31
Iain Simmons Well-Connected Alliance (McConnell Dowell Constructors) The Waterview Connection Project k Progress update on the TBM Turnaround and Cross Passages Australian Tunnelling Conference 14 October 2015

Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Embed Size (px)

Citation preview

Page 1: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Iain Simmons Well-Connected Alliance

(McConnell Dowell Constructors)

The Waterview Connection Project k

Progress update on the TBM Turnaround and Cross Passages

Australian Tunnelling Conference 14 October 2015

Page 2: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Introduction to the Project

Auckland New Zealand’s largest city- Population of 1.46 Mio

- One third of NZ’s population

- 36% of gross domestic product

- Less than 2km wide isthmus

Key transport links- Running through congested central corridor

- Overly dependent on central, single north-south spine

2009 Government Policy- Seven roads of national significance (RONS)

- Waterview Connection is the ‘jewel in the crown’

Western Ring Route- Missing link between SH 20 and SH 16

- 48km motorway ring route

- Links major population and industrial centres

Waterview Connection- 5km of new motorway

- 2.4km of which comprises two three lane tunnels

Project Costs- NZ $1.4 B

Page 3: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

- Southern Zone – surface works from the tunnel’s southern portal to SH 20

- Tunnel Zone – underground works to build the twin 2.4 km three lane tunnels

- Northern Zone – surface works from the tunnel’s northern portals to SH 16, incl. GNR

interchange

3 Distinct Construction Zones

Page 4: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update
Page 5: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update
Page 6: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Tunnel Facts

- SB length 2398m, NB length 2410m

- Excavation dia. 14.41m, internal dia. 13.1m

- Max. vertical grade 5%, min. radius 1,500m

- Min. overburden above crown 10m at portals, max. overburden 40m

- 450mm segmental lining thickness

- Cross-passages 4.2m width x 4.8m wide x 11m long16 within driven tunnels, 2 within ventilation buildings

- One combined cross-passage / low point sump

- Cross-passage spacing 150m, length around 11m each

- 3 traffic lanes each direction

Tunnel Section – Connecting State Highway 16 with State Highway 20

Page 7: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Tunnel Work - Logistics

• All Logistics from Southern Portal

• 24hour Operation 6 days per Week

• Expected Spoil Volume approx. 800,000m3

• Spoil Removal via Conveyor Belt, up to 4620m3/day at peak progress

• 50,000 Truck Movements based on HPMV Trucks (17m3, 52 ton)

Multiservice Vehicle to carry one complete Segment Ring (9+1)

Multiservice Vehicle to carry two Invert Culverts

Page 8: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Geological Long Section

Three main Rock Types:

• Extremely weak locked Sands (EU1)

• Un-weathered Siltstone (EUL), alternating Siltstone/Sandstone (EUSL) and weak to very weak moderately cemented Sandstone (EUS2)

• Well cemented Sandstone (EUS3), volcaniclasticGrit/Sandstone (EUg)

Unit Unit Description Typical Strength

Vb Basalt UCS : 50 - 150 MPa

A Tauranga Group Alluvium Su : 30 – 70 kPa

ER Residual Soils Su: 50 – 150 kPa

EW Weathered ECBF Rock Su : 100 – 250 kPa

EU1 Extremely Weak Uncemented Sandstone

UCS : 0.5 - 2 MPa

EU2 Very Weak InterbeddedSandstone/Siltstone

UCS : 2 - 10 MPa

EU3 Weak Volcaniclastic, Coarse Grained Sandstone (Parnell Grit )

UCS : 10 – 30 MPa

Page 9: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

TBM Face Pressure Utilisation

Zone 1 2 2-1 3 4 5A 5B 5C 6 7 8 9 10 11A 11B 11C

0

100

200

300

400

11

00

0

11

10

0

11

20

0

11

30

0

11

40

0

11

50

0

11

60

0

11

70

0

11

80

0

11

90

0

12

00

0

12

10

0

12

20

0

12

30

0

12

40

0

12

50

0

12

60

0

12

70

0

12

80

0

12

90

0

13

00

0

13

10

0

13

20

0

13

30

0

13

40

0

13

50

0

Predicted face pressureOptional face pressure (+GW)Proposed face pressure by TRMActual face pressure applied

Chainage

Page 10: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Northern Portal TBM Operations

Page 11: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Northern Portal TBM Operations Face Pressure

Thrust Force

Page 12: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

North Portal TBM Reception MethodologySectional view of TBM and support frame in northern sump

Page 13: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

North Portal TBM Reception MethodologySectional view of TBM and support frame in northern sump

Page 14: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

North Portal TBM Reception MethodologyReview of the requirement for the arrival frame for southern reception

Page 15: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

TBM Head Inspection Cutterhead Condition at Breakthrough

Page 16: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Key facts

- Headwall support steel structure to secure headwallagainst TBM pressure before breakthrough

- TBM moved onto transport cradle for rotation and sideways movement

- Hydraulic jacks used to pull the cradle with the TBM loaded

- Steel floor plates and grease injection enable cradle to slide

- TBM startup using shove frame and temporary steel segments.

- Turnaround commenced in October 2014 and was completed 24 April 2015

including the construction of 250m of the northbound tunnel.

TBM turnaround - within NAT

Page 17: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

TBM Turnaround Pulling System

Page 18: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

TBM TurnaroundHydraulic Pulling Unit

Page 19: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Nicole sort out film clip

Page 20: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

TBM Turnaround Back Up Gantry Pulling System

Page 21: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

TBM Turnaround Back Up Gantry Pulling System

Page 22: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update
Page 23: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Cross Passages

• 16 number cross passages constructed between the main tunnels

• Each opening uses 6 steel segments

• Main tunnel lining propped before opening

• Horizontal and vertical wedges to ease removal of temporary panels

• Rigid connections with precast segments

• Special precast segments adjacent to the steel segments

Page 24: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Canopy Tubes

Cross Passages

Page 25: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Installing Props

Cross Passages

Page 26: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Cross PassagesPrimary Lining SprayedConcrete Support

Page 27: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Cross PassagesWaterproof MembranePermanent Lining Invert

Page 28: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Cross PassagesPermanent Lining Arch forms

Page 29: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Cross PassagesPermanent Lining Collars

Page 30: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Cross PassagesGround Improvement Pre-excavation Grouting at XP8, XP11 and XP12

Page 31: Iain Simmons - Well Connected Alliance - Waterview Tunnel construction update

Thank You