Upload
nguyenkhuong
View
221
Download
1
Embed Size (px)
Citation preview
Generator RefurbishmentSwiss Chapter of IEEE 2008
Thomas Kunz / Dr. A. SchweryGrimsel, 11th of June 2008
IEEE PES Swiss Chapter - 11.06.2008- P 2
Content
• Challenges in Refurbishment
• Stator Winding Diagnosis
• Development of Insulation System
• Typical Scope / Case studies
• Introduction
IEEE PES Swiss Chapter - 11.06.2008- P 3
• Investments in renewable energy sources become more and more interesting
Introduction
• Increaser in Energy consumption
• Increase in Oil and Gas price
• Opposition against Nuclear Power
• Climate change− CO2 emission reduction
Political and economical influence factors
IEEE PES Swiss Chapter - 11.06.2008- P 4
• Old Hydro fleet− Few investments over the
last decades
• Market liberalization− Unbundling− More fluctuation in electricity
price− Change in operation mode of
power stations (intermittent operation)
• Hydro – Refurbishment, a topic in Europe
20061998 2002
Introduction
Political and economical influence factors
~150 Days
IEEE PES Swiss Chapter - 11.06.2008- P 5
Large New Mini-hydroRefurbishment
Introduction
Market, Average volume 2007-11
IEEE PES Swiss Chapter - 11.06.2008- P 6
Definition: Refurbishment, Upgrade, Repair
Time
Customer Value
Repair
RefurbishmentMaintenance
Upgrade / Uprate
Introduction
IEEE PES Swiss Chapter - 11.06.2008- P 7
Content
• Challenges in Refurbishment
• Stator Winding Diagnosis
• Development of Insulation System
• Typical Scope / Case studies
• Introduction
IEEE PES Swiss Chapter - 11.06.2008- P 8
Risks and Difficulties
• Missing or incomplete information− Incomplete set of OEM drawings
available− Not reliable or incomplete
measurements− Unknown material properties
• Old meets new− Changes in design
• Competitor design – own design− Different basic assumptions
• Physical laws can not be changed by a specification
Challenges in Refurbishment
IEEE PES Swiss Chapter - 11.06.2008- P 9
• Data collection− OEM drawings− Measurement reports− Visual inspection
• Electrical re-computation (base line)− Adjustment of experience factors− Special computations
• New electrical design− Efficiency increase− Temperature levels
Addressing the Challenges - Engineering Process
Challenges in Refurbishment
IEEE PES Swiss Chapter - 11.06.2008- P 10
• Check ventilation design − Avoid pressure drops in inactive
zones− Adjust volume flow to desired
temperature level• Mechanical validation
− Pole claws− Shaft flanges− Damper ring connections− …
Challenges in Refurbishment
Addressing the Challenges - Engineering Process
IEEE PES Swiss Chapter - 11.06.2008- P 11
Content
• Challenges in Refurbishment
• Stator Winding Diagnosis
• Development of Insulation System
• Typical Scope / Case studies
• Introduction
IEEE PES Swiss Chapter - 11.06.2008- P 12
New stator winding
• Build in a new winding in an existing stator core
• Same slot dimensions
• Improved insulation system− improved insulation material− increased filling factor
• Possibility to increase output power or reduction of copper losses
Typical scope / Case studies
IEEE PES Swiss Chapter - 11.06.2008- P 13
New stator core and winding• Improved properties of steel
laminations− Reduced iron losses
• Improved core pressing system− Avoidance of buckling
Typical scope / Case studies
IEEE PES Swiss Chapter - 11.06.2008- P 14
New stator core and winding
0 0.002 0.004 0.006 0.008 0.01 0.012 0.014 0.016 0.018-1.5
-1
-0.5
0
0.5
1
1.5x 104 line to line voltage (original and reconstructed signal) in [V] versus time in [s]
0 5 10 15 20 25 30 35 400
0.5
1
1.5fourier series coefficients in [%] thf factor in % : 1.8752
• Change of number of slots− Reduction of parasitic forces− Improved magnetic / thermal
utilisation balance− Checking of THF factor
Typical scope / Case studies
IEEE PES Swiss Chapter - 11.06.2008- P 15
Ventilation calculation of existing machine
Typical scope / Case studies
IEEE PES Swiss Chapter - 11.06.2008- P 16
• Ventilation network analyses:− Even Volume distribution on
stator core
• Coupled Temperature calculation− Uneven preheating of
cooling air axial direction
Typical scope / Case studies
Ventilation calculation of existing machine
IEEE PES Swiss Chapter - 11.06.2008- P 17
• Improved air distribution− Taking into consideration
the preheating of the cooling air
• Homogeneous temperature distribution on the active parts
• Systematic analyses of the machine is the base for the definition of an improved air flow distribution
Ventilation calculation of existing machine
Typical scope / Case studies
IEEE PES Swiss Chapter - 11.06.2008- P 18
• Located in Norway near the Glomfjord
• First operation in 1993
• Vertical shaft driven by a Francis turbine
• Stator and rotor winding directly water-cooled
• 410 MVA / 333 rpm
• 21 kV / 50 Hz
Typical scope / Case studies
IEEE PES Swiss Chapter - 11.06.2008- P 19
• Winter 2006− Several consecutive short-
circuits on the high voltage line
• Damage in August 2006− Smoke detection sensors
tripped the generator− Overheating of end
laminations
• Stator winding− Due to water-cooling only the
outer corona protection of some bars was damaged
Typical scope / Case studies
Damages
IEEE PES Swiss Chapter - 11.06.2008- P 20
• Repair of the old machine
• Computations on the stator core end laminations:− Magnetic field
distribution with 3D-FEM− Power losses
(analytical)− Temperatures (network)
PTooth
θAir
θCore
RAir
RCore
θYokeRYoke
θBar
RBar
PTooth
θAir
θCore
RAir
RCore
