    Basis components of hydro projects

    Diversion Structure-Dam/ Barrage/ Weir/

    Trench Weir Feeder channel, Trash racks, Intake gates

    Power Intakes, Desilting Tanks/ Chambers/

    basin, Spilling arrangements Power channel, Forebay tanks, Head Race

    Tunnel

    Surge Shaft, Pressure shaft, Penstocks,Power house, Transformer Hall

    Draft tube, Tail Race Tunnel/ Channel,

    Construction adits & permanent adits

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    3/119

    LAYOUT OF HYDRO PROJECTS

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    4/119

    Corporate centre

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    5/119

    IRIGATION CANAL

    CANAL FALL POWER HOUSE

    INTAKE

    CANAL FALL

    POWER HOUSE

    TAIL RACE

    CHANNEL

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    6/119

    POWER CHANNEL DEVELOPMENT

    FALL

    DIVERSION STUCTUREPOWER INTAKE

    TAIL RACE

    POOL

    RIVER

    POWER CHANNEL

    FOREBAY PENSTOCK

    POWERHOUSE

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    7/119

    POWER TUNNEL DEVELOPMENT

    FALL

    DIVERSION STUCTUREPOWER INTAKE

    HEADRACE

    TUNNEL

    TAILRACE

    POOL

    POWERHOUSE

    RIVER

    SURGESHAFT

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    8/119

    U/S AND D/S SURGE TANK SYSTEM

    UNDERGROUND POWER HOUSE

    AIR VENT

    DOWNSTREAM

    SURGE SHAFT

    PRESSURE SHAFT

    STEADY STATE LEVEL

    UPSTREAM SURGE SHAFT

    TAILRACE TUNNEL

    HYDROSTATIC LEVEL

    LOW PRESSURE

    CONDUIT

    RESER-

    VOIR

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    9/119

    ACCESSSHAFTDAM

    RIVER

    SURGECHAMBER

    TAIL RACETUNNEL

    UNDERGROUNDMACHINEHALL

    UPSTREAM STATION ARRANGEMENT

    (SWEDISH SYSTEM)

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    10/119

    PRESSURE TUNNEL

    PRESSURE SHAFT

    EXCAVATED SURGE TANK

    TURBINE

    TAILRACE

    MIN SURGE LEVEL

    INTAKE

    SURGE TANK

    MAX SURGE LEVEL

    MAIN INLETVALVE

    GATE GROOVE

    STEADY STATE LEVEL

    RESERVOIR

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    11/119

    INVESTIGATION & PROJECT

    FORMULATION STAGES

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    12/119

    FR/ DPR

    GEO-TECHNICAL

    INVESTIGATION

    PROJECT

    OPTIMIZTION

    CONSTRUCTIONMATERIAL SURVEY

    EIA

    STUDIES

    SEISIMIC

    STUDIES

    TRANSPORTATION

    STUDY

    TOPOGRAPHICAL

    SURVEY

    DISASTER

    MANAGEMENT

    STUDIES

    SOCIO-ECONOMICSTUDIES

    HYDROLOGICALSTUDY

    STUDIES AND INVESTIGATIONS

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    13/119

    PROJECT FORMULATION STAGES

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    14/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    15/119

    PPROACH ROADS, LAND, QUARRY SITES, DUMPING AREAS,

    TEMPORARY INSTALLATION SERVICES LIKE CAMP OFFICE,FIELD HOSTEL, GUEST HOUSE, FAMILY QUARTERS FOROFFICERS & STAFF, MAIN OFFICE, WORKSHOPS, DG POWERGENERATING SETS, MAIN STORES, GARRAGE, COMPRESSORSTATIONS, DISPENSARY, SECURITY STAFF

    COMMUNICATION FACILITIES

    AGGREGATE PROCESSING PLANT (APP),CONCRETE BATCHING PLANT (CBP)QUALITY CONTROL LAB

    AREA FOR PROCESSING FILL MATERIALSTORES FOR BLASTING MATERIAL

    WATER SUPPLY & SEWERAGE DISPOSAL SYSTEM

    CONSTRUCTION EQUIPMENTS

    INFRASTRUCTURAL FACILITIES REQUIRED

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    16/119

    General layout of facilities & installations

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    17/119

    Construction Materials

    OPC to be used for shotcrete & grouting and PPC to beused for concreting & masonry.

    Steel to be sourced from reputed Suppliers like SAIL,TISCO, RIL etc. confirming to the provisions of the

    document. Structural Steel to be sourced from reputed Suppliers like

    SAIL, TISCO, RIL etc. confirming to the provisions of thedocument.

    Material available from under ground excavation foraggregates.

