Waterview Connection - The Final Drive to completion Annual Australian Tunnelling Conference – Sydney 2016 Iain Simmons – Alliance Project Manager, Well-Connected Alliance David Taylor – M&E Construction Manager, Well-Connected Alliance 11 th October 2016

Iain Simmons & David Taylor - Well Connected Alliance

Embed Size (px)

Citation preview

Page 1: Iain Simmons & David Taylor - Well Connected Alliance

Waterview Connection -The Final Drive to completion

Annual Australian Tunnelling Conference – Sydney 2016

Iain Simmons – Alliance Project Manager, Well-Connected Alliance

David Taylor – M&E Construction Manager, Well-Connected Alliance

11th October 2016

Page 2: Iain Simmons & David Taylor - Well Connected Alliance

Waterview Connection –The Final Drive to Completion

1. (Re)Introduction to the project

2. Recap on tunnel facts

3. TBM final breakthrough

4. TBM de-mobilization

5. Status across the three distinct project zones

6. Cross passage completion

7. M&E fit-out to the tunnels and ventilation buildings

8. Timeline for completion

9. Community legacy

10. Questions

Contents

Page 3: Iain Simmons & David Taylor - Well Connected Alliance

Key Auckland transport links- Less than 2km wide isthmus

- Traffic running through congested central corridor

- Overly dependent on central, single north-south spine

- Network “ladder” model adopted

Western Ring Route- One of the NZ Governments seven roads of

national significance (RONS)

- Waterview Connection is the missing link between SH 20 and SH 16

- Completes 48km motorway ring route for the NZ Transport Agency

- Links major population and industrial centres

Waterview Connection- 5km of new motorway

- 2.4km of which comprises two three lane tunnels

Project Costs- NZ $1.4 Billion – the country’s biggest roading

project

(Re)Introduction to the Project

Page 4: Iain Simmons & David Taylor - Well Connected Alliance
Page 5: Iain Simmons & David Taylor - Well Connected Alliance

Tunnel Section – Connecting State Highway 16 with State Highway 20

Tunnel Facts

• Southbound length 2398m

• Northbound length 2410m

• Internal dia. 13.1m

• 3 traffic lanes each direction

• Max. vertical grade 5%, curve min. radius 1,500m

• 18 Cross-passages linking both main tunnels together, spaced every 150m

Page 6: Iain Simmons & David Taylor - Well Connected Alliance

Tunnel LayoutCross Section

M&E

Traffic Envelope

Lining

Pavement

Stage 2 Backfill

Stage 1 Backfill

Service Culvert

Page 7: Iain Simmons & David Taylor - Well Connected Alliance

Tunnel during excavation

Page 8: Iain Simmons & David Taylor - Well Connected Alliance

Completing the Northbound TunnelTBM Breakthrough

Page 9: Iain Simmons & David Taylor - Well Connected Alliance

De-commissioning the TBM

Completing the Northbound Tunnel

Page 10: Iain Simmons & David Taylor - Well Connected Alliance

Completing the Northbound TunnelDe-commissioning the TBM

Page 11: Iain Simmons & David Taylor - Well Connected Alliance

Completing the Northbound TunnelDe-commissioning the TBM

Page 12: Iain Simmons & David Taylor - Well Connected Alliance

Completing the Northbound TunnelDe-mobilisation of the TBM

Page 13: Iain Simmons & David Taylor - Well Connected Alliance

Great North Road Interchange (GNRI)

• 4 new Highway Bridges linking with State Highway 16

Page 14: Iain Simmons & David Taylor - Well Connected Alliance

GNRI Current Status

Page 15: Iain Simmons & David Taylor - Well Connected Alliance

Southern SectionAerial view looking South

Page 16: Iain Simmons & David Taylor - Well Connected Alliance

Finishing the Southern Approach PortalSouthern civils entering final stages

Page 17: Iain Simmons & David Taylor - Well Connected Alliance

Cross PassagesLogistical challenge of 16 cross passages

Page 18: Iain Simmons & David Taylor - Well Connected Alliance

Cross PassagesExcavation – monitoring load transfer

Page 19: Iain Simmons & David Taylor - Well Connected Alliance

Cross PassagesShotcrete primary support

Page 20: Iain Simmons & David Taylor - Well Connected Alliance

Cross PassagesWaterproof lining

Page 21: Iain Simmons & David Taylor - Well Connected Alliance

Cross PassagesInvert Formwork

Page 22: Iain Simmons & David Taylor - Well Connected Alliance

Cross PassagesCross PassagesCollar Reinforcement

Page 23: Iain Simmons & David Taylor - Well Connected Alliance

Collar Formwork

Cross Passages

Page 24: Iain Simmons & David Taylor - Well Connected Alliance

Completed cross passage ready to hand over to the M&E team

Cross Passages

Page 25: Iain Simmons & David Taylor - Well Connected Alliance

Completing the paving

What’s happening underground right now?

