View
219
Download
6
Tags:
Embed Size (px)
Citation preview
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
LCLS Undulator System Update
FAC Review
October 29th(30th&31
2007
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
ANL/LCLS Undulator Project Management Chart
Bill Berg
Lori Cesario
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
ANL/LCLS Undulator System Integration Engineer
BERG, WILLIAM Argonne National Laboratory
9700 S. Cass, IL 60439
Extension:2-6929
BLDG 401-B2199
Radio Page:4-1882
E-mail Page:[email protected]
E-mail Address:[email protected]
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
ANL/LCLS Undulator System Program Control Management System (PCMS)
Fran Clark retired in September 07 – STA advisor when required
Lori Cesario now ANL PCMS main point of contact
Lori CesarioArgonne National Laboratory
9700 S. Cass, IL 60439
Extension:2-7389
BLDG 362 C169
E-mail Address: [email protected]
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
ANL LCLS Major Effort Covered for FY08
09/07 – Completed FY08 Agreement sheet estimates for ANL/LCLS workers
10/07 - ANL management agree LCLS effort profiles for FY08
1.4.1 Management:
Hired Integration Engineer (replacement for Pile)
Secured 2 QA Engineers/Reps(~ 1 FTE) thru Sept 08
Secured 2 QC coordinators for Progress, Task Coordination & Documentation ~ thru July08
Added part-time secretarial assistance
1.4.2 Controls:
Sufficient Effort available - continued support required
1.4.3 Undulator Magnet and Support:
Sufficient Effort available - continued support required
1.4.4 Undulator Vacuum System:
Sufficient Effort available - huge effort is required to meet schedule
1.4.5 Diagnostics:
BPM - Additional engineering and technician help added for BPM production
BLM - Sufficient Effort available - Using almost one extra FTE from Diagnostics group
- huge effort is required to meet schedule for both BPM and BLM
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
ANL LCLS Effort Profile/Plan FY08/09
ANL production engineering effort drops off significantly in March/April 08ANL production engineering effort drops off significantly in March/April 08
April through July 08 technical leads and key players left to help with delivery and April through July 08 technical leads and key players left to help with delivery and installation issuesinstallation issues
Documentation hand over will be covered through September 08Documentation hand over will be covered through September 08
July 08 through September 08 only key 1.4.1 management left. All management effort is July 08 through September 08 only key 1.4.1 management left. All management effort is reduced by 50% reduced by 50%
End of September 08 – ANL plans to be off the projectEnd of September 08 – ANL plans to be off the project
FY09 ANL has small budget to contribute to Undulator CommissioningFY09 ANL has small budget to contribute to Undulator Commissioning
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
LCLS Installation and Commissioning Time-LineLCLS Installation and Commissioning Time-Line
linac/BC2 Install linac/BC2 Install
2007200720072007
LTU/Undulator System LTU/Undulator System instalation Check instalation Check
out/Commissioning out/Commissioning
AAAA SSSS OOOO NNNN DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ
Inj./Linac/BC2 Inj./Linac/BC2 Commissioning Commissioning
Beneficial Occupancy.Beneficial Occupancy.Und. Installation Und. Installation
LTU/und.LTU/und.hall “Co occupancy.”hall “Co occupancy.”
2008200820082008
“Dirty Install”
Prep for Support Stand Installation
Girder Installation
Starts
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
0
5
10
15
20
25
30
35
40
45
Support Motion
Support Motion Est
Quadrupole
Quad Est
Vac Chamber
Vac Chamber Est
Vac Supports
Vac Supports Est
Vac Bellows
Vac Bellows Est
Vac Spools
Vac Spools Est
BFW
BFW Est
BPM
BPM Est
BLM
BLM Est
Tuning
Tuning Est
Girder Assembly
Girder Inst
Current ANL delivery schedulesCo-occupancyUndulator Support StandsCables/Cable Trays
Beneficial OccupancySupport Mover SystemGirders, Control Electronics
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
Major Deliverables& Concern factors scaled to 10 (0-5 schedule 0-5 technical)
1.4.1 Management:
Safety
Quality Assurance
Budget and Schedule
Integration and Installation
Admin. – Procurement, vendor management and documentation.
1.4.2 Controls: 5 (4s -1t)
Cables (tunnel and inter-undulator): cable trays, and racks.
Motion controls: sub micron leveling, control algorithms and software.
Ancillaries: Thermal monitoring, undulator limit switches etc.
Vacuum controls: Interface integration only – some limit protection.
