36
STATE OF MICHIGAN DEPARTMENT OF ATTORNEY GENERAL P.O. BOX 30755 LANSING, MICHIGAN 48909 BILL SCHUETTE ATTORNEY GENERAL July 18, 2018 Ms. Kavita Kale Michigan Public Service Commission 7109 West Saginaw Highway Lansing, MI 48917 Dear Ms. Kale: Re: MPSC Case No. U-18424 Enclosed find the Attorney General's Exceptions to the Proposal for Decision, and related Proof of Service. Sincerely, Joel B. King Assistant Attorney General cc: All Parties

Attorney General's Exceptions to the Proposal for Decision

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

STATE OF MICHIGAN DEPARTMENT OF ATTORNEY GENERAL

P.O. BOX 30755 LANSING, MICHIGAN 48909

BILL SCHUETTE ATTORNEY GENERAL

July 18, 2018

Ms. Kavita Kale Michigan Public Service Commission 7109 West Saginaw Highway Lansing, MI 48917 Dear Ms. Kale: Re: MPSC Case No. U-18424

Enclosed find the Attorney General's Exceptions to the Proposal for Decision, and related Proof of Service.

Sincerely, Joel B. King Assistant Attorney General

cc: All Parties

1

STATE OF MICHIGAN

BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION ___________________________

In the matter of the Application of Consumers Energy Company for Authority to Increase its Rates for the Distribution of Natural Gas and for other relief. __________________________________________/

MPSC Case No. U-18424

Attorney General's Exceptions to the Proposal for Decision

Bill Schuette Attorney General Joel B. King (P81270) Assistant Attorney General Michigan Department of Attorney General Special Litigation Division Sixth Floor Williams Bldg. 525 W. Ottawa Street P. O. Box 30755 Lansing, MI 48909 (517) 373-1123 [email protected]

July 18, 2018

2

Introduction

On July 2, 2018, Administrative Law Judge (ALJ) Suzanne Sonneborn issued

her proposal for decision (PFD) in this case. In the PFD, Judge Sonneborn provided

that exceptions to the PFD must be filed on or before July 18, 2018. Accordingly,

the Attorney General, by and through, Assistant Attorney General Joel B. King,

files the instant exceptions.

On October 31, 2017, Consumers Energy Company (“Consumers Energy,”

“Consumers,” “CECo,” or “the Company”) filed its application seeking $178.194

million in rate relief for the 12-month period ending June 30, 2019 (“projected test

year” or “test year”). The Company also sought incremental rate relief of $39.161

million associated with $301.987 million of capital expenditures included in an

expanded Investment Recovery Mechanism (IRM). As part of its case, Consumers

originally requested a return on equity (ROE) of 10.50% and an overall rate of

return of 6.11% on its total rate base. In its initial brief, the Company revised its

requested revenue increase downward to $82.775 million while increasing its

requested ROE to 10.75%. It also adjusted its IRM request.

The Attorney General would like to note up front, as he did in his initial

brief, that Consumers made these requests and asserted that almost $200 million of

rate relief is necessary a mere three months after the Company was granted a rate

increase of approximately $29 million in its last gas rate case, U-18124.

Additionally, the Company’s request came 18 months after the Company was

granted a rate increase of approximately $40 million in its second-to-last gas rate

3

case, U-17882, and 33 months after the Company was granted a rate increase of

approximately $45 million in its third-to-last gas rate case, U-17643.

ALJ Sonneborn recommended in her PFD that the Commission adopt her

findings, conclusions, and recommendations on rate base, capital structure, cost of

capital, and operating revenue and expenses which would lead to an estimated

revenue deficiency of approximately $10.6 million, an authorized ROE of 10.0%, and

an overall cost of capital of 5.86%. She also recommended approval of an expanded

IRM.1 The Attorney General files these exceptions to respond to certain of ALJ

Sonneborn’s findings, conclusions and recommendations as described below.

Standard of Review

Recently, the Michigan Public Service Commission (“MPSC” or

“Commission”) summarized the standard of review of an ALJ decision as follows:

[I]n issuing a ruling, an ALJ does not create findings of fact or conclusions of law that bind the Commission. The ALJ’s decision is a recommendation, and the Commission is not subject to the constraints imposed by a legal standard of appellate review in deciding whether to accept, reject, or modify the ALJ’s assessment of the evidence or legal analysis. See MCL 24.281(3); MSA 3.560(181)(3) (“On appeal from or review of a proposal of decision the agency, except as it may limit the issue upon notice or by rule, shall have all the powers which it would have if it had presided at the hearing.”) In the matter of the complaint of AT&T Communications of Michigan, Inc., MPSC Case No. U-12321 (August 31, 2000), p 13. In fact, the Commission has held that “it will reverse an administrative law

judge’s ruling if the Commission finds that a different result is more appropriate.”

1 PFD page 267.

4

In the matter of the application of the Midland Cogeneration Venture Limited

Partnership for approval of capacity charges contained in a power purchase

agreement with Consumers Power Company, MPSC Case No. U-8871 (June 28,

1988), p 2.