Page 26: Iain Simmons & David Taylor - Well Connected Alliance

Completing the M&E Installation

What’s happening underground right now?

Page 27: Iain Simmons & David Taylor - Well Connected Alliance

M&E Fit-out

• Main challenges and lessons learnt

• Ngarara - The drilling gantry

• M&E fit-out Scope of works

Page 28: Iain Simmons & David Taylor - Well Connected Alliance

Black roof 86,000m2

Tunnel Painting

White walls 48,000m2

Page 29: Iain Simmons & David Taylor - Well Connected Alliance

• Tunnel Anchors (Approximately 36,000 post installed mechanical anchors in bored tunnel)

• Supports (Approximately 8,600 supports in bored tunnel)

• Typically support groups located (longitudinally) in the centre of every ring, skipping every third ring, e.g. 2m, 2m, 4m spacing

Tunnel Supports

Page 30: Iain Simmons & David Taylor - Well Connected Alliance

• Tunnel lighting (4000)

• PA Speakers

• Radio Rebroadcast (RRB)

• Dynamic signage

Tunnel Systems

• Speed Cameras

• CCTV

• Overhead detection and barrier gates

Page 31: Iain Simmons & David Taylor - Well Connected Alliance

• Fire deluge and hydrants (175 sprinkler zones, 109 double hydrant outlets)

• Jet Fans (62)

• Sliding egress doors (36)

• LHD Cable (10km)

Fire Life Safety

Page 32: Iain Simmons & David Taylor - Well Connected Alliance

• Tunnel and culvert cable support system (50km cable tray)

• HV, LV, data and comms cabling (270T, 400km)

• 8 Transformers, 4 x 22kv Switchgear Panels, 8 x LV 690V/415V MSB, 4 x UPS Units, 500 Batteries, 64 x XP DB’s, 40 x RIO’s

Electrical Distribution

Page 33: Iain Simmons & David Taylor - Well Connected Alliance

• Exhaust Fans (8)

• Maintenance Hoists (17)

• HVAC

• Fire alarm, gaseous suppression and foam suppression systems

• 3 drainage sumps (13 pumps)

• Fire water storage tanks (5)

• Fire water pumps (5)

Vent Building Systems

Page 34: Iain Simmons & David Taylor - Well Connected Alliance

Challenges and Lessons Learnt

Design

• Subcontractor design

• Inter disciplinary coordination

Procurement

• Procurement packages

• Overseas supply and lead times

• Seismic compliance

Construction

• Planning & coordination amongst teams

• Storage & site facilities

Commissioning

• FAT

• Systems completion and handover

• Programme

Page 35: Iain Simmons & David Taylor - Well Connected Alliance

Challenges and Lessons LearntDesign

• Subcontractor design

• Inter disciplinary coordination

• Construction and stakeholder review

Procurement

• Procurement packages

• Overseas supply and lead times

• Post award Subcontractor submittals

• Seismic compliance

Construction

• Resourcing

• Construction area handover

• Planning & coordination amongst teams

• Storage & site facilities

Commissioning

• FAT

• Systems completion and handover

• Programme

Page 36: Iain Simmons & David Taylor - Well Connected Alliance

Ngarara – The Drilling Gantry

Page 37: Iain Simmons & David Taylor - Well Connected Alliance

Ngarara – The Drilling Gantry

Page 38: Iain Simmons & David Taylor - Well Connected Alliance

Ngarara – The Drilling Gantry

Page 39: Iain Simmons & David Taylor - Well Connected Alliance

Overall Project Programme

October

2016

Page 40: Iain Simmons & David Taylor - Well Connected Alliance

Waterview Playground

Community Benefits – already in use

Page 41: Iain Simmons & David Taylor - Well Connected Alliance

Boardwalks, Shared paths, Skate parks, BMX tracks

Community Benefits – more to come

Page 42: Iain Simmons & David Taylor - Well Connected Alliance

Thank you