Meeting of the LCLS Facilities Advisory Committee. LCLS Project Management M. Reichanadter / SLAC. Outline. Status of the LCLS Progress in the past six months Project Management Cost and Schedule Performance Contingency Allocation Organization and Integration - PowerPoint PPT Presentation
Citation preview
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005
Meeting of the LCLS Facilities Advisory Committee
LCLS Project Management
M. Reichanadter / SLAC
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 2
Outline
Status of the LCLS
Progress in the past six months
Project Management
Cost and Schedule Performance
Contingency Allocation
Organization and Integration
Plans for the next six months
Risks/challenges ahead
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005
LCLS Project Status•LCLS Critical Decision Status;
–CD-0 Approve Mission Need – Complete (Jun01)–CD-1 Approve Preliminary Baseline Range – Complete (Oct02)–CD-2A Approve Long-Lead Procurement Budget – Complete (Jul04)–CD-3A Approve Start of Long-Lead Procurements – Complete (Dec04)–CD-2B Approve Performance Baseline – April 11, 2005
•OECM validated baseline June 7, 2005–CD-3B Approve Start of Construction – Scheduled (Mar06)–CD-4 Approve Start of Operations – Scheduled (Mar09)
•LCLS Major Upcoming Start/Completion Dates;–Start of LCLS Construction Start– Mar06–Injector Laser Commissioning Start– Jun06–Injector E-Beam Commissioning Start– Apr07 –Linac-to-Undulator Commissioning Start – Mar08–“First Light” (E-Beam through Undulator) Start – May08
•LCLS Major Upcoming Project Reviews–DOE Status Meeting – Nov17, 2005–CD-3B DOE “Lehman” Review – Feb06
•Assess readiness for start of construction
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005
LCLS Project Status (last six months) •SLAC has reorganized its divisions and upper management.
– ISMS, construction/contractor management procedures have undergone extensive revision.– Additional training for all personnel and higher visibility on safe working practices at SLAC.\– More visibility into SLAC Operations and Photon Science.
•LCLS is in the Design/Procure/Construct (execution) phase.– Safety First! Then think about schedule, technical and cost.– Performance and progress based on “earning-value” against its resource-schedule.– With CD-2b, changes are handled via LCLS Change Control Board (working well)
•LCLS Staffing at ANL, LLNL and SLAC nearing full project team (on schedule).– Strengthened Procurement and Conventional Facilities– A few positions are still open (Controls Mgr, Undulator ME’s @ SLAC, CF UTR’s)
•LCLS Procurements are going well with the dedicated cell.– Procurement team is co-located with technical team and working reasonably well.– All Injector, Linac, Undulator & CF LLP’s are well-advanced– CM/GC procurement (LCLS largest and most complex now awarded (Turner Construction).
•LCLS Technical Specifications improving.– Technical Specifications continue to mature most are now complete or nearing completion.
•Photon System (XTOD and XES) are the least mature (input from Users and final CF design
– System Integration strengthened with R. Boyce, D. Marsh and A. Chan.
•LCLS Title 2 Design is key concern.– Schedule delays (30% submission late) Cost high (working to get back in the box)
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 5
LCLS Activities @ SLAC
MMF-4,000sf facility used to tune, measure and store undulator magnets
S20-2,160sf facility Laser &
Control Rm
S24 Stairway
You are here
B750 LCLS temporary staging/storage, permanent lab,
testing and machine shop space. Share with other users, LSS?, EXO?
Remove Mark II Detector?
FFTB/BSY Vertical Wall
Project
B280 LCLS Central Design Team
2 floors, 84 offices ~13,000sf
• LCLS upgrades to the SLAC site are underway. (LLP funding)
• Shutdown allows the installation of key injector components in the injector vault.
