of the WSDOT Project Manager depending on Project schedule.

After Notice to Proceed is given, the CONSULTANT shall prepare a Project Management Plan

(PMP) for endorsement by WSDOT.

This Scope of Work describes coordination efforts required between WSDOT, the

CONSULTANT, and the Subconsultants. The WSDOT Kelso Area Engineering Office will be

the point of contact between the CONSULTANT and WSDOT support groups and be involved

in all aspects of the Project. The CONSULTANT shall coordinate with personnel from various

WSDOT offices, including Survey, Geotechnical Division, Materials, Environmental,

Communications, Utilities, Engineering Services, Bridge and Structures Office, Hydraulics,

Traffic, Maintenance, Headquarters Construction Office and Headquarters Design Office over

the course of the Project. The CONSULTANT shall ensure that all WSDOT input and

comments are addressed and incorporated into the deliverables.

WSDOT will provide a draft version of the Risk Matrix to the CONSULTANT as an optional

starting point to develop the Risk Matrix for the Preliminary Engineering and Procurement

Phases of the Project. Reporting of emergent issues, and if necessary, potential changes or

revisions to the Project schedule or cost estimate shall be provided on a regular basis.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 8 of 34

Deliverable(s):

• Project Management Plan.

• Risk Matrix for Preliminary Engineering and Procurement Phases.

PM B - Subconsultant Coordination

The CONSULTANT shall manage their Subconsultants to ensure adherence to the Project scope,

schedule, and budget.

Scope: The CONSULTANT shall provide direction to their Subconsultants and review their work

over the course of the Project. This work element includes attending meetings, communicating

current Project developments, planning work items with the Subconsultants, and performing

Quality Assurance reviews of their work.

Prior to the start of any work, the CONSULTANTS shall confer with their Subconsultants and

the WSDOT Kelso Area Engineering office and support groups. At this time, these groups shall

discuss and agree on expectations, the Subconsultants’ work plan, deliverables, and the QA/QC

review process.

Schedule: The CONSULTANT shall monitor the status of individual work elements and review

monthly Subconsultant progress reports.

Budget: The CONSULTANT shall monitor the Subconsultant’s budgets and costs/invoices on a

monthly basis over the course of the Project.

Subconsultants shall submit changes in overhead schedules and rate tables on an annual basis

through the CONSULTANT to WSDOT for approval.

Deliverable(s):

• Subconsultant monthly invoice and progress report.

• Annual changes to Subconsultant overhead schedules and rate tables.

PM C – Develop and Update the Schedule (Preliminary Engineering and Procurement

Phases) Within ten (10) working days after task order execution, the CONSULTANT shall prepare and

submit to WSDOT a draft critical path method Project schedule (for the Preliminary Engineering and Procurement Phases) utilizing Primavera P6 with the following information:

1. All activities necessary to complete the Project.

2. Planned order of work activities in a logical sequence. 3. Durations of work activities in working days. 4. Activity durations that are reasonable for the intended work.

5. Sufficient detail to evaluate the progress of individual activities on a daily basis. 6. Physical completion of all work within the authorized task order timeframe.

Restraints may be utilized but may not serve to change the logic of the network or the critical path. The schedule shall display, at a minimum, the following information:

1. Contract and Agreement Number and Title.

2. Critical Path. 3. Activity Description.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 9 of 34

4. Milestone Description. 5. Activity Duration.

6. Predecessor Activities. 7. Successor Activities. 8. Early Start and Early Finish for each activity.

9. Total Float and Free Float for each activity. 10. Start and Completion Dates for Preliminary Engineering and for Procurement 11. Procurement Milestones – RFQ Issue Date, SOQ Due Date, Notification of Short-listed

Submitters, RFP Issue Date, ATC Submittal Deadline, Proposal Due Date, Announce Best Value Proposer, and Notice to Proceed

12. Data Date.

A rough preliminary design schedule has been developed by WSDOT and will be provided to

the CONSULTANT to use as an optional starting point for the draft schedule. The

CONSULTANT can choose to make modifications to the WSDOT-provided schedule or

develop an independent schedule. WSDOT will review the CONSULTANT’s draft schedule

and return comments within fifteen (15) working days after receipt. The CONSULTANT shall

respond to WSDOT comments and finalize the schedule within ten (10) working days for

endorsement by the WSDOT Project Manager. The endorsed schedule shall be made the

baseline and be included in the PMP.

Typical procurement milestone timeline requirements are outlined in the Design-Build RFP

and ITP template documents. A procurement schedule template (in Excel) is available on the

WSDOT Design-Build Sharepoint site and can also be utilized to provide a quick outline of the

procurement schedule.

The CONSULTANT shall submit an updated Project schedule on a monthly basis.

The CONSULTANT shall report on the status of the schedule, including items completed

and items remaining, within the monthly progress reports. Deliverable(s):

• Draft and Final Project Schedule in electronic PDF format.

• Updated Project Schedule on a monthly basis in electronic PDF format.

PM D - Monthly Progress Reports and Invoices The CONSULTANT shall submit monthly invoicing and progress report for work performed

that period.

The CONSULTANT shall develop cost projections on a bi-monthly timeframe and propose

corrective actions as needed. Corrective actions could include formal requests for scope of

work and/or budget modifications.

The CONSULTANT shall submit changes in overhead schedules and rate tables on an annual

basis to WSDOT for approval.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 10 of 34

Deliverable(s):

• Monthly invoice and progress report.

• Cost projections that include both CONSULTANT and Subconsultant costs by month

for the Project duration shall be delivered every two months to coincide with WSDOT’s

aging reporting cycle.

• Annual changes to overhead schedules and rate tables.

PM E - Coordination Meetings

E.1 Project Kick-off Meeting

Prior to beginning work, the CONSULTANT shall coordinate with the Project Office to set

up a Project Kick-off Meeting which shall include the CONSULTANT, Subconsultants, and

Project Office and WSDOT support groups. This meeting is an opportunity to discuss and

confirm the Project requirements, scope, timelines, and issues. This meeting will be used to

obtain team endorsement of the PMP and schedule. Deliverable(s):

• Kick-off meeting agenda, invitee list, and meeting materials.

• Draft and Final Meeting Minutes.

E.2 Project Management Meetings

The CONSULTANT shall meet monthly with the WSDOT to ensure timely progress of the

work. Subconsultants and WSDOT support groups shall be attendees as needed. Meetings

will occur monthly and will be in person, or coordinated via conference call and Skype for

Business or similar technology, as mutually agreed.

