14
Corey Harpe Fossil Hydro Operations Co-op Development Program May 5 th 2016

End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Embed Size (px)

Citation preview

Page 1: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Corey HarpeFossil Hydro OperationsCo-op Development ProgramMay 5th 2016

Page 2: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

About Me■ University of Florida

– Junior: Mechanical Engineering

– Graduation: May 2018■ How many rotations with Duke Energy?

– Session 1: High Energy Piping at Crystal River Steam Plant

■ Central Engineering – Inspection Services

– Mentor: Chris Barbee

– Supervisor: Scott Bowes

– Director: Robert Hathorn

Page 3: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Today’s Discussion

• My Safety MomentI• Responsibilities this RotationII• Inspection Drawings Project

• Intro – Benefits – Moving ForwardIII

• Hanger Weight Analysis Project• Intro – Benefits – Moving Forward

IV• Tour of Crystal River Nuclear PlantV• Looking AheadVI

Page 4: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

My Safety Moment

Hard Hat Required

On my first day at Crystal River, Chris and I were walking down the inspection locations with scaffolding contractors. On top of the boiler I ran into a steel beam and it knocked my hard hat off and smacked my forehead. Lesson learned to carefully plan out walking paths and to take your time.

Page 5: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Responsibilities this Rotation■ Analyzed

– Flow Accelerated Corrosion at Anclote 1 and 2

– Loading on Hanger Support System at Crystal River 4

– Inspection history to predict equipment lifespans

■ Attended– Inspection Services All Regions Staff Meeting

– Hines Mechanical Equipment Reliability Meeting (MERM)

– Asset Configuration Tracker Level II Training

■ Designed– Inspection drawings and submitted piping isometrics through ACT

■ Researched– Structural Integrity HEP Webinar Series

Page 6: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Inspection Drawings Project - Intro

Page 7: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Inspection Drawings Project - Benefits

■ Improving skill set– Applied previous drafting table experience

■ Man hours saved– Help Lead Engineer save time for future

inspections

– Precise drawings will help the drafting team save time during Configuration Changes

■ Dollars saved– Scaffolding and insulation costs are

reduced when you have accurate weld positions

Page 8: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Inspection Drawings Project – Moving Forward

■ Plans to submit these drawings through ACT next fall so they can be uploaded in fusion

Page 9: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Hanger Weight Analysis Project - IntroHanger Calculated Load (lbs) Documented Load (lbs) Type Comparison Pipe Orientation Location4H2-1 12,700 18,214 Constant 70% Horizontal Boiler Out S4H2-2 19,099 23,154 Constant 82% Horizontal4H2-3 19,919 21,785 Constant 91% Horizontal4H2-4 26,448 19,660 Constant 135% Horizontal4H2-5 44,572 56,139 Rigid 79% Vertical4H2-7 30,867 31,391 Constant 98% Horizontal4H2-8 20,180 19,204 Constant 105% Horizontal4H2-9 15,908 21,247 Constant 75% Horizontal

4H2-11 49,392 53,992 Constant Clamp 91% Vertical4H2-12 77,736 64,259 Rigid 121% Vertical4H2-15 18,269 22,244 Constant Trapeze 82% Horizontal4H2-17 21,230 19,168 Constant 111% Horizontal4H2-18 24,328 22,328 Constant Trapeze 109% Horizontal Turbine4H2-35 18,652 18,833 Constant 99% Horizontal Boiler Out N4H2-34 24,801 28,862 Constant 86% Horizontal4H2-33 26,859 22,585 Constant 119% Horizontal4H2-32 48,557 60,368 Rigid 80% Vertical4H2-30 36,586 29,550 Variable Spring 124% Horizontal4H2-29 26,279 22,230 Constant 118% Horizontal4H2-27 30,635 53,992 Constant Clamp 57% Vertical4H2-26 86,333 66,925 Rigid 129% Vertical4H2-23 27,222 23,710 Constant Trapeze 115% Horizontal4H2-21 23,678 25,308 Constant 94% Horizontal4H2-20 16,842 13,752 Constant 122% Horizontal4H2-19 27,079 21,390 Constant Trapeze 127% Horizontal Turbine4H2-16 26,079 34,272 Constant Clamp 76% Vertical Crossover4H2-22 26,252 42,800 Constant Clamp 61% Vertical CrossoverTotal: 861,419 857,362 100%

Page 10: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Hanger Project - Benefits

■ Learned valuable information– Helped build understanding of the

system prior to using modeling programs

■ Training– Shadowed Steve Grace, Hanger SME,

for walk downs at Crystal River, Hines, and Tiger Bay

■ Testing– Verified hangers are operating safely

Page 11: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Hanger Project - Moving Forward■ Next fall I will be modeling piping systems in AutoPIPE to plot

stresses to optimize inspection locations

▲Available from: bentley.com

Page 12: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Tour of Crystal River 3 Nuclear Power Plant

▼Available from: tampabay.com ▲Available from: corporate.vattenfall.com▼Available from: ansnuclearcafe.org

Page 13: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Looking Ahead

■ Returning this Fall to continue working with Chris Barbee and the High Energy Piping & Welding team

Page 14: End of Session 1 Presentation 5-5-16 Corey Harpe EXTERNAL

Questions?

Available from: suncoastnews.com