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 6
LCLS Performance – Aug05
1.1 Project Management 8,880 8,375 8,648 -505 -273 0.94 0.97 28,970 28,970 0
1.2 Injector 7,113 6,163 6,096 -951 67 0.87 1.01 19,297 19,297 0
1.3 Linac 3,122 3,049 2,520 -73 529 0.98 1.21 26,431 26,431 0
1.4 Undulator 8,912 6,244 6,206 -2,668 39 0.70 1.01 50,724 50,724 0
1.5 X-ray Transport 4,356 4,225 4,102 -131 123 0.97 1.03 27,127 27,127 0
1.6 X-ray Endstations 721 721 680 0 41 1.00 1.06 14,779 14,779 0
1.9 Conventional Facilities 4,813 4,828 5,394 15 -567 1.00 0.89 80,649 80,649 0
1 LCLS Total Base Cost 37,917 33,604 33,646 -4,313 -42 0.89 1.00 247,976 247,976 0
315,000 315,000
67,024 67,024
31.3% 31.3%
13.6% 13.6%
2.1 LCLS Project Mgmt, Planning & Admn (OPC) 4,437 4,538 4,345 101 193 1.02 1.04 33,021 33,021 0
2.2 Injector (OPC) 699 757 578 58 179 1.08 1.31 6,107 6,107 0
2.3 Linac (OPC) 1 1 1 0 0 1.05 1.00 2,545 2,545 0
2.4 Undulator (OPC) 742 689 776 -53 -86 0.93 0.89 5,873 5,873 0
2.5 X-ray Transport (OPC) 480 412 339 -68 73 0.86 1.22 4,015 4,015 0
2.6 X-ray Endstations (OPC) 165 137 98 -28 39 0.83 1.39 5,200 5,200 0
2.9 Conventional Facilities (OPC) 0 0 0 0 0 0 0 0
2 LCLS Total Other Project Cost 6,524 6,534 6,136 10 397 1.00 1.06 56,761 56,761 0
64,000 64,000
7,239 7,239
14.4% 14.4%
LCLS Total Obligations to Date 58,430 11.5% 11.5%
LCLS Total Project Cost 44,441 40,137 39,782 -4,303 355 0.90 1.01 379,000 379,000
13.2% 13.2%
LCLS Other Project Cost
LCLS Cost/Schedule Status Report - Work Breakdown Structure
WBS Variance
Schedule
Actual Cost Work
Performed
% Complete LCLS Base Cost
% Comp LCLS Other Project Cost
Avail. Management Reserve
% Contingency / Rem. Work
% Contingency / Rem. Work
31-Aug-05
SPI CPI
Performance Indices
Cumulative to Date ($K) At Completion ($K)
Budgeted
Avail. Contingency
Work Performed
VarianceLatest Revised
Estimate
Budgeted Cost
Work Scheduled
Cost
% Complete LCLS TPC
LCLS Total Estimated Cost
• LCLS in the “green”
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 7
LCLS TEC Planned Spending / MonthLCLS PROJECT - PED & CONSTRUCTION
0
10,000,000
20,000,000
30,000,000
40,000,000
50,000,000
60,000,000
70,000,000
80,000,000
Mo S 17,613,41 1,663,846 2,281,115 2,968,973 3,286,115 4,140,441 5,962,705 5,517,648 7,741,969 6,294,452 6,155,789 5,380,789 5,463,736
Mo P 17,613,41 1,663,846 2,281,115 2,625,520 2,915,361 2,976,891 3,527,565
Mo A 17,613,41 1,663,846 2,281,115 2,876,780 2,729,733 3,335,870 3,144,993
Cum S 17,613,41 19,277,25 21,558,37 24,527,34 27,813,46 31,953,90 37,916,60 43,434,25 51,176,22 57,470,67 63,626,46 69,007,25 74,470,99
Cum P 17,613,41 19,277,25 21,558,37 24,183,89 27,099,25 30,076,14 33,603,71
Cum A 17,613,41 19,277,25 21,558,37 24,435,15 27,164,88 30,500,75 33,645,75
Prior Mo's
MAR_05 APR_05 MAY_05 JUN_05 JUL_05 AUG_05 SEP_05 OCT_05 NOV_05 DEC_05 JAN_06 FEB_06
• Variances caused by inaccurate plan rather than real schedule delay.
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 8
LCLS TEC Planned Spending / Month
• Largest variance due to plan called for full earned-value on Und materials rather than progress payment.
