41
1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance Ltd Green IT Business Transformation Seminar

1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

Embed Size (px)

Citation preview

Page 1: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

1

Planning & Optimising the Green IT Datacentre:

Design, Operation & Management Best Practices, Technologies & Challenges

Pierre Ketteridge, IP Performance Ltd

Green IT Business Transformation Seminar

Page 2: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

2

Yes! Of course…

…but only with careful planning, design and management!

Introduction

Page 3: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

3

• The direct carbon impact (ie Carbon Footprint) of Data Centres on the environment is almost exclusively related to power consumption

• Data Centres do not (when properly designed and managed) vent hot air or polluting gases into the atmosphere – cooling should be a ‘closed system’

• There may be indirect carbon impacts through staffing levels, travel to and from site, operational maintenace and housekeeping

Introduction

Page 4: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

4

PowerDistribution

ITComponents

Cooling 50%

40%

10%…Lighting accounts for 1-3%, dependent on whether LO operation is implemented or not

Introduction

15% of business power consumption is accounted for by Data Centres & ICT…

Page 5: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

5

Cooling falls into two categories:

• Air Cooling

• Liquid (water) Cooling

Cooling

Page 6: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

6

Air Cooling

The traditional way of cooling a Data Centre Computer Room:

• CRAC (Computer Room Air Conditioner)• Water Chiller• Cold Aisle/Hot Aisle Configuration

Cooling> Air Cooling

Page 7: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

7

Inherent limitations of CRAC-based Air Cooling Systems:

• CRAC capacity needs to be 30% greater than the actual demand• Limitations in cooling (5kW – 7kW per rack)• N+1 active equipment resilience/redundancy drives efficiency of cooling system down further

Cooling> Air Cooling

Page 8: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

8

Some Easy-to-Implement Air Cooling Optimisation Suggestions:

• Hot Aisle/Cold Aisle Arrangement• Cold Aisle Containment• Blanking Panels• Raised Floor Brush Strips• Underfloor, Inter- and Intra-rack Cable Management• Free Air Cooling

Cooling> Air Cooling

Page 9: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

9

Cooling> Air Cooling> Hot Aisle/Cold Aisle

• With no hot aisle/cold aisle arrangement, returning heated air mixes with the CRAC-cooled air and cooling to the DC CR equipment is impaired. There is also the issue of bypass cold airflow, which can impact chiller operation.

• With a hot aisle/cold aisle arrangement, chilled air is forced out into the front-of-cabinet facing cold aisles, across the equipment surface, and warm air is channeled out into the rear-of-cabinet facing hot aisle for return to the chiller/CRAC.

Page 10: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

10

Cooling> Air Cooling> Hot Aisle/Cold Aisle

• Ineffective positioning of CRACs impair the airflow around the DC CR.

• CRACs along the side walls are too close to the equipment racks, and will cause the airflow to bypass the floor vents in those cold aisles.

• Place cooling units at the end of the equipment rows, not mid-row.

• CRACs should be aligned with the hot aisles to prevent hot/cold aisle airflow crossover, which apart from increasing the temperature of air supply to the rack fronts but also can trigger the cooling unit to throttle back, reducing cooling overall.• Limit maximum cooling unit throw distance to 50'

Page 11: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

11

Separation of High-density Racks

Cooling> Air Cooling> Hot Aisle/Cold Aisle

• Air cooling systems become ineffective when high-density racks are co-located

• “Borrowing” of adjacent rack cooling capacity is not possible in this configuration

• An alternative (other than self-contained cooling) is to spread out high-density racks to maintain the cooling averages

• Obviously this is not always practical – witness the prevalance of blade server and virtualisation technologies – two to five times the per rack power draw of traditional servers

Page 12: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

12

Cooling> Air Cooling> Cold Aisle Containment

Cold Aisle Containment• Very simple to deploy / Retrofit

• Hot and cold aisles physically separated

• Greater watts per rack approx 10kW

• Over sizing of the CRAC is reduced

• CRAC efficiency is increased due to a higher delta T

• CRAC fan speed can be reduced which provides:

