DUNS-Nr.:
Rating scale first development (Tier 1): A = 90 - 100% Development capability fulfilled
B = 75 - 89% Development capability partially fulfilled
C = < 75% Development capability not fulfilled
Rating scale second development (Tier 2): incapable/capable
Assessment
Date:
Distributor:
Plastic parts for GM and Mazda
Pritzke, Jens (K-ES/B1)
Seite 1/5
Form responsibilitiy: Volkswagen AG, K-ES TE-Lieferantenbewertung, Brieffach 1446, 38436 Wolfsburg, DeutschlandChange status 01.11.2008 (A4-Format)
Poerksen, Maik (VWG Malaysia)
Che, Fong Mei (VWG Malaysia)
Werner, Thorsten (EKKF)
Raguse, Michael (EKP/Z)
Second Development
ProductsLocations/Development locations JV-Partner
Main plant Shah Alam, Selangor (MY)
Capable
Findings / Requirements / Highlights / Management informations
No of Employees
Technical Tie-up with Marui (since 2010)
(Global Sourcing)(Forward Sourcing)
Location information to suppliers
Corporate structure:
FE
648
Niedenfuehr, Sven (EKKF/2)
ASSY Door Trim
Armrest : >PES< 867-
Plastic Injection moulding >PP<
6RU
-
011C 74%
Component-related assessment of development partnerConsolidated Development Control, K-ESB
Lot 76 & 75A, Jalan Sementa 27/91, Section 27, 40000 Shah Alam, Selangor,Malaysia
Hicom Teck See Manufacturing Malaysia Sdn. Bhd.
652100793Potential analysis for localization
VW 250 G (RL IN)
Visit purpose:
Nazare, Anja (K-ESB)
Utzeri, Giancarlo (K-ES/B1)
Lauck, Joachim (K-ESB)
First DevelopmentPart number
Name, Organisation, Auditor Signature Name, Company Signature
Terence SOO Thean Hin (COO)Walenkamp, Gijs (K-ESB - TE-Auditor)
Audit Result
24.09.2010
Rayong plant(Thailand)
Tanjung Malim plant(MY)
210
Plastic parts23
Component/Product Group(with product technology)
Information to suppliers :-Hicom-Teck See belongs to 51% DRB-HICOM and 49% Teck See Plastic.
-Built in 1962 with a capital of ¡Ö RM260 Mil. In 2009 and 810 employees -Product Portfolio : Plastic parts (Instrument panel, bumper, door trim)
-Customer : Proton, Perodua (ca. 95% Tier 1) and Brose (Tier 2) 97 % Tier1 vs. 3 % Tier2 -Certification : ISO 9001 , ISO / TS 16949, ISO 14001
Management info for assessment results :The company HTS is currently classified as a typical manufacturing / Built-to-print supplier for plastic circumferences like instrument panel without
slush-OB, door trim and bumper. This company is in consideration as a potential supplier for a localization project of VW Polo G-Circumferences The company is able to produce based on customer data tools and set up appropriate production processes and carry out optimization loops
Significant own development skills are lacking. CAD and CAE expertise, testing facilities and material testing.
The project management is structured and based on customer specifications
Other differences: see report
Premise Procurement :
-Support through a TE-Wolfsburg engineering services
-Termination of the report illustrated weaknesses
-Introducing company/technical concept in operating department TE-Wolfsburg
The company was requested to eliminate the weaknesses as mentioned in the report, with a nomination by an action plan. Plant : Overview of test equipments, material safety data sheets, Chrome planning
Development Partner's Info
Customer
Part name: Part-Number.:-
6RU 867
(Emphasis [Sum 100%])
1. Specification and environment norm (2%)
2. Design and simulation system (17%)
3. Design capacity and skills (19%)
4. Technology und Product (4%)
5. Testing (19%)
6. Prototyping (15%)
7. Project competency/communication (12%)
8. Methods of project development (12%)
Result analysis:
Forward Sourcing 194
(new Product Design) 260*100
Global Sourcing(without new product design)
Participants:
Azmi Wahap (Manager Autom.Comp.&Eng. Division) Kainz, Thomas (QS-Auditor, Audi Ungarn)
Seite 2/5
If yes, from which supplier:
Selangor (Malaysia)
Sarly Adle Bin Sarkum (Head of Division Bus.Dev.)
