Jubilee site redevelopment
1
Project summary
The redevelopment of the Moberly and Jubilee Leisure Centres is part of the Active Queen’s Park project, that will bring a major improvement and increase in the amount of sports and leisure facilities in the Queen’s Park area.
Jubilee Phase 1 – Completed September 2017• Comprised 28 Apartments/Maisonettes
Moberly Leisure Centre development – Completed in January 2019• Leisure Centre opened in June 2018 (circa 80,000 sq. ft.)
• 56 Apartments and 15 Townhouses
Jubilee Phase 2 – Due for completion autumn 2022• The new Jubilee Leisure Centre will be a multi-use three-court
sports hall and community suite
• 56 new homes, 19 of which will be made available by the council at below market rents
Aerial view of Jubilee site
Phase 1 Phase 1
© Google Maps 2020
Jubilee site redevelopment
2
The scheme - Phase 2
Westminster City Council, in partnership with developers EcoWorld International, is building 56 new homes, 19 of these affordable, and providing a new leisure centre. Overall the development will consist of:
• 56 homes - 11 one-bedroom apartments, 25 two-bedroom apartments and 20 three-bedroom houses.
• 19 of these homes will be purchased by Westminster City Council to provide at below-market rents. Of the 19, four will be one-bedroom and 15 will be two-bedroom homes
• These 19 homes will be built above the new Jubilee Leisure Centre comprising a multi-use three-court sports hall and community suite.
© Levitt Bernstein
Community Suite
Multi-use Sports Hall
Lancefi
eld Street
Caird Street
Bruckner Street
Bannister House
Th
ird A
venu
e
Barfe
tt Stree
t
Seco
nd
Ave
nu
e
First Ave
nu
e
Th
ird A
ven
ue
Jubilee site redevelopment
3
Elevated visuals
© Levitt Bernstein
© Levitt Bernstein
Architect’s impression of Caird Street
Architect’s impression of Lancefield Road and Jubilee Leisure Centre
Jubilee site redevelopment
4
SITE SET UP17 February•Demolition vehicle movement onto site.
•Installation of Welfare Units & O�ce (2 x 35ft Container Cabins).
Demolition vehicle movement onto site.
Installation of welfare units and o�ce (2 x 35ft container cabins).
SCAFFOLDING24 February – 9 March•Erected in two locations: Caird Street and Lancefield Street.
•Sca�old will be wrapped in tough plastic sheeting (Monoflex) for the protection of the public from noise and dust.
Erected in two locations: Caird Street and Lancefield Street.
Sca�old will be wrapped in tough plastic sheeting (Monoflex) for the protection of the public from noise and dust.
HOARDING17 February – 2 March•Repairing, realigning and repainting the hoardings.
•Adding notice boards to keep residents informed.
•Safety Signs displayed for public and contractor safety information.
Repairing, realigning and repainting the hoardings.
Adding notice boards to keep residents informed.
Safety signs displayed for public and contractor safety information.
STRIP OUT17 February – 2 March• Removing internal content from buildings.
• Removing waste from site via lorries.
MECHANICAL REMOVAL16 March – 13 April•Demolition Excavators begin demolition (folion sequence)
•Larger sections of buildings to be dismantled methodically by pulverising into smaller pieces, crushed into smaller pieces (approx. 75mm and under).
SITE CLEARANCE27 April•Ensuring all waste and surplus products are removed from site.
•Site is left in a clean, safe condition to be handed over for the next phase.
•Removal of Welfare Units, Machinery & Equipment.
Ensuring all waste and surplus products are removed from site.
Site is left in a clean, safe condition to be handed over for the next phase.
Removal of welfare units, machinery and equipment.
REMOVAL OF SLAB AND FOUNDATIONS30 March – 20 April• All concrete ground slabs and
foundations holding up the existing building will be removed by breaking down into smaller pieces and stockpiled ready for crushing on site.
PREPARING MATERIAL FOR REUSE6 – 26 April•All hardcore and concrete will be crushed on site so that it can be reused for the construction of the new build.
•This process will reduce the number of lorries having to enter and exit the site to take waste away.
All hardcore and concrete will be crushed on site so that it can be reused for the construction of the new build.
This process will reduce the number of lorries having to enter and exit the site to take waste away.
BACKFILLING WITH 6F220 April – 27 April•The crushed material which has been reduced in size to approx. 75mm and under is then certificated as a product known as 6F2, which can then be used as a base material to form paths, roads, piling mats etc.
The crushed material which has been reduced in size to approx. 75mm and under is then certificated as a product known as 6F2, which can then be used as a base material to form paths, roads, piling mats etc.