Arguments

While examining the Attorney General’s substantive arguments and

objections, the Commission should consider that Consumers Energy bears the

burden of proof to demonstrate that its proposals are just and reasonable. The

obligation of proving any fact lies upon the party who substantially asserts the

affirmative of the issue.2 A plaintiff always has the burden of proving its cause of

action.3 As applied to administrative cases, a party seeking relief must prove his,

her, or its claim by a preponderance of evidence.4 Likewise, in cases before the

Commission, the utility bears the burden of proof by a preponderance of evidence.5

Given the nature of the burden of proof, the Commission may reject even

uncontradicted evidence.6 When the burden of proving a fact falls on one party,

2 White v Campbell, 25 Mich 463, 475 (1872). 3 Caruso v Weber, 257 Mich 333; 241 NW2d 198 (1931). 4 Dillon v Lapeer State Home & Training School, 364 Mich 1, 8; 110 NW2d 588 (1961); BCBSM v Governor, 422 Mich 1, 88-89; 367 NW2d 1 (1985). 5 In re Michigan Gas Utilities Co, MPSC Case No. U-7484, Opinion & Order dated August 30, 1983; In re Detroit Edison Co, MPSC Case No. U-8030-R, Opinion & Order dated July 9, 1987, pp 16-17. 6 Woodin v Durfee, 46 Mich 424, 427; 9 NW 457 (1881); Accord, Yonkus v McKay, 186 Mich 203, 211; 152 NW 1031 (1915); Cuttle v Concordia Mut Fire Ins Co, 295 Mich 514, 519; 295 NW 246 (1940).

5

then the other party does not have the burden of proving the opposite fact.7

Therefore, Consumers Energy bears the burden of proof to demonstrate that its rate

increase and other requests in its application are just and reasonable.

Here, the Attorney General would like to present a general critique that he

has of the ALJ’s approach to the PFD. Throughout the PFD, the ALJ appeared to

hold a loose, at times incorrect, idea of which party has the burden of proof.

Numerous times throughout the PFD she said something to the effect of, ‘since no

party has objected to the Company’s position, the ALJ recommends that it be

approved.’8 This is an inappropriate approach to ratemaking, and fails to hold the

Company to the standard of prudent and reasonable requests, proven by a

preponderance of the evidence. It is a troubling shift of the burden away from the

Company and onto Staff and Intervenors. The Attorney General requests that the

Commission take note of this inappropriate application of the burden of proof

throughout the PFD and adjust the order accordingly, where the Company has

failed to meet its burden.

Rate Base

The Attorney General recommended and supported a total adjustment in rate

base of $231 million based on reductions to capital expenditures of $335.2 million

and working capital of $8.9 million in his initial brief which if adopted, would

7 S.C. Gary, Inc v Ford Motor Co, 92 Mich App 789, 803-804; 286 NW2d 34 (1979). 8 See e.g. PFD p 119, under “Business Services Capital Expenditures.”

6

decrease the Company’s projected test year revenue deficiency by $21.1 million.9

ALJ Sonneborn recommended reducing rate base by $301,409,000.10 In the process

she rejected several of the Attorney General’s recommended reductions to capital

expenditures and working capital.

Capital expenditures, which mainly drive the growth in Consumers Energy’s

rate base, more than doubled in the five-year time frame from 2010 to 2014 and will

likely triple in the next five years.11 It is clear that the Company is continuing a

major ramp-up of capital expenditures in a variety of areas despite its existing rate

base of over $4.4 billion.

In his initial brief and reply brief, the Attorney General, through his expert

Sebastian Coppola, analyzed the Company’s forecasted capital expenditures by

major department or area and identified more reasonable expenditure levels that he

recommends the Commission adopt. As noticed and mentioned by the Commission

in its January 20, 2017 Order in case U-18124, Consumers has a track record and

tendency of overstating the rate relief that the Company believes it requires.12

Accordingly, throughout this case the Attorney General has attempted to provide

more reasonable projections and levels of the Company’s revenue requirement. The

9 Attorney General’s (Confidential) Initial Brief, dated March 22, 2017 (pp 58-59). All page references will be to this version of the Attorney General’s Initial Brief. 10 PFD page 163. 11 U-18124 (7 TR 1289). 12 Order page 8.

7

Attorney General’s exceptions will address several of his proposed reductions in

capital expenditures that were rejected by the ALJ.

RATE BASE

While not an exception from the ALJ’s PFD, the Attorney General would first like to note that he is particularly troubled and concerned with Staff’s and the ALJ’s findings with regard to Consumers’ practices surrounding its Pipeline Integrity Program

While the AG agrees with the ALJ’s findings in her PFD with regard to

Consumers’ Pipeline Integrity Program, he would like to emphasize to the

Commission that he is particularly troubled with the findings and the conclusions

drawn by Staff and the ALJ surrounding this program. Specifically, Staff found

that

Consumers is unnecessarily repairing pipe defects that can be as small as one-inch with pipe segments in excess of 50 feet. It is Staff’s belief that this practice is conducted to allow the Company to capitalize these remediation digs.13

The Company attempted to deflect attention and criticism from its pipe replacement

practices through discussion of public safety and the technical aspects of pipeline

repair and replacement.14 While the ALJ recognized the continued importance of

the program and pipeline safety, she stated that

this PFD nonetheless finds troubling the results of Staff’s investigation into the Company’s pipeline remediation dig practices based on data provided by the Company and the unflattering portrait that Staff’s investigation has painted regarding the internal inconsistencies between the Company’s capitalization practices and subsequent justifications for them under the guise of public safety.

13 Staff’s Initial Brief pp 71-93; see also Confidential 6 TR 1658-1688. 14 See Consumers Energy’s Initial Brief; 5 TR 1392-1399.

8

Significantly, the Company has not substantively challenged the … six conclusions reached by Staff as a result of this investigation, as outlined at length in Mr. Miller’s testimony and supported by his Exhibits S-12.0 through S-12.56.15 [citations omitted]

The PFD went on to say that

Consumers Energy’s ability to capitalize on its pipeline remediation program by unnecessarily remediating minor pipe anomalies with pipe segment replacement lengths in excess of 50 feet, which expenditures in turn result in a rate relief request that, if approved, increases customers’ rates, amounts to a practice that ultimately exceeds the fair value or benefit to ratepayers. Doing so is neither prudent nor reasonable.16

Saying that such a practice by the Company is “neither prudent nor reasonable” is

an understatement at best.