The CONSULTANT shall schedule, prepare the meeting agenda, facilitate the meeting, and

maintain records for the meeting:

• The meeting agenda shall include the Project status regarding scope, schedule, and

budget. Agenda items shall report on the status of current and upcoming (within the

next three (3) to six (6) months) critical path activities and upcoming milestone

deliverables.

• Meeting notes shall include action items with assignments and deadlines. The

following meeting shall follow up on outstanding action items.

• This meeting will provide an opportunity for WSDOT and the CONSULTANT to

identify and discuss any new issues and to manage risk. Issue logs and risk matrices

shall be updated accordingly.

Deliverable(s):

• Monthly Project Management meetings.

• Meeting agendas, draft and final meeting minutes, issues log, updated Risk Matrix.

E.3 Cost Risk Assessment (CRA)

The objective of the CRA is to reduce risk and to verify or improve upon the conceptual design

and subsequent construction scenarios by reviewing the Conceptual Plan and procurement

documents. Additional elements of focus will be determined during the Prep-Meeting.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 11 of 34

The CRA shall be included as an activity on the Schedule.

The CONSULTANT shall provide a CRA Risk Leader and a Cost Leader who are independent

from the Project Consultant and WSDOT team. The Leaders shall communicate scope and

schedule with the team members, prepare study materials for the CRA team, review project

data prior to the study, lead/facilitate the CRA team in the Risk and Cost Analysis process (Job

Plan). The analysis will consist of a computational Monte-Carlo algorithm, or comparable,

with repeated random sampling of at least 5,000 realizations to produce a probability

distribution.

The CONSULTANT shall organize and participate in a Prep-Meeting between WSDOT and

the CONSULTANT. The purpose of the meeting is to establish the goals and objectives of the

CRA Workshop, determine what information is available for the CRA team, and confirm

technical experts required for the Workshop. Meeting will be in person, or coordinated via

conference call and Skype for Business or similar technology, as mutually agreed.

The CONSULTANT shall organize, participate in and facilitate up to a 3-day CRA Workshop

for the Project. On the last day of the workshop, the CONSULTANT shall conduct a CRA

report-out presentation. WSDOT will identify and invite audience participants for the CRA

report-out presentation.

The CONSULTANT shall write the Draft and Final CRA reports. These reports will be

provided to WSDOT for review and comments.

Assumption(s):

• The CONSULTANT will arrange for and supply all CRA team members.

Deliverable(s):

• Schedule for CRA Workshop.

• Agenda and notes for CRA Prep-Meeting.

• Cost model, graphics, estimates, schedules, and other project data, including project

constraints, for use during the workshop.

• Agenda and invitee list for CRA Study.

• Up to three (3) day CRA Workshop.

• Presentation of Study findings (PowerPoint).

• Draft and Final CRA Report

E.4 RFQ – Page Turns

The CONSULTANT shall coordinate with WSDOT to schedule “page-turn” meetings for

technical reviews of the RFQ fifteen (15) working days after 60% and 90% turn-in. Meetings

will be in person, or coordinated via conference call and Skype for Business or similar

technology, as mutually agreed.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 12 of 34

During the page-turn meeting, the CONSULTANT shall “track-changes” to incorporate

revisions to the text that can be made quickly during the meeting. Otherwise, the

CONSULTANT shall add comments into the document with a short description of the

input/feedback and initials of the person who will follow up to address the input/feedback.

The CONSULTANT shall incorporate and follow up on all page-turn meeting feedback within

two (2) weeks of the page-turn meeting.

Deliverable(s):

• 60% and 90% RFQ Page-Turn Meetings w/ modified document.

• Revisions in response to WSDOT review comments at 60% and 90% reviews.

E.5 RFP – Page Turns

The CONSULTANT shall coordinate with WSDOT to schedule “page-turn” meetings with

Subconsultants and WSDOT support groups for technical reviews of the RFP three (3) weeks

after 60% and 90% turn-in. Meetings will be in person, or coordinated via conference call and

Skype for Business or similar technology, as mutually agreed. Different time slots shall be

scheduled for page-turn meetings to review different sections of the RFP according to

discipline.

The CONSULTANT shall incorporate and follow up on all page-turn meeting feedback within

two (2) weeks of the page-turn meeting.

Deliverable(s):

• 60% and 90% RFP Page-Turn Meetings w/ modified document.

• Revisions in response to WSDOT review comments at 60% and 90% reviews.

E.6 Constructability Reviews

The CONSULTANT shall conduct two (2) meetings with WSDOT for constructability reviews. The constructability review meetings shall occur within six (6) weeks after the Project Kick-off

Meeting and two (2) weeks after the 60% RFP-completion milestones to ensure that the Project Concept Plan and Basic Configuration are constructible and maintainable. Meetings will be in person, or coordinated via conference call and Skype for Business or similar technology, as

mutually agreed.

The CONSULTANT shall facilitate the meeting and lead the discussion of complex

constructability issues including, but not limited to, construction duration, construction staging strategies, worker and public safety including traffic control and access to the Highlands Neighborhood and adjacent businesses, maintenance of Project infrastructure, and potential

construction cost-saving measures.

The CONSULTANT shall coordinate the scheduling of this meeting with WSDOT. WSDOT will identify the WSDOT attendees.

The CONSULTANT shall develop construction staging approach, concepts, and plans, as

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 13 of 34

necessary to aid in the discussion, and shall distribute materials at least one (1) week prior to the meetings to allow time for participants to prepare and review. The CONSULTANT shall

document the meetings and review, resolve, and provide responses to the WSDOT’s review comments. Deliverable(s):

• CONSULTANT shall develop Conceptual construction staging approach, concepts and

plans, as necessary, for the Project.

• Technical information, graphics and plans for the constructability review, meeting notes,

recommendations, and commitments.

• CONSULTANT shall facilitate Constructability reviews with WSDOT.

• Responses to the 60% and 90% RFP-completion review comments and meeting minutes

for the 60% and 90% RFP-completion constructability review meetings.

PM F – Project Setup

F.1 Basemap and InRoad files

WSDOT will provide the CONSULTANT a basemap and InRoads files (Digital Terrain Model

[DTM] and ALG files) that document existing conditions in the field for preliminary

engineering.

WSDOT will provide Records of Survey in the area and existing centerlines of SR 432,

SR433, Oregon Way, East Port Way and West Port Way. WSDOT will also provide the

proposed right-of-way centerline in an InRoads ALG file. The CONSULTANT will provide

the proposed roadway centerlines of SR 432, SR433, Oregon Way, East Port Way and West

Port Way along with the right-of-way footprint.