• We are correcting the plan.
UNDULATOR SYSTEM (TEC)- SPA
0
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
16,000,000
18,000,000
Mo S 2,965,465 281,380 402,133 257,358 958,576 1,162,423 2,884,622 1,223,069 1,423,281 1,151,226 1,596,843 1,034,532 1,288,822
Mo P 2,965,465 281,380 402,133 267,959 876,646 843,105 607,519
Mo A 2,965,465 281,380 402,133 679,807 531,300 878,825 466,762
Cum S 2,965,465 3,246,846 3,648,978 3,906,336 4,864,912 6,027,335 8,911,957 10,135,02 11,558,30 12,709,53 14,306,37 15,340,90 16,629,73
Cum P 2,965,465 3,246,846 3,648,978 3,916,938 4,793,584 5,636,689 6,244,208
Cum A 2,965,465 3,246,846 3,648,978 4,328,786 4,860,086 5,738,910 6,205,673
Prior Mo's
MAR_05 APR_05 MAY_05 JUN_05 JUL_05 AUG_05 SEP_05 OCT_05 NOV_05 DEC_05 JAN_06 FEB_06
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 9
LCLS Cost and Schedule Performance
LCLS Cost and Schedule Indices (TEC Only)
0.800
0.850
0.900
0.950
1.000
1.050
1.100
BCWP/BCWS (SPI)
BCWP/ACWP (CPI)
• Biggest SV (In, UN) appear to be due to an inaccurate plan not a schedule delay.
• Call for managers to utilize a 6-mo look-ahead
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 10
LCLS Summary Schedule – Aug05Highlights
• Schedule Float
•Mar05 213 days•CP - Und B.O. - Und Inst to 1st Light
•Maintained full schedule float on critical path
• Starting construction on schedule is key
• CP - Und B.O. – Inst to 1st Light
• FY05 Shutdown•~1 month
• FY06 shutdown •~ 4 months
• FFTB Shutdown•Jul06•LCLS may request advancing this date
DOE Milestones
Major LCLS Milestones
Conventional Facilities Sector 20 Injector Facility
Linac Facility
Main Control Center
Magnetic Measurement Facility
Undulator Hall
Other Facilities (Undulator,BD, RY, NEH, FEH,FEE, BTH,CLOC & X-Ray Xport)
Injector Drive Laser
RF Gun
Linac Design/Procurement
Installation
Undulator
Design
Testing at MMF
X-Ray Transport & Diagnostics
Commissioning Diagnostics
X-Ray End Stations
Operations
FY 2009OCT JAN APR JUL
FY 2008OCT JAN APR JUL
FY 2007OCT JAN APR JUL
FY 2006OCT JAN APR JUL
FY 2005OCT JAN APR JUL
FY 2004OCT JAN APR JUL
T1 Title 2 Construction
Title 1 Title 2 Construction
T1 Title 2 Construction
Title 1 Title 2 Construction
Design/Procure
Design/Procure
Commission
L1, BC1, L2, BC2, L3, & LTU, E-Dump
Commission
Design
F/MM
Commission
Operations
Design/Procure
Commission
S20/Alcove B.O. Linac B.O.
BD B.O.
MCC B.O.
MMF
CD2bCD3a CD3b CD4
FFTB Shutdown
Rcv 1st Arts
LCLS ARR LCLS Start Operation (X-Ray to Far Hall)
Start Proc for
T3 Constr
Laser Design/Procure/Assy
MMF
Drive Laser RFP
CableplantX-Band Klystron
Ti Strongback
Magnet Blocks
Magnet Poles
Del of 1st Arts to MMF
Install
Title 1 Title 2 Construction
CLOC B.O.
XTOD B.O.
FEH B.O.
FEE B.O.NEH B.O.
Procure
Drive Laser Award
L1, BC1
1st Light
L2,BC2,L3
E-Dump Install
LTU Install
BTH B.O.