- Reduced running costs - Increased MTBF

Page 13: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

13

Cooling> Air Cooling> Blanking Panels

• Reduction and stabilization of equipment air-intake temperatures• Elimination or reduction of the number and severity of hotspots • Increased availability, performance, and reliability of IT equipment, especially in the top one-third of the equipment cabinet

• Elimination of exhaust air recirculation within the cabinet, optimising cooling and reducing energy consumption and OpEx• Deferral of CapEx (additional cooling capacity)• The potential of greening the data center by reducing its carbon footprint

Page 14: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

14

Raised Floor Brush Grommets

Cooling> Air Cooling> Raised Floor Brush Strips

• Self-sealing and interwoven closure system • Brush grommets can be installed as DC is commissioned, or retro-fitted • No changes to existing wiring configuration • Fits into the raised floor tiles prior to cabinet installation • Simple• Inexpensive

• Cable openings allow approx. 60% of conditioned air to escape • Use brush grommets to seal every cabling entry point • Increases static pressure in the under-floor plenum - ensures that the DC airflow remains at a pressure above atmospheric • Extend reach of Hot Aisle/Cold Aisle system

Page 15: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

15

Cable Management – Intra-rack, Inter-rack and underfloor

• Airflow within racks is also affected by unstructured cabling arrangements

• Deployment of high-density servers creates new problems in cable management

• Cut data cables and power cords to the correct length – use patch panels where appropriate

• Equipment power should be fed from rack-mounted PDUs

• Raised floor/subfloor plenum ducting carries other services apart from airflow:– Data cabling, power cabling, water pipes/fire detection & extinguishing systems

• Remove unnecessary or unused cabling - old cabling is often abandoned beneath the floor – particularly in high churn/turnover Co-Lo facilities

• Spread power cables out on the subfloor - under the cold aisle to minimize airflow restrictions

• Run subfloor data cabling trays at the stringer level in the hot aisle - or at an “upper level” in the cold aisle, to keep the lower space free to act as the cooling plenum

Cooling> Air Cooling> Cable Management

Page 16: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

16

What is Free Cooling?

Cooling> Air Cooling> Free Air Cooling

DC CRAC

Chiller Unit

Roof-Mounted Free Air Cooler

Page 17: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

17

Average UK Temperatures

Cooling> Air Cooling> Free Air Cooling

-5

0

5

10

15

20

25Ja

n

Feb

Mar

Apr

May Ju

n

Jul

Aug

Sep Oct

Nov

Dec

Month

Deg

rees

C

Average Day

Average Night

Page 18: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

18

Budgetary Example – Projected Cost of Running the System for a Year

Not using the Free Cooler• Chiller Capacity 150 kW• Energy needed to run the chiller 62 kW• Numbers of Hours running per year 8784• Cost per kWh £0.0784Total Cost of Running per Year £42,697.00

100% free cooling 70% of the year• Chiller capacity 150 kW• Energy needed to run the chiller 62 kW• Numbers of hours running per year 2580• Cost per kWh £0.0784• Cost of running the chiller £12,540.00• Cost of running Free Cooling (10.4kw) £ 5,058.00Total Cost of Running per Year £17,599.00

200C

150C

200C

200C

Cooling> Air Cooling> Free Air Cooling

Page 19: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

19

• When going above 10kW per rack a new, more targeted/directed cooling method is required

• Most common methods is Water Cooling

Cooling> Liquid Cooling

High Density Data Centres and Liquid Cooling

Page 20: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

20

So What is Liquid – or Water – Cooling? Cooling> Liquid Cooling

• Delivery of chilled water to multiple heat exchange points from a central unit

• The central unit circulates water from the buildings existing chilled water loop

• Heat exchange units in rear doors (one per cabinet, capacity 30kW) or side doors (2 x dual cabinet resilience, 2 x 15kW)

• Heat is carried away in the water - air is ejected back out into the DC at the same temperature it entered the rack - zero thermal footprint

Page 21: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

21

Why Use Water Cooling?