The CONSULTANT shall utilize Bentley MicroStation Version 8i, Power InRoads Version 8i

and the WSDOT InRoads Feature Code List (Updated 3/21/17). Deliverables shall be

compatible with the WSDOT Plans Preparation Manual and the WSDOT Electronic

Engineering Data Standards Manual. Underlying WSDOT CAE resource files can be found

on the internet WSDOT CAE Support website.

See also Section 2.5 Survey in this Scope of Work.

Deliverable(s):

• Proposed roadway centerlines of SR 432, SR 433, Oregon Way, East Port Way and

West Port Way along with the right-of-way footprint.

F.2 Document Control and Management

Throughout the life of the Project, ProjectWise will be utilized to allow WSDOT, the

CONSULTANT and the SUBCONSULTANTS to manage, share, distribute, and review

documents. The CONSULTANT shall set up the contract file structure for document control

and manage the Project documents in ProjectWise. See also Section PROC of this Project

Scope of Work.

Deliverable(s):

• Contract file structure in ProjectWise.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 14 of 34

PM G - Quality Assurance / Quality Control (QA/QC) Reviews The CONSULTANT shall provide QA/QC reviews for services performed under this Scope of

Work in accordance with an approved CONSULTANT QA/QC plan.

The CONSULTANT shall designate (a) qualified staff member(s) to perform QA/QC reviews on

all deliverables. The reviews shall cover documents, reports, plans, and pertinent information on

an ongoing basis.

The CONSULTANT shall submit a CONSULTANT QA/QC plan for approval by WSDOT that

outlines a review of the assumptions, concepts, production, and presentation of product format

that assures the overall Project objectives are being fulfilled. The Quality Control process shall

address how changes in Project scope, schedule, and budget will be addressed when they are

identified.

WSDOT will provide additional reviews. The CONSULTANT Project Manager shall work with

the WSDOT to coordinate these reviews with the appropriate WSDOT staff members. WSDOT

support groups will be utilized to review and provide direction of pertinent work items, and will

coordinate with the CONSULTANT’s Project Manager and pertinent staff members.

QA/QC reviews of specific work elements are included in respective sections of this Scope of

Work.

Deliverable(s):

• CONSULTANT QA/QC Plan.

PM H – Public Involvement

The CONSULTANT shall prepare a Public Involvement Plan in coordination with the WSDOT

that outlines a process for providing information to and obtaining input from the public about

the Project. The plan will serve as a roadmap during the Preliminary Engineering and

Procurement Phases of the Project for carrying out public involvement with a target audience

consisting of business owners in the Project Area, residents of the Highlands Neighborhood,

School District, and emergency services.

Access to the businesses and local neighborhood streets during construction will be a discussion

item.

WSDOT will develop and update a Project website throughout the Project. The

CONSULTANT shall provide necessary project information to WSDOT that could include, but

is not limited to, displays or folio graphics so they can implement the plan.

The CONSULTANT shall consider public input and feedback received and, with WSDOT

concurrence, incorporate it into the Preliminary Engineering and Procurement documents.

Deliverable(s):

• The Public Involvement Plan shall be no more than five pages.

• Project information in display or graphic format, as needed.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 15 of 34

H.1 Open Houses

The CONSULTANT shall prepare for, facilitate, and attend one (1) Open House to present the

refined preferred alternative. The CONSULTANT shall coordinate the logistics for the open

house including scheduling, location arrangements, multi-media advertisements (mailers, social

media, newspapers), sign-in sheets, comment cards, display boards, handout materials. The

Open House shall be held in Longview, WA. The CONSULTANT shall design a newspaper

advertisement, and provide text for advertisements in coordination with WSDOT. WSDOT

shall approve the newspaper advertisements prior to publication.

The advertisement shall be printed in English and in Spanish. The CONSULTANT shall

provide an English/ Spanish translator in the open houses.

WSDOT, in coordination with the City of Longview (CITY), will be responsible for producing

the advertisements and sending it out to the WSDOT’s local media contacts. The

advertisements will clearly state that these meetings are part of the WSDOT and CITY’s effort

to meet Section 106 public involvement requirements. The CONSULTANT shall provide

open house information to WSDOT so the Project website can be updated.

The CONSULTANT shall schedule a 1-hour open house “dry run” meeting including the

WSDOT and CITY staff members who plan to attend. These meetings will occur

approximately one week prior to the Open House. Drafts of all display and handout materials,

along with information about roles, responsibilities and staffing needs, will be reviewed and

discussed at these meetings.

Assumptionss:

• All print materials shall be printed in English and Spanish.

Deliverables:

• Preparation, facilitation, logistics, print materials, exhibits, for two open house.

• Comment card compilation, summary, responses and distribution to the project team,

WSDOT and CITY for each open house;

• Document public meeting comments and one hard copy and one electronic copy of

documentation;

• Develop a newspaper advertisement for publication in The Daily News;

• Develop, coordinate, produce, and distribute press releases and direct mail notification

for each open house and the access hearing;

• Email WSDOT with information on web site updates; and

• Preparation and facilitation for two 1-hour open house "dry run" meetings.

H.2 Limited Access Hearing

The CONSULTANT shall prepare for, facilitate, and attend a Limited Access Hearing.

The CONSULTANT shall prepare and develop the Limited Access Hearing plans scripts,

exhibits, and reports. The CONSULTANT shall plan to submit up to fifteen (15) iterations of

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 16 of 34

the Access Hearing plans to WSDOT to review its accuracy and consistency. The

CONSULTANT shall prepare an information packet that must be mailed to the abutters other

entities in accordance with the WSDOT Design Manual.

The CONSULTANT shall provide the Hearing facilitator and a court reporter.

The CONSULTANT shall coordinate the logistics of the Limited Access Hearing, including

scheduling, location arrangements, hearing room set-up (such as podium, microphones, chairs),

multi-media advertisements (mailers, social media, newspapers), sign-in sheets, exhibits and

handout materials. The Limited Access Hearing shall be held in Longview, WA. The

CONSULTANT shall design a newspaper advertisement, and provide text for advertisement in

coordination with WSDOT. WSDOT shall approve the newspaper advertisements prior to

publication.

The advertisement shall be printed in English and in Spanish. The CONSULTANT shall

provide the English/ Spanish translator during the hearing.

WSDOT, in coordination with the CITY, will be responsible for producing the advertisements

and sending it out to the WSDOT’s local media contacts. The advertisements will clearly state

that the Limited Access Hearing is part of the WSDOT and CITY’s effort to meet Section 106

public involvement requirements. The CONSULTANT shall provide Limited Access Hearing

information to WSDOT so the Project website can be updated.

