Page 1: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

LCLS Undulator System Status and Schedule

Geoff Pile

Page 2: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Safety Minute

Two really important statements –

1. Never Underestimate the Power of Co-incidence (There could be more safety issues less obvious than the one you are trying to negate)

2. ISM – Do what you say you do!

Define the scopeAnalyze (ALL) hazardsDevelop/implement controlsPerform the work within controlsFeedback & improvement

Even though you wear your PPE you’re not always as safe as you might think. This guy is wearing his face mask while arc welding. In this case, it’s almost as useful as an ashtray on a motorbike.

Page 3: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

All Argonne girder components are planned to be available at least 1 month before the P3 “Early Start” of Girder Assembly

Schedule Considerations

Page 4: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Controls Status and Schedule

Controls -1.4.2 – Work Remaining

Undulator In-tunnel Rack (UIR)

Intra Undulator Cables

Electronic Interface Assembly (EIA)

Page 5: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

1.4.2 - Controls

Ongoing Work

Completed

Page 6: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Undulator In-tunnel Rack (UIR)

Page 7: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Undulator In-tunnel Rack (UIR)

Page 8: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Electronic Interface Assembly (EIA)

~1800 Intra Undulator Cables(pre-made/pre-

tested)

Page 9: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Undulator Magnets and Supports 1.4.3

Undulators (39 @ SLAC 7/2007)

Support & Motion System - girder, cam movers & fixed supports (37@SLAC 3/2008)

X translation issue

Quads and Correctors (36 @SLAC 4/2008)

Page 10: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

1.4.3 - Magnets and Supports

Ongoing Work

Completed

Page 11: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

All 40 undulators were completed by July 2007

Page 12: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Girder Manufacture at Metalex Critical

Engineering and QA Oversight by Argonne

Girders Assembled and Packed at Hi-Tech

Page 13: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

X Translation Stage, Limit Switches, and Adjustable Switch Actuator

Page 14: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Obtaining X Translation Limits & Stops

Page 15: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Tuning block modification

Page 16: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

1.4.3.5 - Quads and Correctors37 magnets and 2 sets of

spare coils completed 4/08

Page 17: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Vacuum Systems 1.4.4

46 Vacuum Chambers produced Manufacture started September 2007 & ended May 2008

33 required

7 spares

1 LTT

5 sacrificed for surface finish measurements

Monumental task, huge effort, successful ending.

Interest has already been expressed in this technology by other projects around the world.

Page 18: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

1.4.4 - Vacuum

Page 19: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Inspection and correction of the LCLS VC end flange

perpendicularity

Inspection of the total Inspection of the total length of the LCLS length of the LCLS Vacuum ChamberVacuum Chamber

Page 20: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Surface Finish Data of 46 Chambers…33 required (7 spare – 5 sacrificed – 1 LTT)

Desirable

Acceptable

Not Desirable

Should Avoid

Slope Criteria from H-D Nuhn adjusted for the oval shape

Longitudinal:

Transverse:

The transverse rms slope tolerance is 60 mrad

Extrusion # h (mm) rms transverse slope (mrad) rms longitudinal slope (mrad)1 353.57 45.45 17.362 216.02 20.03 7.983 248.52 27.78 8.534 236.10 23.69 12.295 261.25 23.03 9.476 271.06 37.19 13.528 302.81 32.23 14.069 251.17 31.14 19.1211 230.72 25.14 9.82

12 294.41 27.43 15.5713 308.75 26.59 12.6414 350.85 38.58 19.3715 306.37 34.49 15.0417 324.34 26.67 16.2018 341.19 50.46 20.5019 246.35 24.78 11.6220 244.29 18.58 8.0821 331.53 34.12 15.4822 268.19 36.40 14.2623 275.33 40.43 18.5624 229.15 23.36 10.8325 258.43 28.51 10.1426 325.92 46.87 18.4627 327.66 53.97 23.1029 327.50 38.76 20.3630 317.95 45.59 18.9131 334.76 47.89 19.9632 230.19 25.44 12.6533 230.15 21.74 10.2734 294.70 44.42 16.3236 245.60 23.85 8.9337 198.97 17.83 6.8538 345.21 48.72 22.8639 311.58 51.02 18.6240 311.04 35.81 15.3341 341.13 49.27 15.5842 233.57 22.24 10.9943 342.60 56.25 21.7444 321.34 52.82 18.6745 332.56 52.82 19.0446 254.38 29.50 10.34         Totals (rms) 36.94 15.52

Page 21: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Diagnostic Systems 1.4.5

BPM – 1.4.5.5

BFW – 1.4.5.6

BLM – 1.4.5.8

Page 22: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

1.4.5.5 - Diagnostics - BPM

Page 23: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

BPM Testing at Argonne

Page 24: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Beam Position MonitorLarge effort- solved serious production problems

Many brazing issues

(differential thermal expansion)

Window QA problems

Multi-step Process now

understood

8 now delivered to SLAC

-remainder on track

Promising World Class Diagnostic

Page 25: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

1.4.5 - Diagnostics – BFW & BLM

Page 26: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Beam Finder Wire

All production problems are resolved at this point, but we were somewhat delayed due to issues with repeatability, chamber coating, and electronic modules.

Two units that should have shipped last week are on the way to SLAC at this time.

Details in Dean Walters’ talk

Page 27: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Beam Loss Monitor

Five production BLMs will be used to protect the undulators by inhibiting beam bunches following an “above-threshold” radiation event.A joint R&D effort is aimed at enhancing these 5 units to enable LCLS to track each undulator’s accumulated radiation dose.

Undulator protection is the highest priority. The BLM will be integrated into the Machine Protection System (MPS) and requires only limited dynamic range from the detectors.Dose tracking will enable long-term magnet damage to be characterized, but requires a radiation detector with large dynamic range (order of 106) and sophisticated diagnostics hardware and software.

30 production BLMs may be built in FY09 if R&D is successful

Page 28: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

BLM in Inserted Position(Can be easily made to track out

with Undulator)Interface Module

Beam Loss Monitor

Page 29: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Long Term Test

Page 30: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Long Term Test

Page 31: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Long Term Test

Page 32: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Status and Schedule

Undulator System Management and IntegrationCPR & Costs to go –

Generally in good shape. Some unplanned effort has been required in the last two months to solve problems and meet production schedules. Most spares costs were moved to OPC. Final spares costs will be recalculated using actuals and any required adjustments will be made.

Green Sheet SystemA Web-based, almost real time, method of managing Argonne-APS cross- matrixed effort – (up to 60 staff 18FTE’s/year)

ASK SystemA Web-based method of managing deliveries and technical documentation. A dictionary/index style look-up system.

Page 33: Geoff Pile FAC Review - Undulator Systempileg@aps.anl.gov 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile

Geoff Pile

FAC Review - Undulator System [email protected]

17 June 2008

Summary

Almost all deliveries complete by July 2008!Production BLMs? TBD (2009)

Argonne Construction team rolls off the project in JulyArgonne Management team drops to half-time in mid-July, and rolls off the project in September.FY09 – a small budget is included for installation and commissioning support