It seems apparent to the Attorney General that Consumers used this

situation to take advantage of its position as a large public utility with many

moving parts and attempted to pad its bottom line at the expense of Michigan

ratepayers. These actions contributed directly to unnecessary escalated costs for

ratepayers, which includes low-income households and Michigan’s most vulnerable

citizens. The Attorney General requests that the Commission take special note of

this circumstance and Staff’s and the ALJ’s findings and respond accordingly,

especially in light of the fact that this proceeding was commenced by Consumers to

ask for additional revenue, stating that it has a revenue deficiency.

The ALJ erred in recommending that the Commission decline to accept the Attorney General’s proposed

15 PFD at pp 84-85. 16 PFD at p 87.

9

disallowance of Consumers Energy’s projected expenditures for the South Oakland Macomb Network.

The Attorney General recommended that the Commission exclude all of the

Company’s projected capital expenditures for the South Oakland Macomb Network,

which includes $15,400,000 for 2018 and $45,300,000 for the six months ending

June 30, 2019.17 The AG’s argument for exclusion of those costs is that the South

Oakland Macomb Network program has not yet been approved by the Company’s

Board of Directors and no work plans for the project or timeline have been

developed by the Company or provided to other parties for a review.18 The

Company disagreed with the ALJ’s position and relied on Ms. Palkovich’s testimony

that the Company does not require approval by its Board for the entire program,

and that the Company has developed a high-level scope for the program.19

The ALJ agreed with the Company, finding that Ms. Palkovich’s testimony

“provided a reasonable explanation for both the project’s procession without specific

approval from the Board of Directors as well as the development of the scope of

work involved and the Attorney General has neither discussed nor challenged her

testimony.”20 The ALJ erred in her findings and conclusion on this matter. The

ALJ’s contention that the AG neither discussed nor challenged Ms. Palkovich’s

testimony is incorrect, as the portions of the AG’s brief on this matter are a direct

17 Exhibit A-59. 18 Attorney General’s Initial Brief, p 71; 7 TR 2387-2388. 19 TR 1525-26. 20 PFD p 103-04.

10

challenge to Ms. Palkovich’s testimony.21 However, even if that were not the case,

the burden remains on the Company to prove that these expenditures are

reasonable and prudent. The AG/other parties need not oppose every request

Consumers makes in order for it to be deemed unreasonable or imprudent.22 Thus,

the ALJ’s comment that the Attorney General failed to challenge Ms. Palkovich’s

testimony in this area is irrelevant.

While the AG continues to maintain his position that the lack of approval for

this project from the Company’s Board of Directors is reason to deny recovery of

these costs, the larger issue is the lack of any concrete work plans or timeline that

would help Staff and Intervenors analyze the necessity, reasonableness, and

prudency of this project.23 The PFD erred in finding persuasive Ms. Palkovich’s

vague testimony about the Company’s development of a high-level scope, beginnings

of designs and engineering, and other preliminary activities. Ms. Palkovich’s

testimony fails to show a concrete commitment by the Company that it is going to

pursue and complete this project. Without more detailed plans or a more thorough

explanation of what stage the project is at, and without approval form the Board of

Directors to proceed with the entire project, the Company has failed to meet its

burden to support these projected expenditures and the ALJ erred in finding that

21 See Attorney General’s Initial Brief, pp 71-72. 22 Woodin v Durfee, 46 Mich 424, 427; 9 NW 457 (1881); Accord, Yonkus v McKay, 186 Mich 203, 211; 152 NW 1031 (1915); Cuttle v Concordia Mut Fire Ins Co, 295 Mich 514, 519; 295 NW 246 (1940). 23 Attorney General’s Initial Brief, pp 74-75.

11

the Company did. Accordingly, the AG requests that the Commission accept the

Attorney General’s proposed disallowance of Consumers Energy’s projected

expenditures for the South Oakland Macomb Network.

The ALJ erred in recommending that the Commission decline to accept the Attorney General’s proposed disallowance of Consumers Energy’s projected expenditures for the Regulator Stations – Distribution Program in 2018.

In his brief, the Attorney General recommends that the Commission reduce

the Company’s proposed capital expenditures for the regulator stations –

distribution program for 2018 by at least $3 million, because the Company failed to

support the amount requested with adequate work plans or details.24 The ALJ

rejected the proposed disallowance, alleging that the Company has sufficiently

demonstrated in its explanation and testimony that the proposed expenditures are

reasonable and that the Attorney General’s rationale for the disallowance “is

premised on a generalization regarding the nature of the Company’s cost

estimates.”25 Here again the ALJ appears to misconstrue the burden and shift it

from the Company to the Attorney General, without analyzing the Company’s

testimony and finding it adequate. Nothing in either the Company’s testimony or

the PFD provides any concrete details or evidence for this large increase in costs

from one year to the next or how that amount was arrived at.

24 Attorney General’s Initial Brief, pp 70-71. 25 PFD p 111.

12

The Company’s explanation for the increase in costs, that the increase is

based on in-house engineering expertise and subject matter expert input, and that

the Company recognizes that the facilities have a limited lifespan and that past

funding has been insufficient, is very high-level and provides nothing more than

cursory statements about how the Company looked into the program and deemed

funding insufficient. 5 TR 1407-08. The ALJ, however, performed no additional

analysis of the record and found the Company’s vague overview to be sufficient.26

In doing so, the PFD errs by not requiring the Company to meet its burden of proof

to prove that these projected costs are reasonable. Accordingly, the Commission

should accept the Attorney General’s proposed disallowance of Consumers Energy’s

projected expenditures for the Regulator Stations – Distribution Program because

they are unsupported.