No
Current Development Projects and Customers:
If the development partners already judged :
Component orProduct group
Technology
Rating result:Date:Middle group:Product:
capable
Judgement criteria for Project:
Total Result
New Product Design
(Forward Sourcing)
Remarks
Yes
Development location(s):
Contact person and position:
Experience cooperation in SE-Process
Proton, Perodua, Mazda, Honda…
Plastic parts in interior and exterior
Various -
Points180
VW 250 G (RL IN)
also with the participants from DRB-Hicom Headquarters
Sarly Adle Bin Sarkum (Head of Division Bus.Dev.)
Saw, David (VWG Malaysia)
Adam Mat Robi (Manager Project Development)
…
Walenkamp, Gijs (K-ESB - TE-Auditor)
Volkswagen AG
Yau Kian Min (Manager Bus.Dev. Division)
Terence SOO Thean Hin (COO)
Yohan bin Mokhtar (Senior Manager Veh.Man.Proj.)
Lim Sheng Shun (Senior Manager Prod. Planning)
Poerksen, Maik (VWG Malaysia)
Che, Fong Mei (VWG Malaysia)
Hicom Teck See Manufacturing Malaysia Sdn. Bhd.
Component-related assessment of development partner
Result =
74%Result = C
ASSY Door Trim
011
30 40 50 60 70 80 90 100
Performance level [%]
30 50 70 90
=max. 260 Points reachable
max. 230 Points reachableEvaluation criteria 2.3, 4. and 8.aare not included in the assessment
corresponds to Rating:
corresponds to Rating:
6R06RG
807853
221.D651
1. 0 5
2.
2.1 0 10
2.2 0 20
2.3 0 4 6 8 10
2.4 0 5.
.
3.
3.1 0 16 24 32 40
3.2 0 4 8 12 16
3.3 0 4 6 8 10
.
4. 0 4 6 8 10
.
Seite 3/5
Does the development partner possess design competency:
If 3.1 =< 24, has the development partner access/grasp to alternatives (foreign capacity):
(max. 50 Points)3. Result
1. and 2. Result
Does the development partner possess sufficient design capacity:
Design capacity and competency
DFÜ: Design data management system not available
VW-compliant data check module: End check & Validity: Catia V5 R19 not available
Points
o
Requirement not fulfilled
Requirement insufficiently fulfilled
Requirement generally fulfilled, deviation present
Requirement generally fulfilled, slight deviation
Requirement fully fulfilled
Component-related assessment of development partner
Cover front and back
ASSY Radiator Grille
Has the development partner all the required specifications and environment standard
Hicom Teck See Manufacturing Malaysia Sdn. Bhd.Assessment criteria for
Points
Points
Points
Points
Has the development partner CAD System compatibility acc. To VW AG (VW01059) and actual System guidelines
Yes, should: Catia V5 R19
CAE: Know-how limited availability, proposed amendment to optimise tooling come from tools supplier
Based on Class A-Surface-Data, component construction at OEM proton on site are performed by 3 of Hicom Teck See employees.
