PM Lecture 6

Embed Size (px)

Citation preview

  • 8/3/2019 PM Lecture 6

    1/45

    1

    Lecture April 7, 2011

    Project Management

  • 8/3/2019 PM Lecture 6

    2/45

    2

    Overview

    Project planning III

    Repetition

    Project Organization

    Summary

  • 8/3/2019 PM Lecture 6

    3/45

    3

    adaptation

    Model of Project Control

    Project planning

    content / deliveries

    start and end dateteam members

    Target values budget

    Control

    Activities

    Project control

    Real values

    Monitoringdiscrepancies

    Real values

    Project execution scope change disturbance capacity problems

    inter personal problems

  • 8/3/2019 PM Lecture 6

    4/45

    4

    From the Structure to Scheduling of a Project

    Work package

    Work breakdown structure

    2 6

    7 12 153

    4

    5

    8

    9

    10

    11

    13

    14

    16

    Schedule (e.g. network)

    1

    BCreate list ofrequirements

    CProject sc hedule

    DConduct

    Feasibility study

    EPhase plan

    Projektmmgtcreation

    F

    Project reportstudy

    GDesign

    system concept

    HDeterminefunctions

    IPhase planconcept

    JDetermine

    development process

    Project reportConcept

    AProject

    organization

    Work Flow

  • 8/3/2019 PM Lecture 6

    5/45

    5

    Example: Gantt-Chart

  • 8/3/2019 PM Lecture 6

    6/45

    6

    0 0 0

    0 0 0

    Project start

    0 1 1

    2 2 3

    1 2 3

    3 2 5

    5 4 9

    5 0 9

    9 0 9

    project end

    9 0 9

    0 5 5

    0 0 5

    5 1 6

    6 1 7

    6 2 8

    7 1 9

    earliest starting date estimated duration earliest finishing date

    latest start Total float latest finishing date

    Determine Critical Path

    Activity 1 Activity 3 Activity 5

    Activity 2 Activity 4 Activity 6

    1. step: forward calculation

    2. step: backward calculation

  • 8/3/2019 PM Lecture 6

    7/457

    Top-down (global) estimation methods For a fast and easy, approximate estimation of projects cost. Uses parameters, key data (e.g. per volume)

    Bottom-up (analytical, AP-based) estimation methods

    Basis for detailed project cost planning Basis for cost based project controlling

    Work packagecosts

    Workpackages

    Type ofcost

    Projectcosts (PC)

    Allocatio

    n

    PC overtime

    Principles of Cost Estimation in Projects

  • 8/3/2019 PM Lecture 6

    8/458

    Project Organization

  • 8/3/2019 PM Lecture 6

    9/459

    Project Organization: Introduction

    Classical (permanent) organization structure of a company

    Determines leadership structure and organizational rules to manage thetask

    Set up for recurring, well-known transaction

    Mostly skill-orientated structure

    But projects require: Intensive interdisciplinary cooperation

    Specific tasks and workflows

    Specific leadership and motivation of employees

    Particular leadership tasks and structure

    => Project organization

  • 8/3/2019 PM Lecture 6

    10/4510

    Definition: Project Organization

    The term project organization refers to the organization,

    which is assigned with a project and its integration in the

    existing organization of the company.

    (Kummer: Projektmanagement. 1986. S. 41)

  • 8/3/2019 PM Lecture 6

    11/4511

    Organizational Structure of a Project

    Organization

    Structure

    Process

  • 8/3/2019 PM Lecture 6

    12/4512

    Tasks of the Structural Organization

    Result- and fact oriented arrangement of the functionalstructure of the project

    Clear allocation of task, responsibilities and competencies

    Effective collaboration and cooperation of all partiesconcerned in the project

    Fast alignment of the project organization to changes in theobjectives and boundary conditions

    Source: Litke, H.-D.: Projektmanagement. Hanser 1995

  • 8/3/2019 PM Lecture 6

    13/4513

    People in Projects

    Steering committee

    Project leader

    Project team

    Special

    functions

    Expert committee

  • 8/3/2019 PM Lecture 6

    14/4514

    People in Projects

    Steering committee

    Project leader

    Project team

    Special

    functions

    Expert committee

  • 8/3/2019 PM Lecture 6

    15/4515

    Steering Committee

    Temporary, project accompanying committee

    Superior authority to project leader and project team (to bereported to)

    Gives a summary of decision-makers and responsiblepersons for the project (e.g. later user, systemresponsibility, commercial responsibility)

    Take essential decisions for project together

    Task ends after project is finished

  • 8/3/2019 PM Lecture 6

    16/4516

    Main Tasks of a Steering Committee

    Principals representative of the interests, the participating divisionsin the project or outsider

    Definition of project objectives and project tasks (together withproject manager)