The CONSULTANT shall schedule a 1-hour open house “dry run” meeting including the

WSDOT and CITY staff members who plan to attend. These meetings will occur

approximately one week prior to the Limited Access Hearing. Drafts of all display and handout

materials, along with information about roles, responsibilities and staffing needs, will be

reviewed and discussed at these meetings.

Assumptionss:

• All print materials shall be printed in English and Spanish.

Deliverables:

• Up to fifteen (15) iterations of Access Hearing plans and scripts for review of accuracy

and consistency.

• Preparation, facilitation, logistics, print materials, exhibits, for the Hearing.

• Comment card compilation, summary, responses and distribution to the project team,

WSDOT and CITY;

• Document public meeting comments and one hard copy and one electronic copy of

documentation;

• Develop a newspaper advertisement for publication in The Daily News;

• Develop, coordinate, produce, and distribute press releases and direct mail notification

for the Hearing;

• Email WSDOT with information on web site updates; and

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 17 of 34

• Preparation and facilitation for a 1-hour Access Hearing "dry run" meeting.

PM I - Develop the Schedule (Design-Build Phase)

The CONSULTANT shall prepare and submit to WSDOT a critical path method Project

schedule (for the Design-Build Phase) utilizing Primavera P6 with the following information:

1. All activities necessary to complete the Project. Activities shall be grouped under

Design or Construction, as applicable.

2. Planned order of work activities in a logical sequence.

3. Durations of work activities in working days.

4. Activity durations that are reasonable for the intended work.

5. Sufficient detail to evaluate the progress of individual activities on a daily basis.

6. Physical completion of all work within the authorized task order timeframe.

Restraints may be utilized but may not serve to change the logic of the network or the critical

path. The schedule shall display, at a minimum, the following information:

1. Contract and Agreement Number and Title.

2. Critical Path.

3. Activity Description.

4. Milestone Description.

5. Activity Duration.

6. Predecessor Activities.

7. Successor Activities.

8. Early Start and Early Finish for each activity.

9. Total Float and Free Float for each activity.

10. Start and Completion Dates for the Design-Build Phase.

11. Design-Build Phase Milestones - Notice to Proceed, 2nd Notice to Proceed if needed for environmental or right-of-way phase, Substantial Completion Operational Completion, Physical Completion, and Project Completion.

The CONSULTANT shall determine activity durations utilizing the procedure outlined in the WSDOT Plans Preparation Manual based on quantities calculated, production rates, schedule, and critical path. The CONSULTANT shall provide backup calculations to support the

durations determined for each activity. “Notes to the Engineer” shall be included in the same binder with the backup calculations to document background information and assumptions made.

Deliverable(s):

• Project schedule at 60%, 90%, and 100% RFP-completion.

• Binder with backup documents.

PM J - Design-Build Estimate

The CONSULTANT shall prepare an Engineer’s Estimate to reflect the expected Design-Build

costs for the Project.

J.1 Bid-Based Parametric Construction Cost Estimate

The CONSULTANT shall base the construction estimate on the Conceptual Plan. For estimation purposes, the CONSULTANT shall break down the lump sum Project construction

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 18 of 34

costs by WSDOT standard bid items whenever possible. The CONSULTANT shall follow guidance provided in the WSDOT Plans Preparation Manual and base costs on bid item history

from recent projects. If a WSDOT standard bid item is not used for the estimate, the CONSULTANT shall make a reasonable estimate of those costs based on experience, supplier/fabricator quotes, or cost manuals. For the discipline areas where preliminary

engineering is not a part of this SOW (see the appropriate section in Chapter 2 Technical

Specifications) and the Conceptual Plan is not defined enough to even develop rough quantities, the CONSULTANT shall make a reasonable scoping-level estimate for those items.

The CONSULTANT shall coordinate with the WSDOT to review the estimate at 60% and 90%

of RFP completion. Reviews should evaluate whether estimates reflect current bidding climate

and trends and adjustments made accordingly.

J.2 Design-Builder Design and Quality Management Plan Costs

The CONSULTANT shall provide a cost estimate for the Design-Builder to design the Project

and deliver Ready for Construction (RFC) Drawings. The CONSULTANT shall also estimate

the Design-Builder’s costs to develop and implement a Quality Management Plan during the

Design-Build Phase of the Project.

J.3 Other Costs

The CONSULTANT shall include in the estimate all other miscellaneous costs that are not

included in J.1 and J.2 including, but not limited to, Washington State Patrol, Environmental

mitigation costs, Partnering, Disputes Review Board, and the Design-Build stipend.

The CONSULTANT shall prepare backup calculations and spreadsheets to illustrate quantities

and prices for each item, as needed. “Notes to the Engineer” shall be included in the same

binder with the backup calculations to document background information or assumptions made.

WSDOT will calculate costs to administer and perform Quality Verification audits of the

Project during the Design-Build Phase. WSDOT will also enter the total Project cost into

EBase.

Deliverable(s):

• Estimate at 60%, 90% and 100% RFP-completion.

• Binder with backup documents.

PROC - PROJECT PROCUREMENT (Request for Qualifications & Request for

Proposals – Instructions to Proposers, CHAPTER 1 General Provisions, Appendices, and

Forms)

The Project will use a two-stage procurement process. The CONSULTANT shall prepare and

complete all Contract procurement documents needed for issuing the RFQ and RFP.

WSDOT will perform all other aspects of the Project Procurement including HQ Contract Ad and

Award Office coordination, meeting with Submitters/Proposers, answering RFQ/RFP questions,

reviewing Alternate Technical Concepts (ATCs), performing evaluations, shortlisting Proposers,

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 19 of 34

and assigning technical credits for use in the Best Value determination. The CONSULTANT may

be requested to assist with technical reviews in support of these efforts.

To develop the RFQ and RFP documents, the CONSULTANT shall provide an individual with

good writing skills who can also act as the primary “gate-keeper” in ProjectWise to ensure

documents are filed correctly and that the latest version of a document is being worked on. The

CONSULTANT shall also manage access into ProjectWise. In addition to document control, this

person shall also merge/assemble the different sections into one final document and shall bookmark

each section of the Table of Contents.

To develop the RFQ and RFP documents, the CONSULTANT shall utilize the most-current

FHWA-approved Design-Build Microsoft Word RFQ, ITP, and RFP templates (available on the

WSDOT Design-Build Program SharePoint site) as a starting point for the Project. The

CONSULTANT shall add project information to the template fill-ins (indicated by asterisks **--

**.) The CONSULTANT shall also make modifications to the templates to reflect, at a minimum,

Project-specific requirements, project size, region practice, and region Design-Build lessons-

learned.