The ALJ erred in recommending that the Commission decline to accept the Attorney General’s proposed disallowance of Consumers Energy’s projected expenditures for the disaster recovery project.

The ALJ erred when she found that the Company adequately refuted the

Attorney General’s concerns regarding the Company’s proposed “disaster recovery

project.”27 Instead of finding that the Company adequately justified the projected

expenditures for the project, the ALJ erroneously focused on whether the Company

26 See PFD pp 111-12. 27 PFD p 139.

13

adequately refuted the Attorney General’s concerns.28 In the Attorney General’s

Initial Brief, he detailed the immense future costs of this proposed project, as well

as the attempts by the Attorney General to get additional information from the

Company on why alternatives to building an entirely new site are not feasible.29 In

responses to discovery requests, the Company stated that it did not run cost-benefit

analyses of alternatives to its preferred plan of building an entirely new center, nor

did it consider what other utilities in the region do with regard to backup

facilities.30

It is clear from Consumers’ discovery responses and testimony that the

Company has proposed to include capital expenditures in rate base in this case for a

costly project that has not been adequately vetted, and where practical alternatives

were not adequately considered. Additional research of other alternatives and

opportunities to reduce capital costs needs to occur before the proposed

expenditures can be deemed to be prudent and reasonable. The ALJ erred in

recommending that the Commission decline to accept the Attorney General’s

proposed disallowance of the Company’s projected expenditures for the disaster

recovery project, and accordingly the Attorney General asks that the Commission

disallow these costs.

The ALJ erred in recommending that the Commission decline to accept the Attorney General’s proposed reduction

28 PFD p 139. 29 Attorney General’s Initial Brief at p 82. 30 Attorney General’s Initial Brief at pp 81-85; see also Ex AG-37.

14

to Consumers Energy’s forecasted cash balance in the Company’s working capital projection.

In this case, Consumers proposed a cash balance level in working capital of

$22.9 million. In the Attorney General’s initial brief, he explained why such a large

cash balance is unnecessary and why it is more expensive for customers to carry

that balance.31 For Consumers to earn a return at the overall cost of capital on such

a large cash balance is costly for customers. Consumers’ arguments for why the

Company needs to carry such a large balance are not supportable when DTE, a

Michigan utility of comparable size, carries a cash balance of around $1 million.32

The ALJ’s PFD again inappropriately shifts the burden off of the Company

and onto an intervenor, without finding that the Company’s level of cash balance is

reasonable and prudent. The ALJ uses a citation from the Company for the

proposition that, “issues insufficiently briefed are deemed abandoned.”33 The

Attorney General’s position on this in his initial brief, which included analysis and

discussion of why an elevated level of cash for working capital is inappropriate, can

hardly be considered “insufficiently briefed.”34 However, even if it the brief did not

include any discussion of the cash balance, or even if the Attorney General explicitly

31 Direct testimony of Attorney General’s expert Sebastian Coppola at pp 88-90. 32 Id. pp 89-90. 33 PFD p 158. 34 See Attorney General’s Initial Brief at pp 91-93.

15

stated that he “abandoned” the issue, that does not excuse the Company’s burden to

show that its projected costs are reasonable and prudent.35

The Attorney General maintains that a cash level of $22.9 million in working

capital is inappropriately high and unnecessarily costly to customers, and

accordingly asks the Commission to disallow the Company from including that level

of a cash balance in this case.

Capital Structure, Cost of Capital, and Rate of Return

The ALJ erred in rejecting the Attorney General’s proposed equity balance ratio.

The Company continues to maintain a capital structure that is unbalanced,

disadvantageous to its customers, and out of line with other similarly situated

utilities. Consumers’ proposed capital structure for the test year only perpetuates

the inequities. Recently, the Commission has been explicit with how it expects the

Company to organize its capital structure, but the Company has been unwilling to

cooperate and continues to come up with excuses for why it should not move to a

balanced capital structure. In its application, Consumers proposed a permanent

capital structure with a common equity component of 52.49%.36 The Attorney

General’s initial brief recommended a capital structure with a 50% equity balance,

which as the ALJ noted was accomplished by increasing the company’s long-term

35 In re Michigan Gas Utilities Co, MPSC Case No. U-7484, Opinion & Order dated August 30, 1983; In re Detroit Edison Co, MPSC Case No. U-8030-R, Opinion & Order dated July 9, 1987, pp 16-17. 36 Exhibit A-14, Schedule D-1a.

16

debt ratio by $322 million and reducing its common equity component by the same

amount.37 The result is a capital structure with 50% of common equity and 50% of

debt and preferred stock.

The Attorney General, as he has in numerous other cases, presents several

cogent reasons for proposing a rebalancing of the Company’s capital structure: (1)

the Commission’s directive in the Company’s most recent rate cases; (2) consistency

with Consumers Energy’s stated goal to maintain a capital structure with a

common equity ratio of approximately 50%; (3) the Company’s capital structure

primarily supports the electric business; (4) the Company’s proposed common equity

ratio is excessive in comparison to most other gas utilities; (5) this higher level of

common equity capital unnecessarily increases costs to customers because common

equity is a much higher cost source of capital than debt; and (6) the Company and

CMS Energy can make the level of common equity in Consumers Energy whatever

they want it to be.38 The ALJ’s assertion that the debt-equity ratio imbalance is

justified because of proposed capital investment reflects a narrow view of capital

funding. Debt is also a form of capital. While debt can be riskier, there are also

costs and risks from too much equity capital that must be considered in determining

the proper debt-equity ratios. The ALJ’s implication that the Company’s credit

rating may suffer if the capital structure is realigned, and that the Company’s

37 Exhibit AG-42. 38 Attorney General’s Initial Brief, pp 93-105.

17

planned investments would thereby be harmed, is similarly flawed.39 As pointed

out by the Attorney General, the common equity ratio of the peer group is just over

50%, as compared to the Company’s proposal of 52.5%.40 Despite a ratio that is

much closer to 50-50 as proposed by the Attorney General, those companies in the

peer group continue to function and do not appear to have difficulty raising capital

due to falling credit ratings, as implied by the ALJ.