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    18/119

    PLANNING OF HYDRO PROJECTS

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    19/119

    CONSTRUCTION PROGRAMME

    Major Activities StartMonth

    EndMonth

    Months

    0 10 20 30 40

    LOI & Mobilization 1 6

    Barrage 3 38

    Intake Pool

    13 38Power Intake 13 25

    Desilting Chamber 3 39

    Gate shaft DC &SFT 3 25Silt Flushing Tunnel 4 35

    GROUTING ANDPLUGING 25 40

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    20/119

    Construction EquipmentsS. No. Equipment and Capacity

    Min Quty in

    Nos

    No.

    proposed

    1 2-Boom hydraulic Drill Jumbo 4 3

    2 Hydraulic Excavator, 2.0 cum 2 -

    3 Hydraulic Excavator, 0.9 cum 4 -

    Hydraulic excavator CK 90 or equivalent 3Hydraulic excavator CK 75 or equivalent 1

    4 Crawler / Wagon Drill 5

    Crawler Drill LM100 or Eq 9

    5 Heavy Duty Rock Drill, 120 cfm (with 24 24

    6 Rear Dumper 18T, 4x4 24

    Rear Dumper 15T, 4x4 19

    7 Crawler Dozer, 180hp 4

    Dozer D6, 165HP 18 Wheel mounted Dozer, 180 hp 1

    9 Wheel Loader, 2.5 cum 3 3

    10 Loader cum excavator, 1.0cum / 0.24cum 3 1

    11 Shotcrete m/c, 4-6 cum 3

    Shotcrete Machine, Aliva 260 or Eq (4 - 3

    12 Shotcrete m/c with Robot Arm, 10-20 cum 3

    Shotcrete machine (30 m3 /hr capacity) 2

    13 Raise Climber, 250 M 2 214 Raise Borer 1 -

    15 Air Compressor, 600 cfm, Electric 6

    16 Air Compressor, 500 cfm, Diesel 3

    Air Compressor, 500-600 cfm, electric /

    deisel9

    Air Compressor, 180 cfm, electric / deisel 2

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    21/119

    Construction EquipmentsS. No. Equipment and Capacity

    Min Quty in

    Nos

    No.

    proposed

    17 Agg Cr plant , 100 tph 1 1

    18 Batching & mixing plant, 60 m3/hr 1 1

    19 Batching & mixing plant, 30 m3/hr 1 1

    20 Collapsible Shutter form with traveler, 2

    Tunnel form with traveler, 8m 2

    21 Transit Mixer, 6.0 m3 15 13

    22Concrete pump truck mounted with

    placing boom, 30m3/hr2 -

    23 Concrete pump, 30m3/hr 2 4

    24 Concrete mixer, 14/10 cft 3 3

    25 Tipper, 10T 24 6

    26 Grout Pump 4 3

    27 Telescopic Crane, 20T 2

    Mobile crane 30T for steel liner work 1

    Crawler crane 20T capacity 1

    28 Hydra / Mobile crane, 5T 2 229 Rib Erector, 1.8Ton 1 1

    30 Scoop Tram / Low profile Loader 1.6 cum 1 -

    31 Scissor,s Platform 1 1

    32 Flat bed Truck 1

    Flat bed Truck 10 ton capacity 2

    33 Trailer 1 1

    Trailer 20 Ton capacity 1

    Trailer 30 Ton capacity 1

    34 Bending & Cutting Machine 1 1

    35 Bending & Cutting Machine (Steel Plate) 1

    Plate bending machine-63mm 1Pug cutting machine 4

    36 Power Winch 2

    Winch 20T Capacity 4

    37 Gantry Crane 1

    Gantry Crane 25 T 1

    Gantry Crane 15 T 1

    Portable gantry crane 30T cap 2

    EOT crane of 30T, 10m 1

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    22/119

    LAYOUT OF SOME OF EXISTING/

    PLANNED HYDRO PROJECTS

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    23/119

    SATLUJ RIVER

    SATLUJ RIVER

    DIVERSION TUNNELS

    MAIN DAM AXIS

    SPILLWAY

    POWER HOUSE

    PENSTOCKS

    KOL DAM -- LAYOUT PLANKOL DAM -- LAYOUT PLAN

    KOL DAM HEPP (4 x 200 MW)

    DIVERSION DIKE

    RESERVOIR

    U/S OF DAM

    DESILTING

    BASIN

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    24/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    25/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    26/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    27/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    28/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    29/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    30/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    31/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    32/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    33/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    34/119

    How does a DC look like?

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    35/119

    VIEW OF UNDER GROUND DESILTING CHAMBERVIEW OF UNDER GROUND DESILTING CHAMBER

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    36/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    37/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    38/119

    Under Ground Excavation

    sequence

    Stage 1 Excavation of Adit ( Top & Bottom)

    Cycle time ( Hr.)