The CONSULTANT shall follow the WSDOT Design-Build Style Guide and make all edits in

Microsoft Word using “track-changes”. The CONSULTANT shall also add comments in the

document that provide the background or justification for each change. The CONSULTANT shall

not “Accept” any changes until the Final version and the Assistant State Construction Engineer has

concurred with all the changes. As the last step prior to “Issue”, the CONSULTANT shall merge

“Accepted” individual sections into one Final document, format the Table of Contents, and save

the file as a pdf.

If new versions of the FHWA-approved documents are released before the Project RFQ/RFP

documents are “Issued” for response by the Submitters/Proposers, the CONSULTANT shall

update all Project documents to reflect the changes unless directed otherwise by WSDOT.

The CONSULTANT shall coordinate reviews of the RFQ and the RFP procurement documents

with WSDOT at 60%, 90%, and Final-completion. See Section E.4 RFQ – Page Turns and E.5

RFP – Page Turns in this Scope of Work.

The 90% procurement documents shall be submitted for review a minimum of ten (10) weeks prior

to the issue date. The CONSULTANT shall respond to, address, and/or revise the documents based

on WSDOT comments for each review.

The Final documents shall be submitted four (4) weeks prior to the issue date.

The CONSULTANT shall assist WSDOT with preparing addenda to the RFQ/RFP documents as

requested.

PROC A - Request for Qualifications

The CONSULTANT shall work with WSDOT to determine the Project Goals and develop the

RFQ documents. The CONSULTANT shall also edit the RFQ forms to reflect the project

information and format the electronic documents to be “fillable” by the Submitters.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 20 of 34

PROC B - Request for Proposals – Instructions to Proposers The CONSULTANT shall work with WSDOT to determine the requirements for the Proposal

content, including but not limited to page limits, goals and evaluation criteria, and technical

credits. The CONSULTANT shall develop the ITP document.

PROC C – Request for Proposals – CHAPTER 1 General Provisions

The CONSULTANT shall work with WSDOT to define the Basic Configuration and develop

RFP – CHAPTER 1 General Provisions section.

WSDOT will establish contract goals for DBE Participation and amounts to assess as

Liquidated Damages for traffic impacts.

PROC D - Request for Proposals – Appendices

Starting with the RFP Appendices for the most recent Design-Build project in the region, the

CONSULTANT shall consult with WSDOT to obtain, assemble, and edit, as needed, all current

and relevant Contract, Basic Configuration, and Reference documents consistent with

specifications and standards across the state or in the Southwest Region. The CONSULTANT

shall review each document with the Project Office and designate them as either Contract, Basic

Configuration, or Reference documents. The CONSULTANT shall incorporate these

documents into the RFP Appendices.

WSDOT will develop several documents that may constitute a portion of the documents the

Consultant shall include in the Appendices for the following disciplines (See appropriate

chapter in Section 2 of this Scope of Work for additional details):

• Survey.

• Geotechnical Design.

• Pavement Design.

• Environmental Permitting.

• Bridge Design.

Deliverable(s):

• 60%, 90% and Final RFP Appendices – Contract, Basic Configuration, and Reference

documents, as applicable.

PROC E - Request for Proposals – Forms

The CONSULTANT shall coordinate with WSDOT to determine the required RFP forms

(Contract Form and the forms included in Appendix A of the ITP). The CONSULTANT shall

edit the RFP forms to reflect the project information and format the electronic documents to be

“fillable” by the Proposers.

The CONSULTANT shall submit all 60%, 90%, and Final documents electronically in

Microsoft Word format (with tracked changes and comments except for the Final) into a

designated folder on the Project document control web site. In addition, the CONSULTANT

shall also submit all Final documents, except for “fillable” forms, electronically in pdf format

for posting to the WSDOT Project Page.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 21 of 34

Deliverable(s):

• 60%, 90%, and Final RFQ documents.

• 60%, 90%, and Final RFP documents.

• Final Excel, Word, and pdf electronic files.

2 – PRELIMINARY ENGINEERING & PROJECT PROCUREMENT (Request for

Proposals – CHAPTER 2 Technical Requirements)

The CONSULTANT shall perform preliminary engineering and prepare the Technical

Requirements (including developing the Basic Configuration, Conceptual Plans (unless noted

otherwise in this Scope of Work), and design documentation) and all Contract procurement

documents needed for issuing the RFP. The CONSULTANT shall be responsible for all aspects of

project development and delivery consistent with a Design-Build contract which include, but are

not limited to, project administration, surveying, basemap development, roadway design,

channelization, geotechnical investigation and analysis, bridge and structure design, hydraulics

analysis and associated design, drainage design, signing design, temporary and permanent

illumination design, traffic control, construction staging, temporary erosion sediment control and

countermeasures, landscaping design, identification of temporary and permanent right of way

needs, identification and resolution of utilities conflicts, support for environmental permitting,

environmental mitigation design, design documentation, cost estimates, specifications and all other

analyses and/or design activities necessary to complete the contract documents for RFP

development.

The CONSULTANT shall coordinate reviews of the RFP procurement documents with WSDOT at

60%, 90%, and Final-completion. See Section E.5 RFP – Page Turns in this Scope of Work.

The 90% procurement documents shall be submitted for review a minimum of twelve (12) weeks

prior to the issue date. The CONSULTANT shall respond to, address, and/or revise the documents

based on WSDOT comments for each review.

The final documents shall be submitted four (4) weeks prior to the issue date.

The CONSULTANT shall use Bentley MicroStation Version 8i to produce the Computer Aided Drafting and Design (CADD) files for any plan sheets created in support of the procurement documents.

The CONSULTANT shall submit all 60%, 90%, and Final documents electronically in Microsoft

Word format (with tracked changes and comments except for the Final) into a designated folder on

the Project document control web site. In addition, the CONSULTANT shall also submit all Final

documents, except for “fillable” forms, electronically in pdf format for posting to the WSDOT

Project Page.

2.1 - General Information

2.1.A Preliminary Engineering and Conceptual Plans - Not Applicable

2.1.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.1 – General Information to reflect the Project technical requirements.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 22 of 34

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.1 – General Information.

2.2 - Mandatory Standards

2.2.A Preliminary Engineering and Conceptual Plans - Not Applicable

2.2.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.2 – Mandatory Standards to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.2 – Mandatory Standards.

2.3 - Vacant

2.4 - Vacant

2.5 - Survey

2.5.A Preliminary Engineering and Conceptual Plans WSDOT will perform surveys of the Project site to advance the preliminary engineering and

procurement for delivery of the Project such as:

• Topographic survey of SR 432, SR 433, and Oregon Way between the SR432/ 433

intersection up to Oregon Way/ Alabama St. intersection, East Port way and West Port

Way.