The PFD also erred in determining that the Attorney General failed to

provide adequate support for his positions on this matter. The Attorney General’s

positions and arguments are well-established in the record, and the Company does

not dispute that moving to a more balanced capital structure would lower costs for

customers.41

In its February 28, 2017 order in Case No. U-17990, Consumers Energy’s

second to last electric rate case, the Commission addressed Consumers Energy’s

capital structure and its seeming inability to reach a 50/50 balance:

The appropriate capital structure of a utility is based on considerations of cost and risk, and in accordance with these considerations, the Commission from time to time adjusted a company’s capital structure to one that was more reasonable. While a company with more debt is a financially riskier enterprise, a company with more equity has a greater amount of capital invested in the most expensive type of capital. Not only is equity capital more expensive than debt capital, but the return on equity adds a tax burden to total revenue requirements, whereas debt does not. Thus, the

39 PFD p 173. 40 Attorney General’s Initial Brief, p 103. 41 See 7 TR 2419-20, lines 12-8.

18

Commission seeks an appropriate balance between the risks and costs of investor debt funding.

Beginning in the 1980s, Consumers adopted a holding company structure and the Commission treated Consumers as a stand-alone company for ratemaking purposes. However, treating Consumers as a stand-alone company has been predicated on the company maintaining “a capital structure roughly balanced between debt and equity.” June 7, 2012 order in Case No. U-16794. In the instant case Consumers states that a balanced capital structure continues to be its goal.

The Commission understands that fluctuations will occur, however it notes that since Case No. U-16191, the amount of equity, on a relative basis, has been consistently increasing. During this period of time, interest rates on long-term debt have been historically low. Accordingly, the Commission agrees with the Attorney General that an imbalance is amplified when considering its impact on the overall rate of return in the current market.” p.63. (emphasis added.)

While the Commission did not perform a rebalancing of Consumers capital

structure in Case No. U-17990, it voiced its expectation that the Company “will

have arrived at or will present a strategy to return to a balanced structure within

the five-year infrastructure plan time period.”42

In its July 31, 2017 Order in case No. U-18124, Consumers Energy’s most

recent gas rate case, the Commission again addressed Consumers Energy’s capital

structure and its continued inability to reach a 50/50 balance.43 In her PFD in this

case, the ALJ noted that in U-18124, the Commission stated that the Company’s

proposed capital structure in U-18124 “represents a departure from its stated

objective of a roughly balanced capital structure” and accordingly directed

42 Commission Order in U-17990, p 64. 43 Commission Order in U-18124, pp 45-46.

19

Consumers to “return to a balanced capital structure.”44 In the PPD, the ALJ

included the pertinent block quotation in a footnote:

The Commission cannot overemphasize the company’s responsibility to rebalance its equity and debt capital. . . Consumers shall, in its next rate case, articulate its strategy to return to a balanced capital structure and the steps it intends to take to reach its stated goal, or the Commission will have to consider using its regulatory authority to rebalance Consumers’ capital structure.45 The same concerns expressed by the Commission in Case No. U-17990 and U-

18124 apply in this case. The Company continues to increase the imbalance

between its debt and equity ratios. Given the Company’s lack of will power to

address this issue head on, despite clear direction from the Commission, the

Attorney General recommends that the Commission act now and approve a capital

structure of 50% common equity and 50% preferred stock and debt, which is

consistent with the Company’s stated goal of 50% common equity and 50% debt and

the Commission’s directive in cases U-17990 and U-18124. It is a more reasonable

capital structure and better balances the Company’s risk versus the cost of capital

to be borne by ratepayers. The ALJ erred in recommending otherwise.

The Commission should approve a return on equity of no more than 9.50%.

The Company requested a 10.50% return on equity (ROE) in its application,

and then increased that request to a 10.75% ROE in its initial brief.46 The ALJ

44 PFD p 172. 45 PFD p 172, citing to Commission’s Order in U-18124, pp 45-46. 46 PFD p 178.

20

correctly dismissed an ROE at either level as excessive.47 In doing so, she pointed

out the flaws and weaknesses in the Company’s analysis.48 Instead, the ALJ

recommends that the Commission approve a 10.0% ROE, which she asserts is

“based upon an objectively reasonable analysis which is consistent with past

Commission decisions and the requirements of Bluefield and Hope, and

acknowledges both the volatility in United States and global markets and the

likelihood of rising interest rates.”49 She also asserts that the ROE recommended

by Staff, as well as the ROEs recommended by ABATE and the Attorney General

(ranging from 9.50% to 9.72%) send the wrong message to investors.50 Her analysis

appears to be based on the voluminous, yet vague and unsubstantiated testimony of

the Company’s witness, Srikanth Maddipati, which references legislative and

judicial underpinnings, consistency and predictability, sufficiency of rates, and

returns and non-constructive outcomes.51 Such vague assertions should not form

the basis for the Commission’s decision, which must balance competing factors.

