16/07/2015 GSA Call for Grants info session. 1 ESSP support to LPV implementation Alejandro Fransoy

ESSP support to LPV implementation

Embed Size (px)

Citation preview

Page 1: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 1

ESSP support to LPV implementation

Alejandro Fransoy

Page 2: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 2

Table of Contents

• EGNOS implementation steps and lessons learnt from previous projects:- Recommendations for ANSPs and Airports- Recommendations for Operators

• ESSP offered support

Page 3: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 3

ESSP support to LPV implementation

Recommendations for ANSPs and airports

Page 4: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 4

1. Meeting National Authority • Establish regular coordination and planning

• Set the implementation project team

• Define the objectives and scope

• Make a first preliminary assessment

• Review existing regulation and guidance

Plan 1 to 3 months

Set an appointment well in advance

Duration

Costs NA

ESSP support to LPV implementationRecommendations for ANSPs and airports

Page 5: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 5

1. Meeting National Authority

2. Airport Capabilities Assess.

• Define CAA requirements

• Airport characterization:

• Navaids (missed APCH)

• CNS (radar)

• ATC/AFIS/No ATC

• Meteo

• Airspace (un/controlled, SID/STAR, etc)

• Infrastructure (lighting, strips, etc)

• Traffic and a/c capabilities

1 to 2 months Duration

Costs NA (subcontract)

ESSP support to LPV implementationRecommendations for ANSPs and airports

Page 6: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 6

1. Meeting National Authority

2. Airport Capabilities Assess.

3. Procedure Design

• Obstacle site survey (update)

• Usually the design is performed by ANSP o Pans Ops 8168 Vol II, Part III; o Annex 14 Vol I; o ICAO 9906 Vol II

• Possibility to subcontract third parties like surveyors, procedure designers or other ANSPs

• Preliminary approval by CAA sometimes req.

2 to 3 months + NSA approvalDuration

Costs 15 – 30k€ for 2 RWY ends

ESSP support to LPV implementationRecommendations for ANSPs and airports

Page 7: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 7

1. Meeting National Authority

2. Airport Capabilities Assess.

3. Procedure Design

4. Flight Validation

• Ground validation

• Independent review of procedure design package

• GNSS SIS assessment (optional) + interferences

• Procedure impact in operations

• Flight validation (need for FAS DB)

• Obstacles (identification of new ones)

• Navigation data

• Fly-ability (pilot workload)

1 to 3 months Duration

Costs 5 to 40k€

ESSP support to LPV implementationRecommendations for ANSPs and airports

Page 8: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 8

1. Meeting National Authority

2. Airport Capabilities Assess.

3. Procedure Design

4. Flight Validation

5. Safety Assessment

• CONOPS, EC 2096/2005 and EC 1315/2007

• Eurocontrol Methodology SAM:

• Functional Hazard Assessment (FHA)

• Preliminary System Safety Assessment (PSSA)

• System Safety Assessment (SSA)

2 to 6 monthsDuration

Costs 10 to 40k€

ESSP support to LPV implementationRecommendations for ANSPs and airports

Page 9: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 9

1. Meeting National Authority

2. Airport Capabilities Assess.

3. Procedure Design

4. Flight Validation

5. Safety Assessment

6. Procedure Approval

• Need for EWA (plan in advance)

• Re-visit:

• Safety assessment

• Procedure design

• Flight validation

1 to 2 monthsDuration

Costs 2 – 4k€

ESSP support to LPV implementationRecommendations for ANSPs and airports

Page 10: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 10

1. Meeting National Authority

2. Airport Capabilities Assess.

3. Procedure Design

4. Flight Validation

5. Safety Assessment

6. Procedure Approval

7. ATCO Training

• Core training

• RNAV concept

• Performances, GPS, RAIM…

• Flight plan

• ATC procedures

• Contingency procedures, separation minima, mixed equipage, phraseology

• Specific to RNP

• Radar vectoring, APCH minima, T&Y…

1 to 2 monthsDuration

Costs 10 to 20k€

ESSP support to LPV implementationRecommendations for ANSPs and airports

Page 11: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 11

1. Meeting National Authority

2. Airport Capabilities Assess.

3. Procedure Design

4. Flight Validation

5. Safety Assessment

6. Procedure Approval

7. ATCO Training

• Charting (ARINC 424)

• SBAS Channel number (Eurocontrol)

• AIRAC 56 days

• AIC/AIP

• Data recording and monitoring

• Publication by AIS provider

8. AIP publication

2 – 3 monthsDuration

Costs NA (ANSP effort usually)