    Agreement and assignment of members to the consulting team

    Controlling and approval of the project plan Setting priorities

    Verification and approval of the elaborated phase results

    Support and advice of all major occurring problems

    Make decisions, which exceed competency of the project manager

    Resource allocation Mediation if conflicts occur

    Enforcement of outside related topics of the project

  • 8/3/2019 PM Lecture 6

    17/4517

    Steering Committee

    Composition 1 representative of each relevant hierarchy level/line

    Representatives of each essential involved parties

    Project manager

    Experts

    Possibly representatives of external groups (politicalrepresentatives)

    Criteria to choose members

    Position, which enhance the implementation of the project

    Expertise Position as an information carrier

    Involvement

  • 8/3/2019 PM Lecture 6

    18/4518

    People in Projects

    Lenkungsausschuss

    Projektleitung

    Projektteam

    SpezielleFunktionen

    Fachausschuss Steering committee

    Project leader

    Project team

    Special

    functions

    Expert committee

  • 8/3/2019 PM Lecture 6

    19/45

    19

    Expert Committee

    Should inform, support and advice the project team

    Placement of expertise in terms of effects, risks,accompaniment

    To carry out results of the project team into special fields

    Committee with supporting and advising function, butwithout decision-making authority

  • 8/3/2019 PM Lecture 6

    20/45

    20

    People in Projects

    Lenkungsausschuss

    Projektleitung

    Projektteam

    SpezielleFunktionen

    Fachausschuss Lenkungsausschuss

    Projektleitung

    Projektteam

    SpezielleFunktionen

    Fachausschuss Steering committee

    Project leader

    Project team

    Special

    functions

    Expert committee

  • 8/3/2019 PM Lecture 6

    21/45

    21

    Project Management

    Is in charge of the attainment of the project goal, as regardscontent as well as competence

    Has the duty to assure the best possible success of theproject, technical as well as economical

    Prerequisites to carry out this duty:

    - Clear project brief- Objectives which are agreed on, realizable and measurable

    - Well-defined area of responsibility

    - Sufficient resources

    - Congruent tasks and authoritiesDuty of the project

    management to intervene

    or to refuse if those termsare not fulfilled!

  • 8/3/2019 PM Lecture 6

    22/45

    22

    Tasks of the Project Management

    To plan the project To align tasks, competencies, responsibilities, resources

    To set priorities

    To assure and control system and project tasks

    To push the project, evolve initiative To take action to realize the project within the given specification

    (activity, costs, deadlines)

    To clear up conflicts

    To prepare and procure decisions

    To initiate contacts

    To assure communication

    To lead and motivate the project team

  • 8/3/2019 PM Lecture 6

    23/45

    23

    People in Projects

    Steering committee

    Project leader

    Project team

    Special

    functions

    Expert committee

  • 8/3/2019 PM Lecture 6

    24/45

    24

    People in Projects

    Lenkungsausschuss

    Projektleitung

    Projektteam

    SpezielleFunktionen

    Fachausschuss Lenkungsausschuss

    Projektleitung

    Projektteam

    SpezielleFunktionen

    Fachausschuss Steering committee

    Project leader

    Project team

    Special

    functions

    Expert committee

  • 8/3/2019 PM Lecture 6

    25/45

    25

    Special Functions

    Consulting in methodology

    Documentation management

    Liaison people (to the concerned parties)

    Power promoter

    Technical promoter

    Social promoter

  • 8/3/2019 PM Lecture 6

    26/45

    26

    Overview of the Project and Organization Structures

    Pure project organization

    Influence project organization

    Matrix project organization

  • 8/3/2019 PM Lecture 6

    27/45

    27

    Pure Project Organization (1)

    Department CDepartment BDepartment A

    Projekt B

    PM B

    Board of

    Management

    Projekt A

    PM A

    Source: Litke, H.-D.: Projektmanagement. Hanser 1995

  • 8/3/2019 PM Lecture 6

    28/45

    28

    Pure Project Organization (2)

    Virtually separate organization for a project

    Managed in full responsibility by the project leader

    Project team members are displaced, delegated for theduration of the project

    Project team members get only briefed by the project

    manager

  • 8/3/2019 PM Lecture 6

    29/45

    29

    + Full concentration of all involved members to the project goals

    + High identification with the project

    + Full line authority of the project manager

    + Clear managerial authority

    + Taut leadership of the project

    + Fast reaction to changes/ disturbances

    + Fast coping with difficulties

    - Allocation of requisite dedicated resources- Little exchange of specialists with divisions

    - Problematic capacity utilization of specialists

    - Critical reintegration of the team members at the end of the project

    Pros and Cons of a Pure Project Organization

  • 8/3/2019 PM Lecture 6

    30/45

  • 8/3/2019 PM Lecture 6

    31/45

    31

    Influence Project Organization (1)

    Board ofManagement

    Department B

    PM Staff

    Department CDepartment A

    Source: Litke, H.-D.: Projektmanagement. Hanser 1995

  • 8/3/2019 PM Lecture 6

    32/45

    32

    Influence Project Organization(2)