At visited headquarters: CAD Data and drawing management / dissemination at tools supplier
Employee qualification : current state matrix, without forecast
VW99000: available, content unknown
B2B access incl. ESL available, person responsible: Project manager
Catia V5 R18 an 19: 3 Licenses
B2B contents should be centrally file and all involved project to be provided
Design- and Simulation System
Has the development partner CAD Systems - if yes, state:
Plastic full simulation and warping: moldflow-analysis would be performed via tools manufacturer; Documentation available
FE Simulation to vehicle occupant protection (ECE, FMVSS, EuroNCAP), head impact, modal analysis and acoustic (NVH), misusage: all about OEM/Customers
Is the development partner using innovative Construction and Simulations method:
CAD-Data storage needs to be improved (Stucture, partial disk, CD-Rom)
Processes: Plactics IM, Blow Molding, no Slush or material after spraying, manual painting at location, using Robot in Thailand branch,
Chrome: currently external supplier, internal facility will be establish in 2011 (micropores)
Used weld technology I-Panel:US-welding (2x), HSK: Hot-Plate welding, no laser trimming or Waterjet available, manual trimming support plate door trim
Plastic: resin --> local resin supplier (see data sheet)
Technology and Product - Does development partner possess innovation potential
If yes, for which product, process or material:
(max. 10 Points)4. Result
Datas are exchanged using CD-ROM with OEM-customer (Proton)
Tools supplier (e.g Moltec, DongWang, Hanguk from Malaysia, Korea, Taiwan)
IDIADA (Spain): Head impact FEM-Analysis
Overall-design: 3Employees (CAD) / CAE: 0 Employee / Project management: 6 Employees as Programme manager plus 14 Product engineers
Has the development partner DFÜ (Data Transmission) and Data Check Module for drawing exchange
(max. 50 Points)
6RU 867 011
Points
Requirement not fulfilled
Requirement insufficiently fulfilled
Requirement generally fulfilled, deviation present
Requirement generally fulfilled, slight deviation
Requirement fully fulfilled
Component-related assessment of development partner
ASSY Door TrimHicom Teck See Manufacturing Malaysia Sdn. Bhd.Assessment criteria for
Points
Points
Points
Points
5.
5.1
a) 0 8 12 16 20 1 -
b) 0 8 12 16 20 1 -
c) 0 8 12 16 20 1 -
d) 0 8 12 16 20 1 -
5.2
a) 0 8 12 16 20 1 -
b) 0 8 12 16 20 1 -
c) 0 8 12 16 20 1 -
0 8 12 16 20 1 -
5.3
a) 0 8 12 16 20 1 -
b) 0 8 12 16 20 1 -
c) 0 8 12 16 20 0
d) 0 8 12 16 20 0
-
5.4 0 20
5.5 0 4 8 12 16
5.6 0 4 6 8 10
-
6.
6.1 0 8 12 16 20
6.2 0 20
6.3 0 4 8 12 16
-
If 5.4 = 0, has the development partner access to alternative (foreign capacity):
The development partner has sufficient testing competency:
external Institute : e.g. TÜV Singapore, IDIADA, local OEM Proton
Testing
Has the development partner appropriate test capabilities for functional testing: Block 5.1 = (Sum of a+b+c+d) / ( No a+b+c+d)
Block 5.3 = (Sum of a+b+c+d) / (No. a+b+c+d) Has the development partner appropriate laboratory equipment and instrumentation:
Block 5.1 = (Sum of a+b+c+d) / ( No a+b+c+d) Has the development partner appropriate test capabilities for continuous testing :
EP 85550.30: Ball drop test on loudspeaker grill (M=0,5 kg RT-10°C, PV3905) --> external institute or OEM
EP 85550.70: Misuse by forces up 500 N on mesh, door tray box under RT-30+70°C --> external institute or OEM
Present : Gauges.