Diagnostic controls: Beam Finder Wire, Beam Position Monitor, Beam Loss monitor etc. Integration of Wire Position Monitor (SLAC component)
Communications: Integrated Tunnel Electronics Rack with on board IOC etc. EPICs programming.
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
Major Deliverables & Concern factors scaled from 0 to 10
(0-5 schedule 0-5 technical)
1.4.3 Undulator Magnet and Support: 4 (3s+1t)
Undulator Magnet Assemblies
Quad magnets and translation stages
Fixed Supports and Motion Systems
1.4.4 Undulator Vacuum System: 7 (3.5s+ 3.5t)
Aluminum Vacuum chamber + Support and leveling System
Pumping – acquisitions move to SLAC
Bellows
1.4.5 Diagnostics: 8 (5s+3t)
Beam Position Monitors
Beam Loss Monitors
Beam Finder Wire
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
1.4.3 Magnets and Supports
Undulators
39 Undulators @SLAC 1 Undulator @Argonne
Support Mover System
1 Support & Motion System @Argonne8 Support & Motion Systems @SLAC4 Support & Motion System @Hi-Tech ready to shipRemaining 25 Support & Motion Systems now in production @Hi-Tech/Metalex
Date
Totals SM systems Delivered to SLAC
(current estimate)
10/24/2007 8
11/7/2007 12
11/21/2007 18
12/7/2007 23
12/21/2007 28
1/15/2008 33
1/23/2008 38
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
Quadrupoles
Two 1st articles - marginally low in field
They were rejected and the revised design has 123 laminations instead of 115.
Two new replacement first articles are in production and will be delivered to ANL this week; we have negotiated with ET to speed up the rest of the schedule and bring us back on track.
1 production Quadrupole stage is at Argonne;
the rest were delivered to SLAC.
Date
Totals Delivered to SLAC
(current estimate)
11/5/2007 1
11/13/2007 2
11/19/2007 3
11/29/2007 5
11/29/2007 7
12/4/2007 11
12/19/2007 15
1/9/2008 19
1/18/2008 23
1/30/2008 27
2/8/2008 31
2/19/2008 35
2/25/2008 37
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
Long Term Test Update
Final Design 1st Article support stands and girder delivered to ANL – installed QA accepted in September 07.
The support motion and girder assembly installation process is a “work in progress” – see LTT slides
The pre-production girder has been cut in half. We are using it with the two pre-production supports to create the short and long break sections too.
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
1.4.4 Vacuum System
Un-resolvable questions with Stainless Chambers -Decision made in September 07 to build production
Extruded Vacuum chambers
Two full sized Aluminum prototypes have been built.
All planned fabrication steps have been performed.
The chambers have been baked and their measured out-gassing rate is lower than the specification
Many preparations for production are in-process or in place.
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
Aluminum Extrusion
Prototype Conclusions…
The extrusion can be manufactured and machined with wall thickness and straightness required to meet final installation tolerances. The full length chamber can be produced within all acceptable dimensional tolerances.
Uniform 0.5 mm nominal wall thickness and vacuum integrity required to maintain the specified average pressure was achieved.
Average surface finish achieved in testing - meets current PRD spec.
The polishing process improves the surface finish without introducing contaminants
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
1.4.4 Vacuum System
ANL will be the “General Contractor” for manufacture of the Aluminum Extruded Vacuum Chambers
Extrusions (in House)Explosion bonded C-fix Flanges (on order)Extrusion Polishing in process (outside Vendor)Extrusion Machining in process (outside vendors)Ready for flange welding and vacuum processing (in House) Significant in house Engineering and QA oversight required
Outstanding progress so far on very demanding schedule (almost parallels SS working schedule) but experienced group fully committed to meet it.