Cooling> Liquid Cooling

• Water 3,500 times more thermally efficient than air

• Air cooling only delivers 5-7kW of cooling per rack (10kW with hot aisle/cold aisle arrangement)

• High Density DCs place increasing power and thermal control demands on the infrastructure

• Blade servers - up to 80 servers in a standard 42u cabinet – and anything from 80 to 800 virtual machines!

• Fully-loaded blade server rack can produce 25Kw of heat

• Water Cooling can deliver 30kW of cooling to a fully-loaded 42u rack

Page 22: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

22

Adding the benefits of Free Cooling, some CapEx/OpEx implications of Water Cooling:

• Water cooling has a slightly higher install cost (more terminations/ pipe work)…but greater kW per sq ft gives us…– 35-45% reduction in required real estate – 15-30% reduction lower in overall construction costs– 10-20% reduction on total annual fan power consumption– 12-14% reduction in power delivered to mechanical chilled

water plant

• For an average efficiency data centre, annual savings of £22,000 and £80,000 for small and large data centres respectively

• Significant when the design life of the data centre is 10 years

• Reduction in energy is a reduction in costs and also a reduction in your carbon footprint

Cooling> Liquid Cooling

Page 23: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

23

Active Equipment (Networking)

• Switches• Routers• Appliances

– Load balancers– Caching/Proxying – Bandwidth Management– Application Acceleration & Optimisation

Network Components

Page 24: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

24

Data Centre Switch Requirements

• Port density• Performance• Functionality• Feature set• Resilience/Redundancy• Security• Price• Power consumption/Heat output

Network Components> Ethernet LAN Switches

Feeds & Speeds

Capabilities

Page 25: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

25

Data Centre Switch Requirements

Network ComponentsNetwork Components> Ethernet LAN Switches

• High port density per chassis• Low power consumption

• Availability

• High performance• Low latency

Optimised for the environment

Optimised for the application

Page 26: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

26

Network ComponentsNetwork Components> Ethernet LAN Switches

Page 27: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

27

Ethernet Switch Power Consumption - A Comparative Example: 15,000 User Network

Network ComponentsNetwork Components> Ethernet LAN Switches

Solution ALU Configuration Cisco Configuration Delta Power Consumption Cisco/A-L

LAN edge 48 ports 216 x OS6850 216 x Catalyst 3750

LAN edge 24 ports 160 x OS6850 160 x Catalyst 3750

LAN aggregation 40 x OS9000 40 x Catalyst 4500 • LAN core 8 x OS9000 Chassis 8 x Catalyst 6500

Total 102 kW/h

54 kW/h

48kW/h

Across an installed network base of 15,000 ports, it was possible to save 102 kW/h, resulting in:

• Lower Power Consumption• Less Cooling Equipment• Smaller Batteries• Smaller Data Centers

Page 28: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

28

Routers

Network Components> WAN Routers

• Look at power consumption figures/thermal output• Deploy shared WAN architecture – MPLS, VPLS, IP VPNs• Investigate leveraging and integrating bandwidth optimisation and application acceleration technologies

Page 29: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

29

LAN/WAN Optimisation Appliances

Network Components> Appliances> Load Balancing

…an area where we can make a difference, in the way in which technologies are deployed to optimise LAN/WAN bandwidth usage and availability of back-end servers.

An excellent example would be application delivery, traffic management and web server load balancers:

• High Performance through acceleration techniques

• High Availability

Page 30: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

30

More LAN/WAN Optimisation Options…

DPI Bandwidth Management solutions:• Inspection, Classification, Policy Enforcement

and Reporting on all traffic:– Identification - application signature, TCP/UDP port,

protocol, source/destination IP addresses, URL– Classification – CoS/ToS (IP Prec/Diffserv

CodePoint/DSCP); user-defined QoS policy– Enforcement based on user-defined policy – Reporting – RT and long-term – extremely valuable

for SLAs/SLGs in DC environments

Network Components> Appliances> DPI Bandwidth Management

Page 31: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

31

LAN/WAN Optimisation Options (cont’d)

WAN optimisation and application acceleration:

• Usually deployed as a reverse proxy device

• Provides some form of bandwidth management

• Protocol optimisation – making LAN protocols more latency-tolerant

– eg. TCP handshake spoofing

• Object caching– Files, videos, web content, locally cached and served

• Byte caching– Repetitive traffic streams, hierarchically indexed and tagged (inline only)