θYokeRYoke
θBar
RBar
Typical scope / Case studies
Actions
• Minimise standstill time: Repair completed in 95 days
IEEE PES Swiss Chapter - 11.06.2008- P 21
• Optimisation of the design:− Deeper core end stepping in radial direction− Deeper core end slitting with 3 slits per tooth
• Systematic analyses of the failure is the base for the definition of an improved new stator core end design
New design
24 mm 50 mm
Old design
h
50 mm
70 mm
Typical scope / Case studies
IEEE PES Swiss Chapter - 11.06.2008- P 22
• New Stator core and winding• New stator frame• New axial fans
− Cooling air volume reduced from 46 m3/s to 32 m3/s
− Reduced air friction and ventilation losses from 340 kW to 260 kW (measured)
• Considerable potential improvement in Ventilation losses for high speed machines
Witznau (Germany), 2 motor – generators 75 MW
Typical scope / Case studies
IEEE PES Swiss Chapter - 11.06.2008- P 23
• New Stator frame, core and winding
• Stator in two parts manufactured in workshop in Birr
• 60 MVA/ 13.8 kV/428.6 rpm
• 10 % apparent power increase
• Minimization of outage time
Soazza (Switzerland), 60 MVA
Typical scope / Case studies
IEEE PES Swiss Chapter - 11.06.2008- P 24
• Consistent and reliable set of data− Communication between
Customer and Supplier− Complete set of OEM drawings− Experienced engineers
• Short outage time− Assembly in workshop if possible− Optimized project schedule
• Quality− Calculations / Design− Manufacturing / Site− Project Management
Reliable data limits the customer risk
Refurbishment, key factors for success
IEEE PES Swiss Chapter - 11.06.2008- P 25
Content
• Challenges in Refurbishment
• Development of Insulation System
• Typical Scope / Case studies
• Introduction
• Stator Winding Diagnosis
IEEE PES Swiss Chapter - 11.06.2008- P 26
Stresses on the electrical insulation system
Thermal winding temperature, thermal cycling, etc.
Electrical grid over-voltage, discharges in voids, etc.
Ambient humidity, oil, carbon dust, etc.
Mechanical vibrations, electromagnetic forces, etc.
Change of insulating characteristic (ageing)Periodic condition assessments of the stator winding ensure a high reliability of the generating unit
During operation the stator winding is subjected to TEAM stresses
Stator Winding Diagnosis
IEEE PES Swiss Chapter - 11.06.2008- P 27
Purpose and objectives
• Failures on the stator (particularly on the winding) cause more than 40% of the outage time
• Repair work is very time consuming especially in case of an unplanned outage
Stator Winding Diagnosis
05
1015
20
2530
3540
45
Stator Rotor Bearings Excitation Components
Unavailability hours due to FaultsFrequency of faults
Failure on different components in 250 ENEL Hydro generators with an Output >20 MVA
IEEE PES Swiss Chapter - 11.06.2008- P 28
Purpose and objectives
• Guideline values for downtime after insulation break-down− Dismantling of a pole: 2 days− Dismantling of the rotor: 1-2 week− Remove and installation of top
stator bar: 3-4 days− Remove of bottom bars: 2-3 weeks
(several bars necessary, all spare parts e.g. caps, corona protection, wedging, etc. available)
Stator Winding Diagnosis
IEEE PES Swiss Chapter - 11.06.2008- P 29
Standard test program
Stator Winding Diagnosis
• Visual inspection• Charging and discharging current• Leakage current• Dielectric loss factor and
capacitance• Partial discharge• High Voltage
IEEE PES Swiss Chapter - 11.06.2008- P 30
Test of stator slot wedging system
Stator Winding Diagnosis
• The slot wedges loose their tightness during operation depending on
– Wedging system– Insulation– Operation condition
• Potential winding damages due to loose wedging system
– Vibration of stator bars leads to partial discharges between the stator winding and the stator core
– Deterioration of slot corona protection– Increased risk of stator earth fault
IEEE PES Swiss Chapter - 11.06.2008- P 31
Interval for condition assessments
Stator Winding Diagnosis
• 5 years (standard interval)– Stator winding – Wedging system
• Individual planning– Operation conditions – Current status of ageing– Design features– Environment– …
IEEE PES Swiss Chapter - 11.06.2008- P 32
Strength properties on removed bars (example)
Stator Winding Diagnosis
VET 26 kV Start 600 hours 1000 hours 1200 hours
(followed by VET 30 kV)
• Tanδ, real screen• Tapping diagram• Light-Out-Test• Currents on winding
overhang
• Tanδ, real screen• Tapping diagram• Light-Out-Test• Current on winding
overhang• PD measurement
• Tanδ, real screen• Tapping diagram• Light-Out-Test• Current on winding
overhang• PD measurement• Delamination
• Test samples– 2 aged stator bars (dismantled) – 2 spare bars without operation
IEEE PES Swiss Chapter - 11.06.2008- P 33
Results of individual measurements
Stator Winding Diagnosis
• Valuable information– The operation condition and reliability– Potential defects and weaknesses
• Further advantages for thepower producer
– Individual planning of overhaul work– Solid base for investment planning– Ensure safe operation and high reliability– Support Preventive Maintenance
IEEE PES Swiss Chapter - 11.06.2008- P 34
Closed feedback loop in development of insulation system
Stator Winding Diagnosis
Diagnostic methods;PD measurements
Endurance testing(Temperature T, el. Field E)
Endurance testing (T,E)
Material evaluation
System tests“Standard bar”
Prototype element 1:1(form wound coil, bar)
Complete machine(Manufacturing)
Endurance testingProperty testing:mech., electr., therm.