• Wetlands and Ordinary High Water Mark (OHWM) as delineated by WSDOT crews

(See Section 2.8A Environmental).

• Geotechnical boring and instrumentation locations (up to thirty [30] locations)

• WSDOT monumentation in the roadway and on the right of way, property corners,

fence lines, any physical improvements at the site, utilities above and below ground and

any other features to encompass the Project site to be used in the preliminary design.

• Outer limits of right-of-way acquisition needs (See Section 2.24 Right-of-Way) as

identified by the CONSULTANT that may include, but is not limited to:

Fee title acquisition areas

Permanent Easements

Temporary Construction Easements

Location, extent and type of limited access

Turnback lines

Relinquishment areas

• Key features to be included on the Right-of-Way Plans (See Section 2.24 Right-of-

Way) that may include, but is not limited to:

Mitigation Areas

Stormwater Treatment Areas

City limits

Wells, septic tanks, buildings, railroad tracks, diking district features, major

utility corridors (such as BPA or Gas) all within 100’ of the proposed R/W line.

All survey data collected by the CONSULTANT for this Project shall be in Washington

State Plane South Zone coordinate system.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 23 of 34

Deliverable(s):

• None

2.5.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.5 – Survey to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.5 Survey.

2.6 - Geotechnical

2.6.A Preliminary Engineering and Conceptual Plans

WSDOT will perform geotechnical drilling, field and lab testing, engineering, and seismic

design.

At the start of the work, WSDOT will update the CONSULTANT with an initial overview of

the Project geotechnical conditions based on readily available geotechnical and geologic data

for the Project area. WSDOT will identify geotechnical factors that may have an impact on the

Project.

The CONSULTANT shall coordinate with WSDOT and provide any necessary design

information for WSDOT to plan and conduct the field investigation for the Project including

project site data for wall alignments.

The CONSULTANT shall work with WSDOT to establish due dates for deliverables produced

by both parties for the others use.

WSDOT will write the Geotechnical Baseline Report, Geotechnical Data Report, and

Reference Report. The CONSULTANT shall incorporate these reports into the RFP

Appendices.

Deliverable(s):

• Project site data. • Deliverable schedule.

2.6.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.6 – Geotechnical for the Project.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.6 - Geotechnical.

2.7 - Pavement

2.7.A Preliminary Engineering and Conceptual Plans

WSDOT will core the asphalt within the Project limits to determine existing pavement depths

and condition. WSDOT will also design the permanent roadway pavement section for the

Project; temporary paving sections for staging will be designed by the Design-Builder.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 24 of 34

The CONSULTANT shall coordinate with the WSDOT and provide any necessary design

information for them to plan and conduct the field investigation for the Project.

The CONSULTANT shall work with the WSDOT to establish due dates for deliverables

produced by both parties for the other’s use.

WSDOT will prepare the Project Resurfacing Report for the permanent roadway pavement

section. The CONSULTANT shall incorporate this report into the RFP Appendices.

Deliverable(s):

• Project site data.

• Deliverable schedule.

2.7.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.7 – Pavement to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.7 - Pavement.

2.8 - Environmental

2.8.A Preliminary Engineering and Conceptual Plans WSDOT will be responsible for preparing environmental documentation and obtaining all

environmental permits. The CONSULTANT shall assist WSDOT as needed and provide any

design information necessary to complete the environmental tasks.

WSDOT will be responsible for preparing environmental documentation in conformance with

the National Environmental Policy Act and State Environmental Policy Act. WSDOT will obtain the environmental permits needed for the Project including, but not limited to, the following:

• Section 404 of Clean Water Act - US Army Corps of Engineers.

• Hydraulic Project Approval - Washington Department of Fish and Wildlife

• Cowlitz County Critical Area Ordinance

• National Pollutant Discharge Elimination System (NPDES) – Washington

Department of Ecology

WSDOT will determine the wetland delineation, and other Critical Resource Areas.

The CONSULTANT shall provide assistance to WSDOT by providing data and information

needed for environmental documentation and permits including, but not limited to:

• Written detailed project description narrative,

• Area of Potential Effect (APE),

• Preliminary plans,

• Cut and fill area and earthwork quantities,

• Clearing and grubbing limits, including any potential stormwater facilities, staging,

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 25 of 34

stockpile, or access areas

• Area and quantities of cut and fill within wetlands and wetland buffers,

• Temporary and permanent vegetation impacts (upland and riparian disturbance areas),

• Existing and proposed quantities of impervious surface,

• Details regarding the proposed structure and construction methods,

• Estimated number of working days,

• Construction equipment list,

• Potential staging locations,

• Potential construction access,

• Stormwater treatment details (if required).

The CONSULTANT shall respond to WSDOT’s questions and additional data requests.

The CONSULTANT shall coordinate with WSDOT representatives, as necessary, to identify

probable mitigation needs and include associated Project goals and/or mitigation performance

specifications in the Project Procurement documents, as deemed necessary.

The CONSULTANT shall incorporate the WSDOT-prepared permit documents indicated

above into the RFP Appendices

Deliverable(s):

• Area of Potential Effect (APE).

• Project description with construction methodology for environmental permits.

• Assistance, as needed, with drawings/figures showing proposed impact areas, including

wetland, OHWM and wetland buffer impacts, and other drawings and technical data

needed for environmental documentation and permits.

• Drawings showing probable impacts to Critical Area Resources.

2.8.B RFP – Technical Requirements

WSDOT will write RFP Chapter 2.8 – Environmental for the Project. The CONSULTANT

shall incorporate this version of Chapter 2.8 into the RFP.

2.9 - Communications

2.9.A Preliminary Engineering and Conceptual Plans - Not Applicable

2.9.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.9 – Communications to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.9 Communications.

2.10 - Utilities and Relocation Agreements

2.10.A Preliminary Engineering and Conceptual Plans

The CONSULTANT shall identify utilities that will be impacted by the Project. Known

utilities in the Project area include:

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 26 of 34

• Municipal Water

o City of Longview

• Sanitary Sewer Service

o City of Longview

• Storm Drainage

o City of Longview

o Consolidated Diking Improvement District No. 1

o WSDOT

• Telephone, Fiber Optics and Cable Television

o Century Link

o Comcast

o NoaNet

o Sprint

o Wave Broadband/ Cascade Network

• Electrical Services

o Bonneville Power Association

o Cowlitz County PUD

The CONSULTANT shall perform a subsurface utility engineering (SUE) study in the project

area to collect reliable subsurface utility information using methods and techniques outlined in

CI/ASCE 38-02 “Standard Guideline for the Collection and Depiction of Existing Subsurface

Utility Data” to produce a two-dimensional (2D) map and a three-dimensional (3D) models.