Excavators begin to take down existing building.
Larger sections of buildings to be dismantled methodically by breaking into smaller pieces (approx. 75mm and under).
20
20
17 F
EB
RU
AR
Y
24 F
EB
RU
AR
Y
2 M
AR
CH
9 M
AR
CH
16 M
AR
CH
27
MA
RC
H
30
MA
RC
H
6 A
PR
IL
13 A
PR
IL
20
AP
RIL
27
AP
RIL
Programme to remove existing buildings - February to April 2020
Site working hoursSite working hours will be between 08.00 and 17.30 on Monday-Friday and 08.00 and 13.00 on Saturday. To avoid peak time congestion, deliveries will not take place between 8.30 to 9.30am and 2.45 to 3.45pm weekdays. Vehicles will not stop on Caird Street/Lancefield Street.
Note: All dates shown are estimated week commencing and could be subject to change.
Jubilee site redevelopment
5
The demolition sequence is used to define the order and direction in which the buildings will be demolished.
The yellow arrows in the adjacent diagram illustrate the direction in which each building will be demolished. For example, demolition of building A will commence at the north end, completing at the south, and building B will be demolished from the east to west side.
While the demolished remains of buildings A and B are being processed and sorted into stock piles ready for removal or reuse, demolition of building C will commence.
Whilst demolition arisings from building C are being processed, excess waste generated from buildings A and B will be removed from site via the primary site entrance.
Demolition sequence• Removal of intermediate
single storey building A
• Removal of swimming pool building B
• Removal of reception and sports hall building C
• Crushing of materials for reuse
• Backfilling – swimming pool and foundations
Key
Site entrances
Site boundary
Sequence of mechanical demolition
Scaffolding
2m diameter live brick sewer, 10m down
Site assembly point
Welfare unit and site office
Sequence to take down existing buildings
B
C
A
Primary site entrance
Secondary site entrance
Key personnel – Northeast Demolition UK Ltd. 17th February to 30th April 2020
• Bradley Harris, Contracts Director 07841 993093
• Ronnie Mould, H&S Director 07794 124261
• Joseph May, Site Manager 07702 260235
Jubilee site redevelopment
6
Site vehicle entrance
Site working hoursSite working hours will be between 08.00 and 17.30 on Monday-Friday and 08.00 and 13.00 on Saturday. To avoid peak time congestion, deliveries will not take place between 8.30 to 9.30am and 2.45 to 3.45pm weekdays. Vehicles will not stop on Caird Street/Lancefield Street.
The primary site entrance is on Lancefield Street, and demolition related vehicles will enter and exit the site via Harrow Road, Second Avenue, Caird Street, to Lancefield Street.
Key
Vehicle path
Jubilee site
Areas taken in to consideration
Seco
nd
Ave
nu
e
Bar
fett
Str
eet
Firs
t A
ven
ue
Alperton Street
Caird Street
Th
ird
Ave
nu
e
Lance
fie
ld Stre
et
Harrow Road A404
Queen’s Park Public Open Space
St Marylebone CE Bridge School
Queen’s Park Gardens Wildlife Area
Queen’s Park Primary School
Primary site entrance
Jubilee site redevelopment
7
Timeline – January 2020 to autumn 2022
Key personnel and contact details
Monday to Friday (working hours)
• Andrew Hinkins, Senior Development Manager or Laura Montgomerie, Head of Customer Care on 0330 166 2255
Out of hours
• Joseph May, Site Manager – 07702 260235
AUTUMN 2022Jubilee Leisure Centre to openBlock B Townhouses complete
JANUARY 2020Site investigation works
FEBRUARY 2020 TO APRIL 2020Demolition programme commences
FEBRUARY 2020 TO AUGUST 2020Detailed Design and Procurement
AUGUST 2020 TO DECEMBER 2021Construction works commence
DECEMBER 2021Block A and B Apartments complete
Jubilee Leisure Centre available for fit out
20
20
FEB
RU
AR
Y
MA
RC
H
AP
RIL
MA
Y
JUN
E
JULY
AU
GU
ST
SEP
TE
MB
ER
OC
TO
BE
R
NO
VE
MB
ER
DE
CE
MB
ER
20
21
FEB
RU
AR
Y
MA
RC
H
AP
RIL
MA
Y
JUN
E
JULY
AU
GU
ST
SEP
TE
MB
ER
OC
TO
BE
R
NO
VE
MB
ER
DE
CE
MB
ER
20
22
Dates are indicative to overall works programme and could be subject to change.