The ALJ also makes numerous references to the Commission’s recent

statement that parties should consider the degree of financial adjustment that they

ask the Commission to make, “because it is not realistic to make a significant

47 PFD p 207. 48 PFD pp 178-207. 49 PFD pp 207-08. 50 PFD p 206. 51 PFD p 179-81.

21

change in ROE absent a radical change in underlying economic conditions.”52 The

PFD appears to put a significant emphasis on that statement, and uses it as part of

the justification for refusing to deviate too far in either direction from the ROE

established in Consumers’ last rate case.

The Attorney General’s recommended ROE range is based on objectively

reasonable analysis, the correct application of generally accepted models, and is

well documented.53 It should also be pointed out that both Staff’s witness and

ABATE’s witness calculated very similar ROEs.54 While the Commission has stated

that the determination of the ROE is not based merely on mathematical

calculations, the Attorney General provided support beyond mere calculations in his

witness’s testimony, and his Initial and Reply Briefs, to support an ROE below 10%.

Mr. Coppola’s testimony, including Exhibit AG-49, provides evidence of gas utilities

with authorized ROEs of less than 10% that continue to have access to capital

markets and continue to raise debt capital at competitive rates. ROEs below 10%

have not affected these utilities’ credit ratings or financial soundness and likewise

will not negatively impact Consumers’ credit rating or financial soundness.55 The

Company has not effectively rebutted this evidence or similar evidence put forth by

other parties in the case. Nor has the Company provided any evidence that those

52 PFD p 206, 207. 53 Attorney General’s Initial Brief at pp 105-32. 54 PFD p 178. 55 Attorney General’s Initial Brief, p 125.

22

utilities with ROEs below 10% are operating in unconstructive regulatory

environments.

Michigan’s regulatory environment has long been recognized as constructive

to utilities, and as stated by Mr. Maddipati, continues to be recognized as such.56

Part of that is that Michigan has, for a long time, had ROEs higher than, and out of

line with, the national average. While ROEs in the state have been trending down,

as pointed out by the ALJ, they have been doing so slowly, and all the while

customers have been paying inflated rates. Moving to an ROE of 9.50% would bring

Consumers more in line with similarly situated utilities nation-wide and recognize

Michigan’s steadily improving economy.

For the reasons provided above and in his Initial and Reply Brief and witness

testimony and exhibits, the Attorney General recommends that the Commission

authorize an ROE of no more than 9.50%. This ROE is more representative of a fair

return that balances the Company’s true cost of capital and need to attract capital

while minimizing negative rate impacts on customers.

Overall Return on Capital

The Attorney General continues to recommend an overall return on capital of

5.58% which includes a return on common equity of 9.50%, as shown in Exhibit AG-

42, page 1.

Throughput.

56 4 Tr 810-811, 829.

23

A. The ALJ erred in rejecting the Attorney General’s adjustment to forecasted sales. Consumers Energy uses various regression analysis models and a weather

normalization process to forecast gas sales and transportation deliveries for the test

year.57 Consumers Energy’s continued reliance on assumed energy efficiency

savings does not provide a reasonable basis for asserting a decline in sales for which

additional revenue is required.58 As noted by Mr. Coppola, if the Company’s

assumed energy efficiency was correct, we would expect to see cumulative savings of

3.75% over the five year period, however that is not the case.59

The ALJ based her recommendation in the PFD on the Company’s argument

that to exclude the energy efficiency savings adjustment from the forecasted gas

deliveries ignores economic conditions, the fact that the regression models have

been accepted and approved in prior rate cases, and that the Attorney General’s

analysis overlooks the Company’s unchallenged expectation that the weather

adjusted actuals will be within 0.3% and 1.3% of the originally forecasted deliveries

for 2016 and 2017, respectively.60 This is essentially the same reasoning that the

ALJ applied in Consumers’ last gas rate case, U-18124.61

57 2 TR 320. 58 See Attorney General’s Initial Brief, pp 13-15. 59 Attorney General’s Initial Brief, p 12. 60 PFD p 214. 61 See U-18124 PFD p 112.

24

The reasons given for not accepting the Attorney General’s proposed

adjustments are baseless and should not be given any weight. First, each case is

judged on its own merits, and the merits of this case indicate that using regression

analysis leads to unreasonable assumptions regarding the value of energy efficiency

in the sales numbers. It would be absurd to rely on the Company’s faulty regression

analysis in this case, just because the Commission approved similar methodology in

prior cases. Second, actual sales for the past 5-6 years have stayed static, with a

slight increase in the most recent 5 year period.62 Third, Mr. Coppola took into

consideration all of the relevant factors. Because the Company relied on an

assumed rate for energy efficiency in its analysis, the Attorney General conducted

discovery and further analysis to determine the reasonableness of those

assumptions. That discovery included the Company’s historical weather normalized

sales and transportation volumes for 2011-2016 and the twelve months ended

October 2017, and the number of customers the Company had during those time

periods. Mr. Coppola provides additional analysis in his testimony.63

It is apparent that Consumers Energy’s reliance on the assumed energy

efficiency savings does not provide a reasonable basis for asserting a decline in sales

for which additional revenue is required. This was true in U-18124 and remains

true in this case. The Attorney General’s proposed adjustments results in an

62 Attorney General’s Initial Brief, p 11. 63 See, Attorney General’s Initial Brief, pp 10-19.

25

increase of approximately $14.3 million in revenue for the test year over the

amounts proposed by the Company.64

The PFD made no mention of many of the Attorney General’s arguments

included in his initial brief. Specifically, the Attorney General included detailed

arguments that the Company continues to present its data in misleading fashion

and that the Company traditionally forecasts gas deliveries below actual

deliveries.65 These are trends that can be seen from rate case to rate case, and the

Commission should not allow Consumers to perpetuate these habits by approving

the Company’s gas deliveries forecast. The Attorney General’s calculation and

analysis are reasonable and he recommends that the Commission adopt his

proposed reductions.

