26
Javier A. Sevilla CF Commissioning Plan-FAC Review [email protected] rd.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group Conventional Facilities

Javier A. Sevilla CF Commissioning Plan-FAC [email protected] June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

  • View
    219

  • Download
    2

Embed Size (px)

Citation preview

Page 1: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 20081

CF LCLS Commissioning Plan

Javier A. Sevilla

Engineering Group

Conventional Facilities

Page 2: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 20082

Outline

Plan

Team

Commissioning Process

Activities

Deliverables

Summary

Page 3: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 20083

Beam Transport Hall Undulator Hall

Far Experimental Hall

Electron Beam Dump

Front End Enclosure

Near Experimental Hall

X-Ray Transport & Diagnostics Tunnel

Commissioning Areas

Central Utility Plant/ 12Kv Substation 522

Page 4: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 20084

Commissioning Plan

1. Defines Scope of CxA and requirements

2. Part of contract documents for each MEP subcontractor

3. Part of TCCo Contract

http://www-ssrl.slac.stanford.edu/lcls/cf/commissioningplan/

Prepared by

Page 5: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 20085

Scope Definition for CxA

1. List Requirements

2. List Deliverables

3. List team members

4. Provides all reference documentation

https://www-lcls-internal.slac.stanford.edu/projectspace_L2/Project_Office/SOW/ConvFac/1.9-703-r0.pdf

Page 6: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 20086

Team

Commissioning Agent (CxA)

Engineering Economics Inc. (EEI)

CF Engineering GroupCF Construction GroupLCLS QA ManagerTurner

MEP CoordinatorCx Coordinator

SLAC Facilities DeptHVAC, Electrical, Fire Alarm, Ops Mechanics

SubcontractorsO. C. McDonald-HVAC & PipingAlpha Air Balancing AgencyCupertino Electric (CEI)Air Systems, Inc. BMSCeitronics-Fire AlarmMitsubishi-ElevatorAllied CranesRCM-Fire Protection

Page 7: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 20087

Commissioning Agent (CxA)Engineering Economics Inc (EEI)

Selected by using a competitive bidding processFive bids received (AEC, EEI,AEI, and WBI)EEI has offices nationwide and able to shift resources if necessaryCommissioned over 33 million sf

Data centers, office buildingsMedical research labsPharmaceutical labsFederal facilities

LCLS Sector 20 Injector Facilities - successfulLCLS Magnetic Measurement Facilities - successful

Page 8: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 20088

Commissioning Meeting

May 2-08 Weekly Meetings

Started in Nov. 14, 2007- Meetings every 3 weeks

Page 9: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 20089

Commissioning TeamCF LCLS

K. AhmedR. BaclitD. CiorbeaR. MaggiJ. SaldivarJ. A. SevillaL. ShewchukK. Yang

QA ManagerD. Marsh

ESH/BIOR. KerwinE. GomesB. Smith

Subcontractors-TCCO

A. PimentelF. SiscaC. FarnellR. GonzalesG. StricklandJ. FitzgeraldH. LimosneroK. MinchacaD. SwartzR. SpinaR. FurtadoT. LocatelliM. Clayton

SLAC Facilities

B. ChoateG. KuraitisR. RadauK. ChanR. CandelarioB. HarrisonP. FranciscoS. PoitierS. JensenJ. Kang and HV electriciansJ. PfefferkornF. Castillo and LV electriciansK. JoongN. YeungR. ZingsheimEEI

K. QuigleyA. ParkerM. Abrahamson

Page 10: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200810

Commissioning Team at Work

Page 11: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200811

Commissioning Process

PLAN

http://www-ssrl.slac.stanford.edu/lcls/cf/commissioningplan/

Resources (CxA, CF Engrs, TCCO, Subcontractors, Facilities

Requirements (FT, PFT, Acceptance, Inspections)

Configuration Control of test results, observations, inspections, minutes, schedule, acceptance, etc.

Configuration Control of tests results, inspections, training, documentation, acceptance, etc.

Page 12: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200812

Configuration Management Cx Process

ftp://ftp.slac.stanford.edu/groups/lcls/Turner/LCLS%20Commissioning%20Process/

Page 13: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200813

Commissioning Process

Activities

Review of design documents by CxA

Site inspections (CxA, Facilities Dept, CF LCLS)

Prepare list of observations (by Category)

Review of Constructions checklists (CxA and Facilities Dept)

Witness some PFT (CxA)

Perform ALL Functional Testing (FT)

Page 14: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200814

CUP Plan View Drawing M0203

Electrical Rm

Chillers

Boilers

Mech Room-NEH

Page 15: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200815

CUP On-Going Cx Activities

Substation 522

CUP transformers

Chillers SwitchgearBoiler

Page 16: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200816

Commissioning Activities Completed

Substation S522Energized and completed except pending punch list

Rating capacity 4,000 amps, 12.47 KV

Provides power to LCLS three 2.5MVA transformers and others

New medium pressure underground natural gas piping to CUP: 1,400 LF

30 Million BTUHs nominal capacity

BTH West Construction

BTH Switchboard ( 480 v, 3 ph, 800 Amps)

Page 17: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200817

LCLS Substation S522

Substation 522 behind the CUP

12.47 kv Switchgear inside

Page 18: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200818

CENTRAL UTILITY PLANT (CUP)

Major Equipment to CommissionTwo Chillers (425 tons/ea), Primary and Secondary CHW loops and Pumps BTH,UH,EBD,FEE, NEH and FEHOne Boiler (150 BHP/ea) Primary and Secondary HW loops and pumpsDDC Temperature Control System to be connected to SLAC network via ALC Web ControlInterface with EPICS (Technical systems)One Air Compressor (268 SCFM@150psi), Air Dryer and Receiver.

Will provide service to: BTH, UH, EBD, FEE, NEH,X-RAY, FEH Wet Sprinkler System-Ordinary Hazard Group 1

One AHU for electrical roomMechanical rooms for NEH HVAC system (MAU) and AHU’s

Page 19: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200819

Chillers Room in CUP

Page 20: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200820

Deliverables

Final Commissioning Report

Pre-Functional and Functional Test Reports (FT), PFT, Checklists, observations. Etc.

O&M MEP

Training Records

All documentation available for future operations and maintenance

Page 21: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200821

SummaryRoles and responsibilities are clearly defined in the Commissioning PlanExpectations are documented and well understood!CxA reports to CF LCLS and collaborate with TCCO, MEP subs, SLAC Facilities maintenance and operations staff Goal is to deliver a complete and functional project with all MEP systems fully operational, inspected, tested, checked, verified and documented!

Page 22: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200822

End of Presentation

Supporting Documentation to Follow

Page 23: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200823

Partial List of MEP Equipment

Page 24: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200824

Minutes of Meetings

Page 25: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200825

Review Documentation and PFT

Page 26: Javier A. Sevilla CF Commissioning Plan-FAC Reviewsevilla@slac.stanford.edu June 17, 2008 1 CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group

Javier A. Sevilla

CF Commissioning Plan-FAC Review [email protected]

June 17, 200826

CUP Plan View Drawing M0203

Electrical Rm

Chillers

Boilers

Mech Room-NEH