UV Beam to Cathode
33 Prod UndsReceived
Injector Accelerator ARR
Linac ARR
Start Injector Comm (Drive
Laser)
Wall Region Install
Heater Region Install
Accelerator Region Install
Gun Region Install
Inject RF Install
Spectrometer Install
Commission C/O
Injector ARR
Laser Heater Install
Solid Attenuator Install
Gas Attenuator Install
Tunnel Mech/Vac InstallAward Initial Funding
Design/Procure 2-D X-Ray Detector Install
Install
Commission
ConstructionTitle 2UND B.O.
Title 1
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 11
LCLS L1 – L2 Milestone Performance
LCLS showing good milestone performance @ L2 in FY05
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 12
LCLS L3 Milestone Performance – FY05
LCLS showing good milestone performance @ L3 in FY05
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 13
LCLS L3 Milestone Performance – FY06
FY06 will be a key year for LCLS.
Boost Phase
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 14
Contingency Allocation to Date
•CF: Interim work on CF + T2 increase, MMF and S20. CM/GC and 30% estimate overruns will require significant additional contingency.
•UN: Undulator materials
•Apr05 rebaseline covered schedule variances in Injector-Linac.
# of BCR's since April 2005
Total: 77BCR's
0
5
10
15
20
PM INJ LN UN XTOD ES CF CT
Contingency Allocation (Oct04 - Present)Total $11.97M (~$1.1M/mo)
-1,000
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
PM IN LN UN XT XE CF
AY
K$
77 BCR’s is high 5 months after baseline
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 15
LCLS Contingency Performance
LCLS Contingency Trend
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
35.0%
40.0%
% Complete BCWP/BAC
Cont/(BAC-BCWP)
Contingency allocation has been reasonable to date. CM/GC + 30% CF estimate will make large draws on contingency in Oct05.
Need to hold the line on contingency until Mar06 (CF construction bids).
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 16
LCLS Procurements and Subcontracts
$0
$10,000
$20,000
$30,000
$40,000
$50,000
$60,000
$70,000
FY05 FY06 FY07 FY08 FY09
AY
K$
T3 Constr
SLAC
LLNL
ANL
AYK$ FY05 FY06 FY07 FY08 FY09 TotalANL $2,219 $15,646 $13,244 $62 $2,104 $33,274LLNL $30 $2,863 $2,615 $4,502 $1 $10,011SLAC $12,425 $14,310 $16,617 $15,514 $4,565 $63,430T3 Constr $2,541 $20,246 $29,993 $5,701 $0 $58,481Total $17,215 $53,064 $62,468 $25,779 $6,670 $165,196
•All major LLP’s are under contract.
•Drive Laser
•Streak Camera
•BC1/BC2 Magnets
•RF X-band (SLAC)
•RF Gun (SLAC)
•Ti Strongbacks
•Magnet Poles
•Magnet Blocks
•1st Und Article
•S20 Facility
•MMF Facility
•Some smaller (less critical) items yet to be procured.
•Laser and Conv Fac are most critical to maintaining schedule.
LCLS Long-Lead Procurements
CM-1
CM-2
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 17
LCLS Technical Specifications
•Technical baseline specifications are defined via;
•GRD
•PRD’s
•ESD’s
•ICD’s
•RDS’s
•Technical specs under configuration mgmt
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 18
LCLS Technical Specifications StatusLCLS Specs
• Jul05• PRD’s @ 37%• ICD’s @ 5%
• 67% is a big improvement but still more to go
• ESD’s particularly IN, LN, and UN need more effort.
• Physics support being added to Photon System
Requirements Document
Total No.
Documents
Number
Approved
Number in Sign-Off
% Complete
Comments
Global Requirements Document (GRD)
1
1
0
100
Complete
Physics Requirements Documents (PRDs)
57
43
1
75
PRDs decreased from 64 to 57
Engineering Specification Documents (ESDs) Management Physics Liaison Support Controls Injector Linac Undulator X-R Endstations Conventional Facilities
104
2 8 4
40 19 8
15 8
53
2 3 3 31 7 0 0 7
0 0 0 0 0 0 1 0 0
51
100 37 75 77 37 0 0 87
Room Data Sheets (RDSs)
58
49
0
84
RDSs reduced from 59 to 58
Interface Control Documents (ICDs) Injector Linac Undulator X-R TOD XES
11 3 4 1 2 1
9
3 4 1 1 0
0 0 0 0 0 0
82
100 100 100 50 0
Linac ICDs reduced from 32 to 4. Undulator ICD reduced from 2 to 1.