The CONSULTANT shall perform the SUE study in compliance with applicable Washington’s

2011 Underground Utilities Damage Prevention Act, any permits, and specifications, and shall

coordinate with Utility Owner and other inspectors, as required.

The CONSULTANT shall collect utility features to an accuracy of 0.10’ horizontally and 0.10’

vertically (+/- 0.03), providing quality level A (QLA) data, as identified in the ASCE 38-02

standards. Buried utilities are to be collected at the top of the conduit, while elements such as

hand holes, junction boxes, clean out, etc. are collected at the top center. Overhead items such

as power poles are to be collected at the center of the pole. Pole owner, style and badge ID are

noted at each object. The CONSULTANT shall assemble all data collected through survey

efforts into an ASCII formatted file that will include Point Number, Northing, Easting,

Elevation, Code, Attribute, and Collection Method to produce a 3D model of the SUE project

area, allowing content to be directly used by WSDOT.

The CONSULTANT shall develop a Traffic Control Plan describing how to provide safe and

efficient movement of vehicular, bicycle and pedestrian traffic through and around a work

zone. The Traffic Control Plan must be submitted to WSDOT a minimum of ten (10) working

days prior to the start of work that will impact traffic flow patterns to allow for review and

approval. The Traffic Control Plan must include, but not limited to, the following:

• Proposed order, duration, and type(s) of the traffic control measure(s) to be used during

on-site activities.

WSDOT will perform all coordination with the utility companies with the CONSULTANT

providing assistance as necessary. The CONSULTANT shall provide WSDOT with

Conceptual Plans to assist with any utility coordination efforts.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 27 of 34

Deliverable(s):

• Drawings and data needed to support utility coordination.

• ASCII formatted file that includes data Point Number, Northing, Easting, Elevation,

Code, Attribute, and Collection Method

• Three-dimensional (3D) models of subsurface utilities.

• Traffic Control Plan

2.10.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.10 – Utilities to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.10 - Utilities.

2.11 - Roadway

2.11.A Preliminary Engineering and Conceptual Plans

The CONSULTANT shall develop the preliminary roadway design based on the Project Conceptual Plans. The Project roadway geometry, including the vertical and horizontal

alignments, for SR 432, SR 433, East Port Way, West Port Way, Oregon Way and any temporary roadway alignments for use during construction shall be designed in accordance with the WSDOT Design Manual and other applicable design standards/manuals.

The CONSULTANT shall identify bicycle and/ or pedestrian paths that will connect the

Highlands Neighborhood to the businesses along SR432, East Port Way, West Port Way and the Lewis and Clark Bridge.

The CONSULTANT shall document, and submit to WSDOT for approval, all design decisions.

Deliverable(s):

• Submit preliminary design for all roadway elements and any associated

documentation of design decisions for WSDOT concurrence.

• Conceptual plans consisting of, at a minimum, vertical and horizontal profiles

and cross-sections.

2.11.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.11 – Roadway to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.11 Roadway.

2.12 - Project Documentation

2.12.A Preliminary Engineering and Conceptual Plans

The CONSULTANT shall develop and assemble the Design Approval package in accordance

with the WSDOT Design Manual and other applicable design standards and in consultation

with WSDOT and FHWA.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 28 of 34

WSDOT will provide engineering documentation previously completed by WSDOT such as the

Project Definition and the Project Delivery Method Selection Guide worksheet.

The CONSULTANT shall submit the Preliminary and Intermediate Design Approval package

at the 60% and 90% completion level of the RFP documents and the Final Design Approval

package ten (10) weeks before the RFP issue date. The Final Design Approval package will

need to be approved and signed off by WSDOT Southwest Region, WSDOT HQ, and FHWA.

The CONSULTANT shall assume up to ten (10) meetings with WSDOT to review the Design

Approval package.

Deliverable(s):

• Up to ten (10) meetings.

• Preliminary and Intermediate Design Approval package for review.

• Final Stamped Design Approval package for signatures.

• Writeable, electronic copy of the Final Design Approval package.

• Any associated design calculations and backup.

2.12.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.12 – Project Documentation to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.12 - Project Documentation.

2.13 - Bridges and Structures

2.13.A Preliminary Engineering and Conceptual Plans

The CONSULTANT shall prepare Bridge Site Data for the Project that includes all applicable

items on the Structure Site Data Checklist (Exhibit 710-1) in the WSDOT Design Manual.

Bridge Site Data shall be submitted to the WSDOT by the delivery date mutually agreed on

and shown on the endorsed Project schedule.

WSDOT will complete the Conceptual Bridge Plans. The CONSULTANT shall coordinate

with WSDOT and provide them with any necessary design information.

The CONSULTANT shall prepare Conceptual Wall Plans that tie into the Conceptual Bridge

Plan wingwalls.

The CONSULTANT shall also develop bridge and wall costs that reflect the Conceptual Plans

to be included in PM J - Design-Build Estimate of this Scope of Work.

Deliverable(s):

• Bridge Site Data and all applicable CAD files, tables, forms, cross-sections, and other

items identified on the Structure Site Data Checklist (Exhibit 710-1) in the WSDOT

Design Manual.

• Conceptual Wall Plans.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 29 of 34

2.13.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.13 – Bridges and Structures to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.13 – Bridges and Structures.

2.14 - Hydraulics

2.14.A Preliminary Engineering and Conceptual Plans

The CONSULTANT shall perform technical analysis, preliminary design and documentation activities which may include: development of anticipated hydrology, topographic map review,

structure sizing and associated design, and roadway drainage design,.

The CONSULTANT will prepare the Preliminary Hydraulic Design that establishes the site hydrology following the template provided by WSDOT. The CONSULTANT shall include the

Preliminary Hydraulic Design in the RFP Appendices as a Reference Document and could be utilized by the Design-Builder as the basis for the Final Hydraulic Design.

The CONSULTANT shall develop a Conceptual Hydraulic Report and associated roadway

drainage design for the Project in accordance with the WSDOT Hydraulics Manual and

Highway Runoff Manual. The Conceptual Hydraulic Report shall be included in the RFP

Appendices as a Reference Document and could be utilized by the Design-Builder as the basis

for the Final Hydraulic Report.

Deliverable(s):

• Conceptual Hydraulics Report for all roadway elements and any associated

documentation of design decisions for WSDOT concurrence. Engineer

preparing the Conceptual Hydraulics Report shall have current (2014 or newer)

HRM certification through WSDOT.