    Good Rock 11.32 (3 m Pull)

    Poor Rock-14.15 (1 m Pull)

    6 m x 6m

    85m

    150m

    235m

    4250 HS

    Invert : 2134m

    Activity Duration 3 to

    7 Months+2132.75m

    EL +2145

    +2124m

    260

    m

    200m

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    39/119

    Stage 2 Excavation of pilot drift ( 6 x 8 m)

    up to EL + 2132.75

    Av. Progress : 95 m/month

    +2132.75m

    80m

    50m

    150m

    Invert : 2134 m

    400m

    Activity Duration 8 to 9.5

    months

    +2132.75m

    +2132.75m

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    40/119

    Stage 3 Outlet tunnels and HRT

    Cycle time ( Hr.)

    Good Rock 9.59 ( 3 m pull)

    Poor Rock - 13.16 (1m pull)

    Ave. Progress 95m/m

    Activity Duration

    Exc 9.5 to14.5 months

    Lining 11.5 to 17.5 months (OutletTunnel)

    80m

    50m

    150m

    400m

    Invert : 2134 m

    4.25 m

    6.0 m

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    41/119

    Stage 4 Side slashing of desilting chamber

    exc up to EL. 2132.75 m & lining upto 2134.m

    Cycle time ( Hr.)

    Good Rock 16.6 ( 3 m pull)

    Poor Rock - 15.36 (1m pull)

    Av. Progress : 70m/m

    Activity Duration

    Exc : 9.5-11.5 months

    Lining : 11.5-17.5 month

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    42/119

    Stage 5 Excavation in benching and ramp formation

    (EL. + 2132.75m to EL. +2129.75m)

    Cycle time ( Hr.) 10.19

    (for 25 sqm benching)

    Activity Duration 17.5-19.5

    months

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    43/119

    Stage 6 Excavation in benching and ramp formation

    (EL. + 2129.75m to EL. +2126.75m)

    Cycle time ( Hr.) 10.19

    (for 25 sqm benching)

    Activity Duration 19.5-25.5 months

    EL+2126.75

    EL+2126.75

    EL+2126.75

    Benching 2 Months

    Lining from El 2129.75 to 2134.0 4 Months

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    44/119

    Stage 7 Excavation in benching

    (EL. + 2126.75m to EL. +2123.75m incl interconnecting

    bottom tunnels & removal of ramp)

    Cycle time ( Hr.) 10.19

    (for 25 sqm benching)

    Activity Duration 25.5-28.5 month

    Interconnecting Tunnels 1 Month

    Removal of bench and benching down 2 month

    EL+2123.75

    EL+2123.75

    EL+2123.75

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    45/119

    Stage 8 Excavation of trench

    Activity Duration 28.5- 39.0 month

    Trench exc 2 Month

    Conc in Trench EL+ 2120 to EL+ 2123.75 =3.5 Month

    Lining in Hopper El + 2123.75 to 2129.75 to 5 Months

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    46/119

    How does a HRT look like?

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    47/119

    Circular HRT

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    48/119

    Horse shoe type HRT

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    49/119

    Modified horse shoe type HRT

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    50/119

    Cross Section of a Horse Shoe HRT

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    51/119

    Surge Shaft

    How does a surge shaft look like?

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    52/119

    Looking from top towards bottom

    Dhaulinganga HEP Surge Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    53/119

    Dhaulinganga HEP Surge Shaft

    Dhaulinganga HEP Surge Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    54/119

    Dhaulinganga HEP Surge Shaft

    Nathpa Jhakri HEP Surge Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    55/119

    Nathpa Jhakri HEP Surge Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    56/119

    Nathpa Jhakri HEP Surge Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    57/119

    Nathpa Jhakri HEP Surge Shaft

    Nathpa Jhakri HEP Surge Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    58/119

    Nathpa Jhakri HEP Surge Shaft

    Nathpa Jhakri HEP Surge Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    59/119

    Nathpa Jhakri HEP Surge Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    60/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    61/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    62/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    63/119

    Excavation Scheme For Surge Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    64/119

    Text (Font Arial 16, Color Black, Line Spacing 30 points).

    Text (Font Arial 16, Color Black, Line Spacing 30 points).

    Excavation Scheme For Surge Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    65/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    66/119

    Surge shaft pilot hole

    Tunnel Level

    Surge shaft Top level

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    67/119

    Surge shaft Reaming

    Surge shaft Top level

    Tunnel Level

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    68/119

    Raise borer

    Nathpa JHAKRI HEP Surge Shaft Raise borer

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    69/119

    p g

    Raise borer

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    70/119

    Raise borer

    Raise borer

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    71/119

    Raise borer

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    72/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    73/119

    Valve House ExcavationValve House Excavation

    SequenceSequence

    Excavation Sequence Of Valve Chamber

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    74/119

    Text (Font Arial 16, Color Black, Line Spacing 30 points).