    Minimum configuration of a project organization

    Functional organization/ hierarchy remains unchanged

    Organization is extended by a project leader in a executive

    management team function (on a sufficient high level)

    Project leader on management team function level- Has only information and advising rights towards the departments

    - Has no decision and directive authority

    - Tracks project regarding content, deadlines and costs

    - Proposes measures to line managers- Motivates employees within the departments to actively participate in

    the project towards the fulfilling of the project objectives

  • 8/3/2019 PM Lecture 6

    33/45

    33

    + Flexibility regarding work force usage (involvement in severalprojects possible)

    + Improved learning curve (experience from several projects)

    + No change of company organization necessary

    + Continued relation to department

    - Limited identification and responsibilities

    - Limited need to solve problems across departments

    - Response and decision time low (involvement of lineorganization!)

    Pros and Cons of the Influence Project Organization

  • 8/3/2019 PM Lecture 6

    34/45

  • 8/3/2019 PM Lecture 6

    35/45

    35

    Matrix Project Organization (1)

    Executive board

    Project 1

    Project 2

    Department A Department B Department C

    Projectrelated

    directives

    Function related directives

    Source: Litke, H.-D.: Projektmanagement. Hanser 1995

  • 8/3/2019 PM Lecture 6

    36/45

    36

    Matrix Project Organization (2)

    Main principle: Combination of a vertical (functional) and ahorizontal (project oriented) organization

    Project executed by the departments as a service providerfor the project (focus on execution)

    Project leader coordinates and is responsible for the projectas a whole (focus on project targets, planning andcontrolling)

    More than one project leader may use same resources

    Project members are assigned to department manager +

    project leader

  • 8/3/2019 PM Lecture 6

    37/45

  • 8/3/2019 PM Lecture 6

    38/45

    38

    + balanced consideration of project dimension and professional

    dimension+ Goal oriented coordination of different interests

    + High identification of all employees with the project

    + Simultaneous technical source for project team members

    - Potential to conflict since different interest of line and project

    - Cut of the authority of the line => danger of arguments concerningcompetencies and passive resistance

    - Enormous coordination effort between line and project management

    - Difficult situation for employees (servant of two masters)

    Pros and Cons of the Matrix Project Organization

  • 8/3/2019 PM Lecture 6

    39/45

    39

    Advantages of a Functional Home Base

    A flexible deployment of staff is possible

    Continuity of further training in expertise is rather assured

    Special knowledge and specific experience can be transferredfrom one project to the next

    Those employees, which are not completely moved out of

    their original organization feel more comfortable and moresecure.

    Source: Litke, H.-D.: Projektmanagement. Hanser 1995

  • 8/3/2019 PM Lecture 6

    40/45

  • 8/3/2019 PM Lecture 6

    41/45

    41

    Choice of the Adequate Organizational Structure

    Project organization and project management can only besuccessful, if the existing management system and the projectorganization match up.

    The choice of the project organization depends on:- structure of the existing organization

    - size and duration of the project

    - its importance for business policy reasons

    - necessity of the interdisciplinary cooperation of different areas

    - project risk

    - availability of resources

    - experience in project organizations

    - number/ frequency of projects in one area

  • 8/3/2019 PM Lecture 6

    42/45

    42

    Project Size

    < 6

    6-50

    > 50

    < 0,4

    0,4-50

    > 50

    < 0,1

    0,1-10

    > 10

    Small project

    Medium sizedproject

    Major project

    Numberemployees

    Mio. DMMan-year

    Source: Litke, H.-D.: Projektmanagement. Hanser 1995

  • 8/3/2019 PM Lecture 6

    43/45

    43

    Reasons for a Change in Project Organization During a

    Project

    Different emphases and people in different phases

    Changes of objectives and contents as the project runs

    Exchange of important staff members

    E l f Ch i P j t O i ti

  • 8/3/2019 PM Lecture 6

    44/45

    44

    Example for a Change in Project Organization

    Creativity and brainstorming

    come to the fore. Performance

    of the project uncertain.

    High interdisciplinarycooperation needed.

    Project has high importance

    for business policy reasons.

    Conceptual design largely

    finished, no need anymorefor cooperation

    with other departments.

    ReasoningProfile of

    project organizationPhaseInfluence-

    project organization

    Matrix-project organization

    pure

    project organization

    Line organization

    Definition

    Draft

    Realization

    TrialSource: Litke, H.-D.: Projektmanagement. Hanser 1995

  • 8/3/2019 PM Lecture 6

    45/45

    Summary and Preparation for the Next Session

    Pure project organization (p.o.): independent, PL in the fore Influence p.o.: existing organization is completed to a minimum Matrix p.o.: overlay of the vertical (functional) organization with a

    horizontal (project orientated) organization

    Preparation Post processing of today's lecture