• Compression– (inline only)

• Proxy support for common protocols

– HTTP, CIFS, SSL (HTTPS), FTP, MAPI, P2P, MMS, RTSP, QT, TCP-Tunnel, DNS etc

Network Components> Appliances> WAN Optimisation

Page 32: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

32

LAN/WAN Optimisation Options (cont’d)

WAN optimisation and application acceleration:• Reverse Proxy• Bandwidth Management• Protocol optimisation – for latency-intolerant

LAN protocols– eg. TCP handshake spoofing

• Object caching• Byte caching• Compression (inline only)• Proxy support for all/most common protocols

Network Components> Appliances> WAN Optimisation

Page 33: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

33

Managing the Data Centre Infrastructure

Infrastructure Management

“Lights Out” operation requires…• Little or no human intervention•Exceptions:

• Planned maintenance• Fault rectification/management (emergency maintenance/repair)• Physical installs/removals• Housekeeping (cable management, MAC)• Cleaning

• How are you going to control it? How are you going to manage it?

Page 34: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

34

Remote Control and Management

Infrastructure Management

• RDC, VNC – In Band Management

• Console Servers – Out of Band Management

• KVM switching (local/remote)

• KVM/IP switching & USB2 VM Remote Drive Mapping

• IPMI Service Processor OOB Management

• Intelligent Power Management (iPDUs)

Page 35: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

35

Infrastructure Management

5

Intelligent Power Management

(iPDU)

Console Server Management

(Routers, Switches, Appliances)

VNC/RDC

KVM/KVM-over-IP(Servers, Blade Servers, Management PCs, Appliance Management Devices)

Service Processor Management

(Closed Loop InBand or Out-of-Band) –

IPMI, iLO, DRAC etcSMASH CLP

Page 36: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

36

Summary - Cooling

• Data Centre “Greening” is mainly down to managing power consumption

• Cooling is the biggest consumer of power (50%)• Optimise your air-cooled CRAC system:

– Cold Aisle/Hot Aisle arrangement– Cold Aisle containment– Blanking Panels– Raised floor/underfloor brush strips/grommets– Free air cooling system

Summary

Page 37: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

37

Summary

Summary – Cooling (Cont’d)

• If deploying high-density bladeservers/virtualisation, consider water-cooling (max kW/hr cooling rises from 5-10kW/hr to 30kW/hr)

• Targeted control• Even distribution of cooling• Full (42u) rack utilisation• Zero thermal footprint – design flexibility• Remember free air cooling reduces costs further• Real Estate savings

Page 38: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

38

Summary - Active Equipment (Networking)

Switches:• high port density, low power consumption, PSU disconnect/fanless

operation• Extrapolate power consumption over entire port count

Routers: • Modular architecture, high density, low power consumption• Make full use of available bandwidth

– Shared services: IP VPN, point-to-multipoint or meshed MPLS– Use/honour QoS marking– Deploy Bandwidth optimisation techniques

Summary

Page 39: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

39

Summary - Active Equipment (Networking) – Cont’d

Appliances:

• Load Balancing – Maximise performance, utilisation and availability of server resources

• DPI Bandwidth Management

• WAN Optimisation

Summary

Maximise performance,

utilisation and availability

of WAN resources

Page 40: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

40

Summary

Summary – Infrastructure Management

• Remote Infrastructure Control and Management enables “lights-out” operation

• Remote console management gives CLI access to network infrastructure – routers, switches, firewalls, other network optimisation appliances

• KVM-over-IP allows remote, distributed control of server and workstation systems

• Service Processor Management allows remote control and management of system processor and environmental monitors/controls

• Intelligent Power Management enables remote monitoring, control and management of PDUs, UPS and battery backup resources

Page 41: 1 Planning & Optimising the Green IT Datacentre: Design, Operation & Management Best Practices, Technologies & Challenges Pierre Ketteridge, IP Performance

41

THANK YOU

Pierre Ketteridge, IP Performance Ltd

[email protected]

[email protected]

www.ip-performance.co.uk

Close