ESSP support to LPV implementationRecommendations for ANSPs and airports

Page 12: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 12

1. Meeting National Authority

2. Airport Capabilities Assess.

3. Procedure Design

4. Flight Validation

5. Safety Assessment

6. Procedure Approval

7. ATCO Training

8. AIP publication

Duration:• 24 months (1st LPV)• 10-15 months otherwise

1 – 3 months; NA

1 – 2 months; NA

2 – 3 months; 15 - 30 k€

1 – 3 months; 5 - 40 k€

2 – 6 months; 10 – 40 k€

1 – 2 months; 2 – 4 k€

1 – 2 months; 10 – 20 k€

2 – 3 months; NA €

Cost: 40 – 140 k€ 2RWY-ends

ESSP support to LPV implementationRecommendations for ANSPs and airports

Page 13: ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 13

ESSP support to LPV implementation

Recommendations for Operators

Page 14: ESSP support to LPV implementation

1. Establish the certification plan • Establishment of Certifying Authority, e.g. EASA• Agreeing the certification basis, e.g. EASA CS-23,

CS-25, etc• Agreeing the compliance summary, e.g. EASA

AMC 20-28• Timeline of deliverables

1 to 2 monthsDuration

Costs NA (subcontracting)

ESSP support to LPV implementationRecommendations for Operators

16/07/2015 GSA Call for Grants info session. 14

Page 15: ESSP support to LPV implementation

1. Establish the certification plan • Part 21 (DOA) or TC Holder (manufacturer)• Aircraft survey• Design data Package• A/C conversion + ground/flight test• Compliance demonstration• STC design approval

STC/SB not available

2. STC/SB elaboration

6 to 10 monthsDuration

Costs 20 to 120 k€ per aircraft

ESSP support to LPV implementationRecommendations for Operators

16/07/2015 GSA Call for Grants info session. 15

Page 16: ESSP support to LPV implementation

1. Establish the certification plan • Part 145 or Manufacturer• Purchase STC• A/C conversion• Airworthiness re-certification

STC/SB not available

2. STC/SB elaboration

STC/SB available

3. Implement changes

3 to 6 monthsDuration

Costs 3 to 120 k€ per aircraft

ESSP support to LPV implementationRecommendations for Operators

16/07/2015 GSA Call for Grants info session. 16

Page 17: ESSP support to LPV implementation

1. Establish the certification plan • Operational Procedures and documentation:

• Operational Procedures Update• Operations Manual Update• Navigation Database Management

• Crew training and training package update• Application for Operational Approval

STC/SB not available

2. STC/SB elaboration

STC/SB available

3. Implement changes

4. Operational approval

2 to 6 monthsDuration

Costs 5 to 20 k€

ESSP support to LPV implementationRecommendations for Operators

16/07/2015 GSA Call for Grants info session. 17

Page 18: ESSP support to LPV implementation

1. Establish the certification plan

STC/SB not available

2. STC/SB elaboration

3. Implement changes

4. Operational approval

1 – 2 months; NA

6 – 10 months; €20k-€120k

3 – 6 months; €3k-€120k

2 – 6 months; €2k-€20k

ESSP support to LPV implementationRecommendations for Operators

• STC/SB available: 6-18 months; €5k-€140k (per a/c) • STC/SB NOT available: 12-24 months; €25k-€160k (per a/c)

16/07/2015 GSA Call for Grants info session. 18

Page 19: ESSP support to LPV implementation

ESSP support to LPV implementation

• LPV implementation status – Published and planned airports, certified & approved operators

• Comprehensive guidance material– ANSPs and airports (Implementation and publication)– Operators (Certification, Training and & Op. Approval)

• Support for EWA signature• Support services catalogue

– Manufacturers, Part 21s, Part 145s– STCs and SBs: available and under development (Part 21 organisations and manufacturers)– Promotion of new (AML) STCs and SBs– Procedure designers and flight validation companies

Awareness Technical support

16/07/2015 GSA Call for Grants info session. 19

Page 20: ESSP support to LPV implementation

• Performance Assessments– EGNOS SoL service performances– EGNOS NOTAMs proposals

• Cost Benefits Analyses– For airports/ANSPs

• Accessibility, navaids rationalisation

– For operators• Avoided DDCs, fuel savings

• Dedicated Workshops• Technical advice on implementation

projects (lessons learnt, PoCs)

Awareness Technical support

Check-out our online EBCAST tool

ESSP support to LPV implementation

16/07/2015 GSA Call for Grants info session. 20

Page 21: ESSP support to LPV implementation

EGNOS User Support websitehttp://egnos-user-support.essp-sas.eu/

• LPV implementation map• Business Case Tool• Guidance material for LPV approval• LPV training package• EGNOS information:

Success stories Brochures Bulletins

16/07/2015 GSA Call for Grants info session. 21

Page 22: ESSP support to LPV implementation

THANKS FOR YOUR [email protected]