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
The Schedule… The Cost……Event Original Completion
DateUpdated Completion Date
Polishing of all extrusions
12/07/07 11/30/07
Machining of all extrusions
4/21/08
Chamber Processing at ANL
4/23/08
Ship Chambers 1-5 to SLAC
1/23/08 2/1/08 1-6
Ship Chambers 6-10 to SLAC
1/28/08 2/22/08 6-11
Ship Chambers 11-20 to SLAC
3/10/08 3/14/08 11-22
Ship Chambers 21-30 to SLAC
3/26/08 4/4/08 22-33
Ship Chambers 31-40 to SLAC
4/25/08 4/29/08 33-40
Cost Items Updated Estimates and Quotes…Oct 07
Extrusions $11,165.44
Flanges $41,310.00
Polishing Prep $350.00
Polishing $152,819.85
Straightening $15,600.00
Machining $238,400.00
Crating $4,979.60
Surface Sampling $5,040.00
ANL labor ~$220,000
Total $689,664.89
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
BPM Status
X-Band Cavity BPMDevelopment phase complete Production procurement in placeFirst machined production units expected in November
Receiver Electronics4 First article prototypes assembled and tested with good results3-BPM testing prototypes incorporate receiver, local oscillator and filter first article packagingProduction procurement ongoing -10 units at SLAC 1/4/08, 20 units by 1/5/08, 30 units by 1/6/08, 40 units by 1/7/08
Test QualificationSuccessful collaborative effort testing and qualifying BPM system Qualified system with the same ADC (PAD) as SLAC LINAC BPM upgrade to minimize risk of integration
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
Comprehensive BPM Test Program
1 m Resolution spec met: (09/27/07) < 0.6mLong term drift spec for 1 hour spec metGain stability spec met1 hour temperature stability spec met24 hour temperature stability spec met electronics with simulated beam
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
Cavity BPM Production Status
Cavity BPM machining contracts placed with parts expected 11/27/07
Two vendors will provide a single machined First Article production BPM for evaluation
Vacuum window first lot delivery 11/12/07
Vendor for brazing BPM pending contract award
Group & # Totals Delivered to
SLAC
Date
RFI: Group A(2) 2 1/15/2008
RFI: Group B (6) 8 2/17/2008
RFI: Group C (10) 18 3/15/2008
RFI: Group D(8) 26 4/16/2008
RFI: Group E(10) 36 5/10/2008
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
1.4.5 DiagnosticsBeam Finder Wire
Weldment, Machined Parts, Chamber, Catalog Items and all Hardware Design and Procurement Documents are complete and are in the procurement and production phase.Wire Card is currently under final design at SLAC.Alignment and Assembly Procedures are 90% completeSchedule for production looks tight and will require good vendor management to keep on target
• Lot #1 ( 3) 12/12/2007 Beam Finder Wires at SLAC • Lot #2 (10) 1/14/2008• Lot #3 (10) 2/11/2008• Lot #4 10) 3/20/2008
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
BFW Assembly (Body Sectioned) Wire Card Down in Inactive Mode
Wire card(Down Position)
Lower Limit Switch(Actuated Position)
Pneumatic Solenoid Valve(Cylinder Vent Position)
Internal Return Spring(Expanded Position)
Electrical Connectors(Down Position)
Internal Kinematic Stop Plates
(Open Position)
Bellows Seal(Compressed Position)
BEAM
Potentiometer (Out Position)
From J. Bailey et al.
1.4.5 Diagnostics
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
1.4.5 Diagnostics
Beam Loss Monitor
Engineering re-design - design is for MPS system and not Diagnostic
PRD complete – This design does not meet PRDCurrent proposal for BLM is only as an MPS input for now
Even in simple form the cost and schedule is still of concern.
Future ANL/SLAC collaboration on upgrade may be viable later?
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
Beam Loss Monitor A Simple MPS/Beam Loss Monitor system for now!
Production design will inhibit beam when beam loss is detected above a pre-determined set-point. Requires limited dynamic range from the detector(s)
Expect to install in undulator tunnel July 08
****************************************************************************************************
A more Sophisticated BLM may be required – no reasonable solution available at present.
Future design will meet PRD requirements. This design will keep track of the total accumulated exposure of the magnets in each Undulator. Helps predict, understand and curtail operational scenarios that may cause long term magnet damage. Requires a large dynamic range for the radiation detector(s) and much more sophisticated electronics and software.
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
Production BLM design
Detector Moves with the Undulator and
protects during undulator roll
out
Geoff Pile
LCLS Und. System Update [email protected] 29th, 30th& 31st October 2007
SummaryGood progress is being made in all areasHot spots
QuadrupolesSchedule – close attention req.
Vacuum Flanges Very finicky – “first time” sealing <100% Good QA, inspection and careful handling required
Vacuum ChamberProduction quality, surface finish, straightening and machining all require careful oversight
BPM moves into ProductionLots of oversight required
Beam Loss MonitorCompletion of design
Final Large Procurements Vacuum Chamber Machining BPM body manufacturing, BPM electronics manufacturing
Schedule ConcernsRF BPMVacuum ChambersBeam Finder Wire CardBeam Loss Monitor