ADJUSTED NET OPERATING INCOME

The ALJ erred in not accepting the Attorney General’s proposed rate of return on plan assets in the Company’s pension and benefits expense.

The ALJ erred in not accepting the Attorney General’s arguments regarding

the Company’s projected rate of return on plan assets. The Company’s decision to

reduce the expected return rate from 7.25% in 2017, to 7.0% in 2018, is unsupported

by the Company in the record and is neither prudent nor reasonable. As pointed

out in the Attorney General’s initial brief, the Company proffered an explanation

64 See, Attorney General’s Initial Brief, p 24. 65 Attorney General’s Initial Brief p 19.

26

during discovery for this reduction, which was thoroughly refuted by the Attorney

General’s witness in his testimony.66

In her PFD, the ALJ disregards the Attorney General’s argument and

discussion that the Company simply picked the return rate of 7.0% before the rate

case was filed, filed it as a part of the rate case, and then attempted to support it

after the fact.67 The fact that Consumers followed this pattern is clear from the

Company’s originally filed testimony and its testimony on cross examination. The

ALJ attempts to spin this as a mischaracterization of Mr. Kops’ testimony, but his

answers on cross examination, as laid out in the Attorney General’s initial brief, are

clear. Therefore, the Attorney General recommends that the Commission accept the

Attorney General’s proposed rate of return on plan assets in the Company’s pension

and benefits expense and set it at 7.25%.

OTHER REVENUE RELATED ISSUES

The ALJ erred in not accepting the Attorney General’s recommendations related to the Company’s proposed expansion of its IRM.

66 Attorney General’s Initial Brief, pp 45-46. 67 See Attorney General’s Initial Brief, pp 48-50.

27

The ALJ erred in recommending a modified and expanded Infrastructure Recovery Mechanism because it is unreasonable, and imprudent.

Consumers Energy has once again proposed An investment recovery

mechanism (IRM) to recover costs for capital expenditures to be made from 2019

until rates are reset in a subsequent general rate case. The Company identified

eight programs that it proposed to include in its expanded IRM: TED-I Distribution;

TED-I Transmission; EIRP-Distribution; EIRP-Transmission; VSR; Asset

Relocation – Decision Analysis Mains and Services; Pipeline Integrity-

Transmission; Pipeline Integrity-Transmission Operated by Distribution.68

Recovery for the investments would be through a surcharge effective from January

1, 2019 until rates are reset in a subsequent general rate case, with a reconciliation

process at the end of June 30, 2020. The amounts to be included in the IRM

continue to reflect a significant amount of capital expenditures for those years and

the ALJ erred by recommending Commission approval of a portion of the Company’s

proposal.

Like the Company’s existing IRM, this IRM would be a surcharge to customer

bills, with any over- or under-recovery adjustments to be recovered in the

subsequent year through a reconciliation process.69 This would be an additional

rate increase to customers on top of what the Commission grants in this case for the

forecasted test year.

68 2 TR 371. 69 Id.

28

The MPSC Staff proposed a revised IRM in this case that would, among other

things, exclude the TED-I Distribution and TED-I Transmission programs.70

Although the PFD notes that Staff continues to support the general concept of the

proposed IRM for high-risk pipelines, the ALJ goes on to note that Staff rejects the

IRM originally proposed by the Company in this case because Staff is starting to see

that the benefits of the IRM that the Company continually espouses, such as less

frequent rate cases and reductions in resources tied to regulatory proceedings, are

not actually being realized.71 This ties into the Attorney General’s continued

contention that an IRM is not an appropriate mechanism to use in this forum and

the only party that benefits from it is the Company.

As the Attorney General and its expert witness, Mr. Coppola, have continually

predicted and warned, if the Commission opened the door for the Company and

approved an IRM of any scope, the Company would soon follow with requests to

expand it further.72 True to the Attorney General’s predictions, three months after

receiving the Order in U-18124, the Company filed this rate case, which included

proposals for including more and larger capital projects in an IRM. If given the

chance, the Company will continue to attempt to blow that door wide open and

include everything it can in an IRM mechanism.

70 6 TR 1896. 71 6 TR 1894. 72 “There is virtually nothing that is appealing about having an IRM for 2018 and 2019 or any future period, as most likely the Company will request it again, if this one is approved.” See U-18124, 7 TR 1355, 8-10.

29

The expansion to the IRM recommended by the ALJ in this case simply

broadens the scope of Consumers’ IRM, and the Company will continue to attempt

to broaden the IRM until the Commission puts a stop to it. The proposed IRM is

another stand alone cost tracking mechanism that would cover a broad range of

capital expenditure programs. It makes for bad regulatory policy and erodes

ratemaking processes that have worked for decades.

In the PFD, the ALJ recommended that a revised IRM, which incorporated the

changes proposed by Staff and agreed to by the Company, should be approved.73

The Attorney General maintains his position that there should be no expansion of

the IRM past what was approved in case U-18124, and argues that the Commission

should re-evaluate the necessity and probity of allowing the Company to employ any

type of IRM. Leaving a re-evaluation of the Company’s IRM to the Commission, the

Attorney General urges in these exceptions that the Commission disregard the

ALJ’s recommendation in the PFD and refuse to expand the Company’s IRM past

what was established in U-18124.