Customer feedbackSite feedback
IEEE PES Swiss Chapter - 11.06.2008- P 35
Life time assessment
Stator Winding Diagnosis
…the combination of both competences…
IEEE PES Swiss Chapter - 11.06.2008- P 36
Life time assessment
Stator Winding Diagnosis
• Customer benefits− Reliable base for planning of
investment− Risk analysis− Optimum use of existing equipment
Intervention is needed if the probability of failure is increasing super proportionally
IEEE PES Swiss Chapter - 11.06.2008- P 37
Life time prediction
Stator Winding Diagnosis
• Prerequisite for lifetime prediction− Design-, system and material know-how− Diagnosis data base with integrated
expert knowledge (historical data)− Experience about combination of
ageing factors− Test facilities, statistical methods and
optimized diagnosis strategies
Information from OEM and operation
IEEE PES Swiss Chapter - 11.06.2008- P 38
Summary
Stator Winding Diagnosis
• Powerful diagnostic methods in order to evaluate the condition of the insulation are available.
• Optimised diagnosis strategies allow to maximise the availability and reliability of the generating unit.
• So far the lifetime can not be predicted whereas the the probability for a failure can be calculated.
• Alstom continuously develop their products for winding diagnosis towards life time prediction
IEEE PES Swiss Chapter - 11.06.2008- P 39
Content
• Challenges in Refurbishment
• Typical Scope / Case studies
• Introduction
• Stator Winding Diagnosis
• Development of Main Insulation System
IEEE PES Swiss Chapter - 11.06.2008- P 40
Development of Main Insulation System
New requirements and challenges
• New market drivers− Government incentives, CO2 credits− Increase of primary energy price− Installed and planned capacity of
renewable energy plants (e.g. wind)
• New product requirements− Products offering grid stability
and higher flexibility
New operation conditions (e.g. cycling of machines)Higher loss evaluation
IEEE PES Swiss Chapter - 11.06.2008- P 41
• New market requirements− Thermal cycling up to 155°C
according to IEEE 1310-1996− Voltage endurance test at 110°C
(US, Canada)
• Performance− Increased field strength− Corona protection system− Stator slot wedging system
Driver for product development (extract)
Development of Main Insulation System
IEEE PES Swiss Chapter - 11.06.2008- P 42
• Development in two main steps− Thermal cycling up to 40 - 130°C− Thermal cycling up to 40 - 155°C
• Basic investigations− Bonding between insulation and copper− Failure mechanism and cycling criteria− Impact of manufacturing process parameters− Life endurance test after cycling
Thermal cycling of stator winding
Development of Main Insulation System
IEEE PES Swiss Chapter - 11.06.2008- P 43
• Discussion and interpretation of cycling criteria− Higher probability to fail on tip-up criteria for an insulation with a
very flat tan delta curve (typically high quality systems)
− Bars that failed on TC have pass standard VET after tests
Thermal cycling of stator winding
0
5
10
15
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.
VOLTAGE (kV)
Tg D
ELTA
x 1
0(-3
)
Initial test
Customer Req. 60% of bars
Max values for 100% of bars
After 500
Tip-
up 0
cyc
les
All bars must be below this line
60% of bars must be below this line
Start point: max: 15%o, average: 10%o
Tip-
up 5
00 c
ycle
s
Development of Main Insulation System
IEEE PES Swiss Chapter - 11.06.2008- P 44
Summary
• New operation condition for the generation units drives new requirements for the product specifications
• Alstom continuously develop the core technologies towards the new market requirements
• In order to evaluate new design criteria further a close cooperation between utilities, suppliers and technical consultants is needed
Development of Main Insulation System
www.alstom.com