    Text (Font Arial 16, Color Black, Line Spacing 30 points).

    q

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    75/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    76/119

    Location of Pressure Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    77/119

    Location of Pressure Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    78/119

    Bifurcation of HRT into

    Pressure shafts under

    construction.

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    79/119

    Bifurcation of HRT Into Two PRESSURESHAFTS Finished.

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    80/119

    CONSTRUCTION OF PRESSURE

    SHAFTS BY RAISE CLIMBER

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    81/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    82/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    83/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    84/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    85/119

    Excavation Scheme For Inclined Pressure Shaft

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    86/119

    Text (Font Arial 16, Color Black, Line Spacing 30 points).

    Text (Font Arial 16, Color Black, Line Spacing 30 points).

    Excavation Scheme For Inclined Pressure Shaft

    Methodology - Enlargement of Inclined Tunnel

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    87/119

    Lower Penstock Tunnel

    A-A Section

    B

    B

    InclinedPenstock

    Tunnel(56d)

    C

    CUpper Penstock

    B-B SectionC-C Section

    A

    A(mucking)

    (enlarg

    ement)

    gy g

    AA

    B

    Intermediate adit

    Pilo

    thole

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    88/119

    Extension of Intermediate AditExtension of Intermediate Adit

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    89/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    90/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    91/119

    POWER HOUSE &

    TRANSFORMER HALL

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    92/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    93/119

    Koyna Powerhouse StageMachine Hall

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    94/119

    Machine Hall

    Koyna Powerhouse Stage

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    95/119

    Machine Hall

    Dhaulinganga HEP MachineH ll

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    96/119

    Hall

    Dhaulinganga HEP Machine Hall

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    97/119

    Dhaulinganga HEP Machine Hall

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    98/119

    Dhaulinganga HEP Machine Hall

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    99/119

    Purulia PSP Crane Beam And Columns

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    100/119

    Purulia PSP Crane Beam And Columns

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    101/119

    Purulia PSP Crane Beam And Columns

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    102/119

    Purulia PSP Machine Hall

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    103/119

    Purulia PSP Crane Beam Columns

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    104/119

    Purulia PSP Machine Hall

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    105/119

    PURULIA PSP CRANE BEAM AND COLUMNS

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    106/119

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    107/119

    CONSTRUCTION OF POWER

    HOUSE & TRANSFORMER HALL

    Excavation Sequence For Powerhouse

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    108/119

    Text (Font Arial 16, Color Black, Line Spacing 30 points).

    Text (Font Arial 16, Color Black, Line Spacing 30 points).

    Excavation Sequence Of Transformer Cavern

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    109/119

    POWER HOUSE

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    110/119

    Stage 1, 2, 2A, 3 & 3AStage 1, 2, 2A, 3 & 3A

    Power House excavation sequencePower House excavation sequence

    Stage

    1,Pilo

    t

    Stage

    1,Pilo

    t

    Stage

    2,2

    A,

    Stage

    2,2

    A,

    Wide

    ning

    Wide

    ning

    Stage

    3,3

    A,

    Stage

    3,3

    A,

    Widening

    Widening

    POWER HOUSE

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    111/119

    Completion of Stage 1, 2, 2A, 3 & 3ACompletion of Stage 1, 2, 2A, 3 & 3A

    Power House excavation sequencePower House excavation sequence

    POWER HOUSE

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    112/119

    Stage 4Stage 4

    Power House excavation sequencePower House excavation sequence

    POWER HOUSE

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    113/119

    Stage 5Stage 5

    Power House excavation sequencePower House excavation sequence

    POWER HOUSE

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    114/119

    Stage 6 Service BayStage 6 Service Bay

    Power House excavation sequencePower House excavation sequence

    POWER HOUSE

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    115/119

    Stage 7Stage 7

    Power House excavation sequencePower House excavation sequence

    POWER HOUSE

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    116/119

    Stage 8Stage 8

    Power House excavation sequencePower House excavation sequence

    POWER HOUSE

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    117/119

    Stage 9 Penstock levelStage 9 Penstock level

    Power House excavation sequencePower House excavation sequence

    POWER HOUSE

  • 7/31/2019 Planning & Construction of Hydro Projects,OCT,08

    118/119

    Stage 10 Excavation completeStage 10 Excavation complete

    Power House excavation sequencePower House excavation sequence