The Attorney General has spent significant time in the past several rate cases

laying out his arguments against an IRM, specifically against approving one in the

context of a rate case, and he will not rehash all of that here.74 However, he would

like to briefly address the ALJ’s main concern with the AG’s position, as noted in

the PFD. The ALJ does not agree with the Attorney General’s characterization of

73 PFD p 267. 74 See e.g. Attorney General’s Initial Brief pp 93-96.

30

the IRM as turning a rate case into an “automatic cost recovery program.”75 While

the statement “automatic cost recovery program,” may slip into hyperbole, the

underlying point remains and the Attorney General wants to make sure that it does

not get lost. The idea of an IRM strays far afield from the structure and purpose of

ratemaking through the general rate case process. As laid out by the Attorney

General in his initial brief:

Rate case review of projected costs offers all parties the opportunity to weigh in on the reasonableness of those projected costs before significant capital expenditures are incurred. This is a tried and true part of rate cases that include projected costs. The IRM defeats that by taking a level of capital expenditures identified in prior years and allowing the Company to recover the associated costs through bill surcharges. This means that there is no specific list of projects or breakdown of components of the program expenditures to challenge upfront. Such challenges can only occur years later, after the summary program amounts have been spent.76

This is the crux of the issue for the Attorney General, and one of the main reasons

that he remains adamant that the IRM should not be utilized or expanded through

a general rate case, either for Consumers or for any utility in Michigan.

Consumers has again failed to make a showing that the IRM is critically

needed or will help customers. The ALJ’s assertion that the record lacks evidence

quantifying risk exposure reductions and increases or evidence regarding reduced

regulatory lag in the recovery of capital costs is inaccurate and nothing more than a

distraction. First, the IRM itself is a risk reducing mechanism. It would continue

to allow the Company to self-implement a surcharge for expenditures that may

75 PFD p 266. 76 Attorney General’s Initial Brief p 94.

31

ultimately not be reasonable or prudent. Second, the point asserted by the Attorney

General is that by reducing regulatory lag in the recovery of capital costs for the

Company, overall earnings volatility is also reduced. This simply reduces the

overall business risk for the Company, and shifts another burden squarely onto

ratepayers.

The Commission should reject the ALJ’s recommendation of any expansion

to the Company’s IRM for the reasons provided above.

The ALJ erred in failing to recommend that the Commission instruct Staff to organize a collaborative to develop a daily balancing program for EUT customers.

In his initial brief, the Attorney General recommended that the Commission

instruct Staff to organize a collaborative effort with all stakeholders for the purpose

of developing a workable daily balancing program for EUT customers of Consumers

Energy.77 In cases U-17900 and U-17334, the Commission ruled that modifications

to the End-User Transportation tariff may be necessary in order to address

inequities to GCR costs, and the Company agreed to present a study of end-user

transportation daily balancing in U-18424.78 Unfortunately, the Company did not

take this requirement seriously and conducted the study in a way that slanted the

daily balancing proposal toward maintaining the status quo.79

77 Attorney General’s Initial Brief p 140. 78 Id. at 140-41. 79 Id. at 140-44.

32

Other gas utilities in Michigan have recognized that problems occur during

cold weather, when gas supplies become scarce and are not fully delivered to the

local utility to match the EUT customers’ demand, or are redirected to higher value

markets by the alternative supplier. SEMCO Gas and Michigan Gas Utilities

Corporation have both moved to EUT daily balancing to prevent the “gaming” of the

system that can occur with monthly balancing.80

The ALJ erred in her conclusions that the Attorney General failed to

demonstrate that the Company’s study was not in good faith and that the Attorney

General failed to establish in the record that a problem exists with monthly

balancing. The PFD provides no analysis of any of the information or analysis

presented in either the Attorney General’s testimony or brief, and appears to simply

side with the Company out of the convenience and safety of retaining the status

quo.81 As numerous parties, including the Commission, have discussed, there is a

problem with monthly balancing that should be addressed by a move to daily

balancing. Accordingly, the Attorney General requests that the Commission

instruct Staff and the Company to convene a collaborative among interested

stakeholders to discuss a move to daily balancing.

80 Id. at 142. 81 See PFD pp 281-82.

33

Relief Requested

The Attorney General respectfully requests that the Commission issue an

order that is consistent with the positions set forth in these Exceptions to the

Proposal for Decision, and the Attorney General’s Initial and Reply Briefs.

Respectfully submitted, Bill Schuette Attorney General Joel B. King Assistant Attorney General Michigan Department of Attorney General Special Litigation Division Sixth Floor, Williams Bldg. 525 W. Ottawa Street P. O. Box 30755 Lansing, MI 48909 (517) 373-1123

July 18, 2018

1

PROOF OF SERVICE - U-18424 The undersigned certifies that a copy of the Attorney General’s Exceptions to the Proposal for Decision, was served upon the parties listed below by e-mailing the same to them at their respective email addresses on the 18th of July, 2018. Amanda Churchill MPSC: Amit Singh Monica Stephens Lori Mayabb Daniel Sonneveldt [email protected] [email protected] [email protected] [email protected] ALJ: Hon. Suzanne Sonneborn [email protected] Attorney General Special Litigation Division: Joel B. King Celeste Gill [email protected] [email protected] [email protected] Seb Coppola [email protected]

Consumers Energy Company: Robert Beach Gary Gensch, Jr. Theresa Staley Bret Totoraitis Anne Uitvlugt Kelly Hall Michael Rampe [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] Midland Cogeneration Venture: Richard Aaron Jason Hanselman Kyle Asher [email protected] [email protected] [email protected] Lansing Board of Water & Light: Richard Aaron Kyle Asher Jason Hanselman [email protected] [email protected] [email protected]

2

RESA: Jennifer Utter Heston [email protected] ABATE: Bryan Brandenburg Michael Pattwell [email protected] [email protected]

Jeffry Pollock Kitty Turner [email protected] [email protected] Residential Customer Group: Brian Coyer Don Keskey [email protected] [email protected]