• Conceptual drainage plans and details.

• Preliminary Hydraulic Design (PHD) with hydraulic design files used.

2.14.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.14 – Hydraulics to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.14 - Hydraulics.

2.15 - Roadside Restoration

2.15.A Preliminary Engineering and Conceptual Plans

WSDOT will develop a Conceptual Roadside Restoration Plan to restore anticipated disturbed

areas and roadside function in accordance with the WSDOT Roadside Policy Manual. Based

on the Conceptual Plan, the CONSULTANT shall provide information and Project

environmental impacts such as the Project footprint and anticipated disturbed areas to WSDOT

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 30 of 34

(See Section 2.8 Environmental).

WSDOT will locate and design off-site mitigation areas, if applicable. (See Section 2.24

Right-of-Way)

2.15.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.15 – Roadside Restoration to reflect the Project technical requirements in

consultation with WSDOT.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.12 – Roadside Restoration.

2.16 - Illumination

2.16.A Preliminary Engineering and Conceptual Plans The CONSULTANT shall develop illumination design concepts in order to prepare preliminary

construction cost estimates only. The CONSULTANT shall coordinate with the WSDOT to

review design concepts

Deliverable(s):

• Illumination systems cost estimate

2.16.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.16 – Illumination to reflect the Project technical requirements in consultation

with the WSDOT.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.16 – Illumination.

2.17 - Signal Design

2.17.A Preliminary Engineering and Conceptual Plans The CONSULTANT shall develop basic signal design (signal needs and feasibility of

installation) in order to develop preliminary construction cost estimates only. The

CONSULTANT shall coordinate with the WSDOT to review design concepts.

Deliverable(s):

• Signal equipment cost estimates

2.17.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.18 – Signal Design to reflect the Project technical requirements in consultation

with the WSDOT.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.17 – Signal design.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 31 of 34

2.18 - Intelligent Transportation Systems (ITS)

2.18.A Preliminary Engineering and Conceptual Plans – Not Applicable

2.18.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.18 – Intelligent Transportation Systems (ITS) to reflect the Project technical

requirements in consultation with the WSDOT.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.18 – Intelligent Transportation Systems (ITS).

2.19 - Signing

2.19.A Preliminary Engineering and Conceptual Plans

The CONSULTANT shall develop signing design concepts in order to prepare preliminary

construction cost estimates only. The CONSULTANT shall coordinate with the WSDOT to

review design concepts.

Deliverable(s):

• Signing cost estimate

2.19.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.19 – Signing to reflect the Project technical requirements in consultation with

the WSDOT.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.19 – Signing.

2.20 - Pavement Marking

2.20.A Preliminary Engineering and Conceptual Plans

The CONSULTANT shall develop conceptual pavement marking plan in order to prepare

preliminary construction cost estimates only. The CONSULTANT shall coordinate with the

WSDOT to review design concepts.

Deliverable(s):

• Pavement marking cost estimate

2.20.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.20 – Pavement Marking to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.20 – Pavement Marking.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 32 of 34

2.21 - Traffic Operations

2.21.A Preliminary Engineering and Conceptual Plans- Not Applicable.

2.21.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.21 – Traffic Operations to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.21 – Traffic Operations.

2.22 - Maintenance of Traffic (MOT)

2.22.A Preliminary Engineering and Conceptual Plans

The CONSULTANT shall coordinate with WSDOT to develop any conceptual construction

staging drawings, construction access, and Traffic Control Plans deemed necessary by the

Project Team to include in the procurement documents.

Deliverable(s):

• Conceptual Staging Drawings, construction access, and Traffic Control Plans, if needed.

2.22.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.22 – Maintenance of Traffic (MOT) to reflect the Project technical

requirements in consultation with the WSDOT.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.22 – Maintenance of Traffic (MOT).

2.23 - Railroads

2.23.A Preliminary Engineering and Conceptual Plans

The CONSULTANT shall obtain necessary permits prior to entering the railroad right-of-way.

The CONSULTANT shall facilitate up to five (5) meetings with the railroad owners and

WSDOT to discuss possible impacts to their operations and facilities. These meetings will be

held in WSDOT Kelso Area Engineering Office.

Deliverable(s):

• Up to five (5) meetings with the railroad owners in WSDOT Kelso Area Engineering

Office.

2.23.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.23 – Railroads to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.23 Railroads.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 33 of 34

2.24 - Right-of-Way

2.24.A Preliminary Engineering and Conceptual Plans

The CONSULTANT, in consultation with WSDOT, shall determine temporary and permanent

right-of-way necessary for the Project. This includes, but is not limited to, parcels within the

Project limits that will be impacted by any temporary detour access road, construction

activities, construction staging areas, and/or environmental mitigation.Permanent right-of-way

is anticipated for this Project.

The CONSULTANT shall obtain deeds and title reports for impacted parcels and provide

WSDOT with information, technical data, and assistance needed to obtain any identified TCEs, permits, and acquisitions. WSDOT will be responsible for working with the affected land-owners to obtain TCEs, permits, and other property rights. WSDOT will develop a Sundry Site

Plan, if needed (See Section 2.15 Roadside Restoration).

WSDOT will complete the red and green markups to existing Right-of-Way Plans (See Section

2.5 Survey) and coordinate with WSDOT HQ for approval.

Deliverable(s):

• Deeds and title reports for impacted parcels.

• Drawings, information, and technical data needed to obtain temporary

easements and permanent right-of-way acquisitions (See Section 2.5 Survey).

2.24.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.24 – Right-of-Way to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.24 Right-of-Way.

2.25 - Control of Materials

2.25.A Preliminary Engineering and Conceptual Plans - Not Applicable

2.25.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.25 – Control of Materials to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.25 Control of Materials.

2.26 - Vacant

2.27 - Vacant

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work

Page 34 of 34

2.28 - Quality Management Plan (QMP)

2.28.A Preliminary Engineering and Conceptual Plans - Not Applicable

2.28.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.28 – Quality Management Plan to reflect the Project technical requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.28 Quality Management Plan.

2.29 - Maintenance During Construction

2.29.A Preliminary Engineering and Conceptual Plans - Not Applicable

2.29.B RFP – Technical Requirements

The CONSULTANT shall modify the current FHWA-approved Design-Build template for

RFP Chapter 2.29 – Maintenance During Construction to reflect the Project technical

requirements.

Deliverable(s):

• 60%, 90% and Final RFP Chapter 2.29 Maintenance During Construction.

DRAFT

SR 432 Longview Grade Crossing - Draft Scope of Work