EP 84610.21: continuous load of arm rest and door handles (steel ball, 150 N, N=10000, -30+70°C) --> external institute or OEM
EP 84110.01: Push in / push out forces / Tear off test of fasteners (RT) --> external institute or OEMEP 84610.10: Function Test: load on arm rest / door tray --> external institute or OEM
EP 84610.12 /EP85550.22: Buckling resistance of trim panel and door tray (RT,+70°C)
EP 84610.50: Temperature aging +LF--> climate chamber (-30+100°C+LF, 48h) -> 1x Climate chamber (-30+177°C+LF) EP 84610.51: climatic cycle---> climate chamber (PV2005) -> 1x Climate chamber (-30+177°C+LF)
EP 85550.10: Door closing Function test by pulling on tray (150N, -30+70°C, N=1000) --> external institute or OEM
High temp. lightfastness (PV1303, 5 cycles, 100 °CXenontest=solisi) --> external institute or OEM
Present : Dimension, Weight, Measuring table, auto. 3D measuring machine (unexact, +/- 0.1 mm). External : Flammability (TL1010)
Material e.g PP : Emission behaviour, Fogging (VW 50180), density, yield stress, elongation, ball indenation hardness, melting temp.…
Continuous monitoring relevant : Present --> Glossmeter
Checking gauge in plastic plant : Present --> Single part and Assy
Significant amounts are performed externally
Ergebnis = (Summe aus den Blöcken 5.1+5.2+5.3) / (Anzahl der Blöcke)
Has the development partner sufficient testing capacity:
Prototyping
(max. 40 Points)6. Results
If 6.2 = 0, has the development partner access to alternative (foreign capacity):
Has the development partner sufficient prototyping capacity:
Has the development partner an adequately equipped and organizationally independent prototyping:
Documentation as per PPAP-Document (Measuring report, test report)
Present : Detailed testing plan, testing specification and documentation
Present : Calibrated and documented measuring devices / no temperature controlled measuring room
Organizationally not independent. Plastic parts are manufactured on original equipment, assembly and construction prototypes in production
Suppliers of component parts
Gauges are used for measuring test part
1 room for master sample storage
Manufacturing and supplier for single part
(max. 50 Points)5. Results
Seite 4/5
Hicom Teck See Manufacturing Malaysia Sdn. Bhd.Assessment criteria for
Points
Points
Points
Points
6R06RG
807853
221.D651
Points
Requirement not fulfilled
Requirement insufficiently fulfilled
Requirement generally fulfilled, deviation present
Requirement generally fulfilled, slight deviation
Requirement fully fulfilled
Component-related assessment of development partner Cover front and back
ASSY Radiator Grille
7.
7.1 0 10
7.2
0 4 6 8 10
7.3 0 4 6 8 10
7.4 N J
.
8.
0 4 6 8 10
0 4 6 8 10
0 4 6 8 10
8. Result (max. 30 Points)
9.
Remarks
Seite 5/5
- Advance know how product development methods (D-FMEA, QFD, DOE)
- Implement capacity planning
- Expansion of test facilities according to part testing specification (Special climate chamber, -40 ° C
/ upgrading auto. measuring machine including Scanpack / material analysis)
- Advance their know how in terms of FEM-methods
- Improve CAD-data storage
(max. 260 Points)Assessment Result
(max. 30 Points)7. Result
Can the development partners set schedules with milestones and resource allocation
Is direct communication (without translation) possible:
and ensure the execution of changes
Project competency / Communication
Processes and to PM clearly defined / structured customized centralized project storage at the server / schedules using MS Project Milestones customer, without critical path
with filling) / Open-point list available
For under development project, project rooms are set up (currently as Proton, Honda)
c) DOE Methods:
b) Design-FMEA:
a) QFD Methods:
English
Is it possible to carry out a development at customer's premises
Is the development partner applying the QM methods
Methods of product development
currently not implemented
QFD not shown in action,part of the circumference in the form of benchmarking by means of various examples
currently no D-FMEA (---> Built-to-print Supplier)iP-FMEA content in order including derivation process monitoring
.
An improvement plan must be presented upon nomination within 14 days after receiving of this report.
In addition the supplier was informed that the next TE capability audits and project-specific performance rating be pronounced by the department.
- Study the contents of B2B-Portal (Supplier manual, norm portal, VW99000…)
- Advance their know how in terms of component design and tool-based design (plastic parts, steering wheel frame)
- Ensure access to KVS
-
At regular time intervals (agreed with the department) significant schedules, to-do lists and meeting of minutes should be provided. .
The company was advised that a pro-active communication is required with the operating department
The project organization (organization, contact person, position and contact information) is to be presented (including any changes) at initial project.
- Improvements in production samples (space, processes, storage, workstations, packaging ...)
The company is requested to resolve the following weaknesses:
Project teams through cross-functional teams in writing and communicated to client
Currently no Resident Engineer near Wolfsburg
No holistic resource planning across projects /
Change Management: Process standard exists, change pass transparent and complete.
Can the development partners set project structures with a responsible project leader: