SUWECO MINI-HYDRO DEVELOPMENT PROJECTS
CAPACITY: 2.1 MW
CAPACITY: 1.5 MW
Solong Mini-Hydro Plant Project
Brgy. Solong, San Miguel, Catanduanes
SOLONG MINI-HYDRO PLANT PROJECT(REVISED QTO)
ITEM NO. ACTIVITY WT %
QUANTITY RELATIVE WEIGHT (%) %
COMPLETEDPreviou
sPrese
ntTo Date
A. CIVIL WORKS 68.051
64.313 0.150 64.46
3 94.728
B. ELECTRO-MECHANICAL WORK
14.512
14.180 0.030 14.21
0 97.916
C. ENGINEERING SERVICES 2.707 2.707 2.707 100.00
D. 13.2 KV TIE LINE, from Solong Powerhouse to Grid 0.370 0.366 0.366 99.00
E. ADMINISTRATIVE/FINANCIAL COST
14.360
14.356
14.356 100.00
% OF ACCOMPLISHMENT(ACTUAL)
95.923 0.180 96.10
3
% OF ACCOMPLISHMENT(PLAN)
100.00
100.00 0.000 100.0
0
SUMMARY OF ACCOMPLISHMENTSAs of March 1-7, 2010
Dam/Weir Structure
Headrace Pipe
Forebay Structure
Penstock Line
Powerhouse Building
Electro-Mechanical Works
Installation of Water Turbines
Installation of Water Turbines
Sub-Station of Solong Mini-Hydro Power Plant
Sub-Station of Solong Mini-Hydro Power Plant
Hitoma 01Mini-Hydro Plant
Project
Brgy. Obi, Caramoran, Catanduanes
HITOMA 01 MINI-HYDRO PLANT PROJECT(REVISED QTO)
ITEM NO. ACTIVITY WT %
QUANTITY RELATIVE WEIGHT (%) %
COMPLETEDPreviou
sPrese
ntTo Date
A. CIVIL WORKS 55.605
53.353 0.271 53.62
4 96.437
B. ELECTRO-MECHANICAL WORK
22.177
21.004 - 21.00
4 94.709
C. ENGINEERING SERVICES 3.975 3.975 - 3.975 100.00
D. 13.2 KV TIE LINE, from Solong Powerhouse to Grid 1.497 0.823 - 0.823 55.00
E. ADMINISTRATIVE/FINANCIAL COST
16.745
16.745 - 16.74
5 100.00
% OF ACCOMPLISHMENT(ACTUAL)
95.901 0.270 96.17
1
% OF ACCOMPLISHMENT(PLAN)
100.00
100.00 - 100.0
0
SUMMARY OF ACCOMPLISHMENTSAs of March 1-7, 2010
Dam/Weir Structure
Headrace Pipe
Forebay Structure
Penstock Line
Powerhouse Building