Total
231
155
2
~67
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 19
LCLS Project Organization (Sep05)
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 20
LCLS Staffing
• 112.0 FTE’s (Sep05)• Staffing nearly complete• Still a few more to go• Does not include
additional staff under contract
– Jacobs– PMCS – AIM– Consultants– CM/GC (Oct05)
Actual Reported LCLS FTE's @ SLAC
0
20
40
60
80
100
120
FT
E's
FY05 funding @ SLAC
Treading water. CR or full-funding?
Award Title I
• Good News: LCLS has staffed up at planned rate.
• Are they all working on the right things?
LCLS Estimated FTE'sFY2004
(actuals) FY2005 FY2006 FY2007 FY2008 FY2009* TOTAL ANL 11.2 15.59 20.76 13.01 2.82 0.33 63.71LLNL 5.4 8.7 10.43 11.77 10.46 5.72 52.48SLAC 40.2 88.48 107.79 106.5 74.59 51.69 469.25Total 56.8 112.77 138.98 131.28 87.87 57.74 585.44
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 21
Davis – Bacon Approval
Thanks to Richard M for working this issue!
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 22
Plans for the Next Six Months (Apr05)
CD-2b (Approve Performance Baseline) doneCD-3a (Authorize Long-Lead Procurements) doneMake plans for full FY05 funding (~$54M) doneGet funds out to partner labs doneStaff up particularly in Ctrls, PM, and Engr doneEstablish colocated procurement cell & staff doneAward Long-Lead Procurements done
Laser, Undulator, MMF, S20Authorize Title II (Jacobs) donePut out SOW for CF Constr Mgmt done
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 23
Plans for the Next Six Months (Oct05)
Make plans for full FY06 funding (~90$M). Phase-fund construction sub-contractsComplete T2 (Jacobs) Design (on schedule, within cost estimate)Prepare for start of construction (Turner)
Prepare independent cost estimate to validate JacobsDevelop construction sequence to minimize impact on SLAC opsPrepare procurement subcontract packages
Prepare project for CD-3bPSAD, PEP, FHA, etc.Independent “Lehman” Review on Readiness
Strengthen System IntegrationDesign Reviews and Technical SpecificationsRisk Registry
Continue good performance on cost, schedule, milestones and procurements
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 24
Near-term LCLS challengesLCLS is the execution phase of the project. Plans are planned, costs estimated, project approved … now it’s time to execute.
FY05-FY06 critical time (boost phase) of the project. Performance (solve problems, make decisions) is key.Follow P3. Watch staffing levels via variances. (Use the 6-month look ahead as a roadmap)Use the Risk Registry pro-actively to manage work (not just a DOE requirement)
FY06 Continuing ResolutionPlanning estimates show enough carryover (due to the FY05 CR) to cover one quarter.
Beyond a one-quarter CR, LCLS will need to defer procurements to retain core staff.
Prepare for start of LCLS Construction (CD-3b)T2 CF is critical path for construction startCM/GC on-board (Good news!)PSAD will require effort from all of LCLS
System Engineering and IntegrationContinue documenting PRD’s, ICD’s, etc.. Mature design reduces risk.RMB and DM will help to provide uniformity and high-quality across the LCLSSustained effort on design reviews will help to validate progress and identify integration issues early on.
Mark Reichanadter
LCLS FAC Meeting [email protected]
Oct 27-28, 2005 25
Summary
Good performance thus far (15% comp)SLAC is organized to support the LCLSLCLS is ~fully staffed up at all LabsMMF/S20/S24/FFTB under constructionUndulators under fabricationOverall milestone performance is goodShutdown going reasonably well so farT2 >30%, CM/GC on-boardLCLS ISMS is the priority.