7/27/2019 SAIC-D-2018 Rev 2
1/1
1. SAES-D-109, Design of Small Tanks, (29 December 2004) & 04 January 2006 (on Dec 2005 Cutoff CD)
contract & use this document along with this checklist as applicable.
REFERENCE DOCUMENTS:
A5Alternative under-tank leak detection and sub-grade protection systems
have prior approval of the Saudi Aramco Engineer.
SAES-D-109
Para 14.3.4
A3 The liner is extended to the internal top edge of the ring foundation.SAES-D-109
Para 14.3.2
A4Joints in the liner are satisfy the leak tightness, permeability, and
chemical resistance requirements for the liner material.
SAES-D-109
Para 14.3.3
A1Flexible membrane liner of minimum 1000 microns (40 mil) thickness
compatible with the stored product are applied under tank bottom.
SAES-D-109
Para 14.3.2
Saudi Aramco
Name, Sign and Date:
A2 Liner is placed at bottom of the ring foundation or minimum 1 meterbelow the top edge of the ring foundation whichever is greater.
SAES-D-109Para 8.6 / 14.3.2
Name, Organization,
Initials and Date:
T&I Witnessed
Y = YES N = NO F = FA*Person Responsible for Completion of Quality Work / Test
REMARKS:
QC Supervisor Proponent and Others
Contractor / Third-Party
NOTES: 1. December 2005 Cutoff Standards CD contains 04 January 2006 Major Revision to SAES-D-109. Ensure this is applicable to the
Name, Initials and Date:
Quality Record Approved: Work Verified
Performed Inspection Work / Rework May Proceed
Name, Initials and Date:
T&I Witnessed QC Record Reviewed
Construction Representative* PMT Representative
Work VerifiedT&I WitnessedName, Initials and Date:
Work is Complete and Ready for Inspection:
Name, Initials and Date:
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05
SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED
SAIC-D-2018 1-Dec-06 MECH-
QC Record Reviewed
Work Verified
QC Inspector PID Representative
QC Record Reviewed
QR NUMBER
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
Insp of Under-Tank Leak Detection, Sub-Grade Protection
PLANT NO.EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
TRAVEL TIM
SAUDI ARAMCO USE ONLYSCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUI
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
ITEM
No.ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DA
Page 1 of 1